Town of Haverstraw, New York Building Permit Guide

To get a building permit in Town of Haverstraw, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

The Town of Haverstraw Building Department at One Rosman Road, Garnerville, issues building permits and certificates of occupancy for Thiells, Garnerville and the rest of the town outside the Villages of Haverstraw, West Haverstraw and Pomona.

Authority: Town of Haverstraw Building DepartmentCode: 2025 Uniform Code, Town Code Ch. 84Phone: 845-942-3710
Authority
Town Building DepartmentTown Hall, One Rosman Road, Garnerville
Apply
Paper applicationNotarized or staff-witnessed affidavit
House fee
$250 + $150 C.O.Plus $10 per $1,000 over $15,000
Permit life
12 monthsOne-year extension $200

For land in the Town of Haverstraw outside its three incorporated villages, building permits come from the town Building Department at Town Hall, One Rosman Road, Garnerville (845-942-3710). You file the town’s paper application with two sets of plans, an owner’s affidavit and each contractor’s Rockland County license and insurance. Under the fee chapter of the Town Code, a single-family house starts at $250 plus $150 for the certificate of occupancy, and a permit lasts 12 months.

What requires a building permit in Haverstraw?

Section 84-4 of the Town Code requires a permit for any work that must meet the Uniform Code or the Energy Code: building, enlarging, altering, improving, moving or demolishing a building or structure, and installing a wood stove, other solid-fuel heater, chimney or flue in a home.

Permit needed

  • New houses, additions and alterations, including finished basements
  • Decks and roof-mounted solar
  • Permanently installed pools deeper than 24 inches, and their barrier fences
  • Wood stoves, fireplaces, chimneys and flues
  • Re-roofing and electric service, meter pan or riser upgrades on a house (flat $150 permits)
  • Demolition, signs and changes of use
  • Commercial, industrial and multi-family work

No building permit

  • One-story sheds and playhouses under 144 sq ft at a one- or two-family home
  • Swings and playground equipment
  • Pools under 24 inches deep set entirely above ground
  • Fences that are not part of a pool enclosure
  • Retaining walls that support no surcharge and impound no Class I, II or IIIA liquids
  • Painting, flooring, tiling and similar finish work; like-for-like equipment
  • Repairs that leave structure, exits, building systems and fire protection untouched

One point to raise at the counter: the fee chapter still lists a “fences and solid wall” fee ($100 or $125) and a certificate of compliance for fences, although Section 84-4 exempts fences that do not enclose a pool. Both are adopted law, so ask first. Zoning still governs every fence: a solid fence or wall up to 4½ feet, or an open fence up to 6 feet, is allowed on a lot line; a taller solid fence or wall must be set back two-thirds of its height, and front-yard fences over 4 feet are not allowed on residential lots.

What the town decides and what the state sets

Chapter 84, adopted by Local Law 1 of 2007, puts the state Uniform Code and Energy Code into effect, lists the exemptions above, sets the 12-month permit term and leaves fees to the Town Board. Zoning (Chapter 167), flood damage prevention (Chapter 87), freshwater wetlands (Chapter 90) and pools (Chapter 150) are local rules.

Town of Haverstraw building department: who handles permitting

The Building Department issues building permits, certificates of occupancy and operating permits and carries out construction and fire-safety inspections; George T. Behn Jr. is the Building Inspector. Fire, burning and sprinkler questions go to the same office through the Town Hall line, 845-429-2200.

Short on time to read all of this?

Get a free quote →
Who issues permits in the Town of Haverstraw
AreaOffice and contact
Town outside the villages (Thiells, Garnerville and other hamlets)Town Building Department, Town Hall, One Rosman Road, Garnerville, NY 10923; 845-942-3710; fax 845-786-7647; buildingdept@townofhaverstraw.org
Village of Haverstraw (12,791 residents)Village Building Department, 40 New Main Street, Haverstraw, NY 10927; 845-429-0300; Monday to Thursday 9 am to 5 pm, Friday 8 am to 5 pm, first Thursday open to 7:30 pm
Village of West Haverstraw (11,025)Village Building Department, 130 Samsondale Avenue, West Haverstraw, NY 10993; 845-947-2800; Monday to Friday 8:30 am to 4:30 pm
Village of Pomona, Haverstraw part (2,344)Village Building Department, Village Hall, 100 Ladentown Road, Pomona, NY 10970; 845-354-0545, option 1; Monday to Friday 9 am to 4 pm

Each village enforces the Uniform Code and its own zoning. The Village of Haverstraw handles its Planning, Zoning and Architectural Review Board paperwork at the building counter, permits pools over 18 inches and all sheds, and issues permits good for six months with up to three renewals. West Haverstraw requires permits for fences, sheds over 144 sq ft and window replacements, asks for county-licensed contractors, charges $115 for a certificate of occupancy and approves complete applications within seven business days. Pomona, which lies partly in the Town of Ramapo, books inspections through its building clerk.

