Town of Clarkstown, New York Building Permit Guide

The Town of Clarkstown Building Department, on the lower level of Town Hall in New City, issues building permits priced by the cost of the job; plumbers and electricians are licensed by Rockland County.

Authority: Clarkstown Building DepartmentOffice: Town Hall, Room 101, New CityPhone: (845) 639-2100
Building Department
(845) 639-21009:00 a.m. to 5:00 p.m., Mon-Fri
Building permit
$150.00 first $1,000Then $18.00 per $1,000
Fences
No permitZoning limits apply
Trade licences
Rockland CountyPlumbers and electricians

Building permits in the Town of Clarkstown are issued by the Building Department, on the lower level of Clarkstown Town Hall, Room 101, 10 Maple Ave., New City, NY. The office is open from 9:00 a.m. to 5:00 p.m., Monday through Friday.

This guide covers the Clarkstown Building Department, its fees and certificates of occupancy, and the Town offices for planning, engineering and road openings. The Town’s building download and highway permit pages could not be read, so the forms and the current Town Board fee resolution were not checked; ask the Building Department for them.

What requires a building permit in the Town of Clarkstown?

A permit is needed to install any permanent or temporary swimming pool, in-ground or above-ground over twenty-four (24) inches deep, and for decks, sheds, heating units and wood stoves. When the application is approved, a permit placard is issued and must be displayed on the job until the work is finished.

Clarkstown does not require fence permits, but the zoning ordinance regulates fences: solid fences and walls cannot exceed 4 1/2 feet along any lot line, and fences cannot exceed six feet unless set back 2/3 of their height from the lot line.

Short on time to read all of this?

Get a free quote →

New York builds on one statewide code, the Uniform Code, outside New York City; the 2025 edition and 2025 Energy Code took effect on 31 December 2025 (the all-electric provisions remain suspended by court order). Cities, towns and villages administer it, and local standards stricter than the code need Code Council approval. The Uniform Code in New York

Who handles permitting in the Town of Clarkstown?

Town of Clarkstown permit offices
OfficeHandlesContact
Building DepartmentBuilding permits, certificates of occupancy, fire permits; Town Hall, Room 101, 10 Maple Ave., New City(845) 639-2100
Planning DepartmentPlanning Board, Zoning Board of Appeals (ZBA), Technical Advisory Committee and Antenna Advisory Review Board applications; 10 Maple Ave.; 9:00 am - 5:00 pm(845) 639-2070
Department of Engineering and Facilities ManagementSite work under a building permit; land disturbance, tree removal and Floodplain Development permits(845) 639-2111
Highway DepartmentRoad opening permits; 12 Seeger Drive, Nanuet, NY 10954; 8:00 am - 4:00 pm(845) 623-7500

Road openings and fire permits in the Town of Clarkstown

Road opening permits

Any opening of a Town street, road or sidewalk, including a driveway connection, needs a road opening (excavation) permit from the Superintendent of Highways. Applicants must give utilities at least 72 hours’ written notice and file proof of that notice at least 48 hours before work starts.

Not sure this scope needs a permit?

Get a free quote →

Annual fire permits

Under Town Code 143-11, certain occupancies, such as business, mercantile, places of assembly, multiple residences and garages, need an annual Fire Permit, applied for during January for the coming year. Forms and fees are available at (845) 639-2100.

Town of Clarkstown permit costs and fees

Fees are based on the dollar cost of the job: $150.00 for the first $1,000 and $18.00 for each additional $1,000 of cost, or part of it.

Plumbing and electrical work in the Town of Clarkstown

Plumbing work that needs a permit must be done by plumbers licensed and registered by the County of Rockland; an owner-occupant of a single-family home may do their own plumbing with a permit. Electrical work must be done by, or under the supervision of, an electrician licensed by Rockland County, and inspected by an approved third-party electrical inspection agency.

Where a municipality issues separate trade permits, the work is done under whatever electrical or plumbing licence that city, town or county requires; many places license neither trade. Trade licences in New York

Rather talk it over?

Call 1-855-478-4290 →

How to get a building permit in the Town of Clarkstown

1. Zoning review

Submit three copies of a plot plan drawn to scale, showing the lot, all structures, setbacks and sanitary and storm sewer provisions.

2. Plan review

Submit two sets of construction drawings, drawn to scale, for review against the New York State Building Construction Code.

3. Site work and road openings

Land disturbance, tree removal and floodplain work go to Engineering; a driveway connection needs the Superintendent of Highways’ permit.

4. Pay and post the placard

Pay the cost-based fee, then keep the permit placard on display until the work is finished.

Every permit carries an expiration date set by the Town of Clarkstown, which may void a permit if work does not start in time; confirm the expiry on phased or delayed work. Permit validity in New York

Rather not deal with the building department?

Get a free quote →

Inspections and certificates of occupancy in the Town of Clarkstown

Electrical inspections are applied for through an approved third-party electrical inspection agency. For a certificate of occupancy you need a valid building permit, the final electrical certificate, three copies of the final survey, testing agency reports, certification by the general contractor and a final plumbing inspection. A temporary certificate of occupancy expires in 90 days.

For commercial certificates, the fire inspectors require fire alarm connection to the Rockland County Fire Control Center (44Control), fire alarm and sprinkler certifications, and a Knox box.

Official Town of Clarkstown permitting resources

These are the primary sources behind this guide. Codes, fee schedules and procedures change — confirm the position for your filing date.

Want this handled start to finish?

Get a free quote →

Frequently asked questions

Does a fence need a permit in the Town of Clarkstown?

No. Clarkstown does not require fence permits, but solid fences and walls cannot exceed 4 1/2 feet along any lot line.

Who licenses plumbers working in Clarkstown?

The County of Rockland. Plumbing work that needs a permit must be done by a plumber licensed and registered by the County, unless an owner-occupant of a single-family home does it with a permit.

How long does a temporary certificate of occupancy last in Clarkstown?

It expires in 90 days.

Simplify Town of Clarkstown permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Inspections are where schedules slip.

Get a free quote →
  • Confirm the Town office for the parcel and the zoning, highway or fire approvals that go with the permit
  • Prepare the application, surveys and plans and file them through the Town’s portal or counter
  • Schedule the Town’s inspections and follow the permit through to the certificate of occupancy

Alliance Permitting is a permit documentation and submission company in New York. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Town of Clarkstown sooner?

Let Alliance prepare, file, and track your Town of Clarkstown permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Town of Clarkstown permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.