Haverstraw permit types and filing rules

Residential permits

Every project uses the same Application for Building Permit, which covers use, erection, alteration, repair, extension, removal, demolition, occupancy and conversion. The top section asks for the tax section, block and lot, the hamlet and the zoning district (staff will help with the tax lot and zone). You then describe the project, give the present use, state the entire cost of labor and materials and name the architect or engineer (with New York license number), the builder, the plumber and the electrician (each with a Rockland County license number). If the Town Board, Planning Board or Zoning Board granted a special permit or variance, its date and decision number go on the form.

The owner or the owner’s agent signs an affidavit on the back, which must be notarized or signed in front of Building Department staff; an incomplete affidavit means the application is refused. A homeowner acting as contractor attaches the coverage page of the homeowner’s insurance policy. Each contractor, electrician, plumber or HVAC installer supplies a copy of the Rockland County license and certificates for disability, liability and workers’ compensation insurance naming the Town of Haverstraw, 1 Rosman Road, Garnerville, as certificate holder. Chapter 84 asks for two sets of construction documents, sealed by a New York architect or engineer where the Education Law requires it, and a site plan showing buildings, any well or septic system and distances to lot lines.

Not sure this scope needs a permit?

Get a free quote →

A permanently installed pool deeper than 24 inches needs a plot plan, and Chapter 150 requires a barrier at least 4 feet high with no more than 2 inches of clearance at the ground, picket gaps of 4 inches or less and self-closing, self-latching gates.

Commercial permits

Commercial, industrial and multi-family work uses the same form. Within three business days of finding a commercial, industrial or multiple-dwelling application otherwise compliant, the Building Inspector sends it to the Architectural Review Board, which has 30 days to act before the application counts as approved. Assembly spaces for 100 or more people also need a town operating permit.

What comes before the building permit

  • Zoning Board of Appeals for variances, special permits and interpretations: $250 for a home, $300 for vacant land, $400 for commercial property, plus a $50 land-use fee.
  • Planning Board site plan review: $50 informal presentation, $50 sketch, then $100 plus $50 per 1,000 sq ft of floor area at the preliminary and final stages.
  • Architectural Review Board for commercial, industrial and multi-family buildings and subdivisions of three or more lots ($50 per house; commercial fees by floor area).
  • Land disturbance under Chapter 140: from $350 for residential disturbance up to half an acre.
  • Town roads: a driveway opening permit is free.
  • Septic: the Rockland County Department of Health must approve new and repaired septic systems.
  • Flood zones: the town is in the National Flood Insurance Program (current map dated March 3, 2014), and a certificate of occupancy can require flood hazard certifications.

Haverstraw building permit fees

Chapter 84 says fees are set by Town Board resolution; the amounts in force are the rows of Chapter 79 of the Town Code, last amended for building permits by Local Law 2 of 2013, with the re-roof and electric-service rows added by Local Law 4 of 2016. The Town Board’s 2026 minutes through September show no new fee schedule.

Rather talk it over?

Call 1-855-478-4290 →
Town of Haverstraw building fees (Town Code Chapter 79)
WorkFee
Single-family house$250, plus $150 for the certificate of occupancy; over $15,000 of cost, add $10 per further $1,000
Alterations and signs$100 up to $1,000, plus $150 for the certificate; add $10 per further $1,000
Multi-family, condominium, commercial, industrial$300 up to $15,000; add $25 per further $1,000; C.O. $150 per unit
In-ground pool$100 up to $1,000 plus $10 per further $1,000; C.O. $150
Above-ground pool$100; C.O. $150
Residential re-roof$150, including the certificate of compliance
Residential electric service, meter pan or riser upgrade$150, including the certificate of compliance
Demolition$200 for the first $1,000 of removal cost, $15 per further $1,000
Fences and solid walls$100 ($1,000 to $10,000) or $125; certificate of compliance $150
Reinspection after a failed or missed inspection$100
One-year permit extension$200 (after 2 years a new permit is needed)
Copy of a certificate of occupancy or violation search$150
Added to every application / certificate$30 per building permit application; $20 per C.O.; $20 per certificate of compliance; $10 per demolition

Read as written, the house row charges $250 for a project costing $1,000 to $15,000 and adds $10 for each further $1,000 or fraction above $15,000, but the code gives no example, so ask the department to price a new home before you budget.

Trade permits and who may pull them

Electrical. Chapter 76, the town’s Electrical Code, makes it a violation to install or alter wiring before an application for inspection has been filed with the New York Board of Fire Underwriters or another inspection agency the town approves, and a system may not be connected to power until that agency issues a temporary certificate or certificate of compliance. The agency reports to the Building Inspector, and its fees are paid by the owner or contractor.

Licenses. Rockland County, not the town, licenses the trades. Its Consumer Protection office issues master electrician licenses (Chapter 250), plumbing, heating, air-conditioning, sheet metal, refrigeration and fire-protection contractor licenses (Chapter 319) and home improvement licenses under a new Chapter 286, adopted by the County Legislature on April 14, 2026 and in force since May 14, 2026. The home improvement law covers repair and remodeling work on homes of up to three units and does not reach plumbing, electrical or architectural work, which have their own licenses. The town form asks for each contractor’s county license number, and the county office (50 Sanatorium Road, Building A, Pomona; 845-364-3901) keeps a public license lookup.

Rather not deal with the building department?

Get a free quote →

Insurance. Every contractor’s workers’ compensation, disability and liability certificates must name the town as holder; an owner doing the work files the declarations page of the homeowner’s policy.

Septic and sewers. The Rockland County Department of Health reviews and approves septic plans drawn by a licensed engineer or architect, inspects the installation and must approve every repair (845-364-2656). Sewer service and connections follow Chapter 137 of the Town Code.

How to apply for a Haverstraw building permit

1. Confirm the parcel is town land

Look at the tax bill: Haverstraw village, West Haverstraw and Pomona parcels go to the village office.

2. Settle zoning and board approvals

Get any variance, site plan, architectural review or county septic approval first and note the decision number.

3. Fill in the application

Give the tax lot, hamlet, project description, full labor-and-materials cost and every professional and license number.

4. Sign the affidavit

Have it notarized, or sign it at the counter in front of Building Department staff.

5. Attach plans, licenses and insurance

Two sets of construction documents, a site plan, county licenses and insurance certificates naming the town.

6. Pay and post the permit

Pay the permit fee at submission and keep the permit visible on site until the work is finished.

Review, corrections and what causes delay

The town does not publish a review time. Common holdups are an incomplete affidavit, which stops an application at the counter, missing Rockland County licenses or insurance certificates that do not name the town, and projects that need a Zoning Board, Planning Board or Architectural Review Board decision first. A permit expires 12 months after it is issued; an extension costs $200 for one more year, and after two years a new permit is required.

Haverstraw inspections and certificates

Call the Building Department at 845-942-3710 when each stage is ready. Work must stay exposed until it is inspected and accepted. Section 84-5 lists the stages the town inspects where they apply: the site before the permit is issued, footings and foundation, slab preparation, framing, building systems including underground and rough-in work, fire-resistant construction and penetrations, solid-fuel appliances and chimneys, Energy Code compliance and a final inspection. A failed or missed inspection costs $100 to repeat.

Every job done under a building permit ends with a certificate of occupancy or certificate of compliance, and a change of use also needs one. Before issuing it, the Building Inspector can require a special-inspection report and flood hazard certifications. A temporary certificate is possible only where the occupied part is safe.

Want this handled start to finish?

Get a free quote →

New York building code

New York builds on one statewide code, the Uniform Code, outside New York City; the 2025 edition and 2025 Energy Code took effect on 31 December 2025 (the all-electric provisions remain suspended by court order). Cities, towns and villages administer it, and local standards stricter than the code need Code Council approval. The Uniform Code in New York

Town of Haverstraw permit FAQ

I live in Garnerville or Thiells. Does the town issue my permit?

Yes, unless the parcel is inside the Village of Haverstraw, West Haverstraw or Pomona; Garnerville and Thiells are unincorporated hamlets served by the town Building Department.

Do I need a permit for a shed in the Town of Haverstraw?

Not for a one-story shed or playhouse under 144 square feet at a one- or two-family home. Larger sheds need a permit and must meet zoning setbacks.

Do I need a permit for a fence?

Section 84-4 exempts fences that are not part of a pool enclosure, but the fee chapter still lists a fence fee, so ask the department about your fence. Solid fences over 4½ feet must be set back from the lot line.

Can I do the work myself as a homeowner?

The town accepts an owner acting as contractor with a copy of the homeowner’s insurance coverage page. Electrical, plumbing and heating contractors you hire need Rockland County licenses.

Who inspects electrical work?

The New York Board of Fire Underwriters or another inspection agency the town approves, filed before wiring starts; the new wiring may not be connected to power until that agency issues its certificate.

How long is a Haverstraw building permit valid?

Twelve months from issue. A one-year extension costs $200, and after two years you need a new permit.

Do I need a permit for an above-ground pool?

Yes, unless it is under 24 inches deep and sits entirely above ground. The fee is $100 plus $150 for the certificate, and the pool needs a 4-foot barrier or guard rails at least 2½ feet high on its walls.

Permit search and official resources

The town has no online permit search. Under Section 84-13 the department’s permits, certificates and inspection records are public records: file the Town Clerk’s FOIL application to see them, or pay $150 for a copy of a certificate of occupancy or a violation search.

Inspections are where schedules slip.

Get a free quote →

Simplify Town of Haverstraw permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in New York. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Town of Haverstraw sooner?

Let Alliance prepare, file, and track your Town of Haverstraw permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Town of Haverstraw permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.