Hanover, New Hampshire Building Permit Guide

Hanover’s Planning, Zoning & Codes Department at Town Hall issues combined zoning and building permits for the town, and every building permit is applied for online.

Authority: Hanover Planning, Zoning & CodesCode: 2024 IBC/IRC, 2018 IECC, 2023 NECPhone: 603-643-0708
Authority
Planning, Zoning & Codes41 South Main Street, 603-643-0708
Apply / file
Online permit portalOne application covers all trades
Home fee
$100 + $0.75 per sq ftFY2027 schedule, adopted June 15, 2026
Review deadline
30 days60 days for commercial and multi-family

In Hanover, the town’s Planning, Zoning & Codes Department issues building permits, and one online application covers zoning, building and every trade for the project. Under the FY2027 rate schedule adopted on June 15, 2026, new living space in a one- or two-family home costs $100 plus $0.75 per square foot, with a $150 minimum, and the town has 30 days to review a complete one- or two-family application.

What requires a permit in Hanover?

Before any building or structure is built or altered in Hanover, the property owner must get a building permit from the Planning, Zoning & Codes office. Hanover permits by building type rather than by trade, so electrical, plumbing and mechanical work is listed on the same application as the building work.

Online permit applications

  • One- or two-family projects
  • Commercial, multi-family, condominium and other projects
  • Amendments to approved zoning and building permits
  • Blanket permits
  • Demolition of an entire structure
  • Installing LP gas or oil-burning equipment
  • Septic designs
  • Signs and awnings
  • Temporary construction controls
  • Wetland administrative permits

No building permit (zoning may still apply)

  • One-story detached accessory structures up to 400 sq ft, other than storm shelters
  • Retaining walls up to 4 feet, unless supporting a surcharge
  • Detached decks up to 200 sq ft and 30 inches above grade that do not serve a required exit
  • Pools less than 24 inches deep
  • Painting, tiling, carpeting, cabinets, counters and similar finish work
  • Re-roofing with the same materials

The permit application covers both zoning and building, and the town stresses that work exempt from a building permit is not exempt from zoning. A small shed, for example, may still need a zoning permit ($50 when only zoning applies).

Who issues building permits in Hanover?

The Town of Hanover’s Planning, Zoning & Codes Department reviews and issues zoning and building permits for the whole town and keeps the records of all building inspections; Grafton County does not issue building permits. Ryan Borkowski is the Building Official and Health Officer, and Jennifer Murray is the Director of Planning, Zoning & Codes.

Short on time to read all of this?

Get a free quote →
Hanover Planning, Zoning & Codes contacts
DetailInformation
OfficeTown Hall, 41 South Main Street, Hanover, NH 03755 (mail: PO Box 483)
Phone603-643-0708
Building OfficialRyan Borkowski, 603-640-3216
Deputy Building Official603-640-3234
HoursMonday to Friday 8:30 a.m. to 4:30 p.m.
ApplyTown online permit portal (iWorQ)

The town’s 2023 Building Code Adopting Ordinance, which sets local administration such as blanket permits, amendments and appeals, is being updated to reflect recent changes in state law.

Applying in Hanover’s online portal

Hanover requires online permitting for building work. Pick the application for the building type (one- or two-family, or commercial, multi-family and condominium), then fill in each section; every section has a No or N/A option, and the page times out if left idle too long. The town’s 2026 companion guide walks through the one- and two-family form field by field.

  • Property and owner: find the parcel by address or tax map number; the owner’s name must match the tax records on the town’s GIS map.
  • Contractor: only contractors registered in the town’s system appear; otherwise choose “Property Owner”.
  • Fire Department review: say whether the job adds or changes sprinklers, other fire suppression or fire alarm devices.
  • Deferred submissions: list items to be sent later; structural elements cannot be deferred, and deferred work cannot start until its plans are approved.
  • Trades: electrical and plumbing work lists the responsible master licence.
  • Energy code: upload the New Hampshire EC-1 form for projects it applies to.

Separate online applications cover amendments to an approved permit (needed for any change in building location, footprint, structure, exits, life safety or significant trade changes), demolition, septic design, signs and awnings, and temporary construction controls. Accessory dwelling unit applications are still filed on paper. Building and zoning permit applications received since May 2020 can be searched in the town’s online permit database.

Blanket permits are limited to owners who employ licensed architectural or engineering staff and maintenance staff: one permit, filed monthly, covers small jobs such as up to 10 device or outlet changes, up to 6 new drainage fixture units, mechanical work for up to 300 sq ft or general construction up to 500 sq ft with no structural or life safety work.

Not sure this scope needs a permit?

Get a free quote →

Hanover building permit fees (FY2027)

Hanover’s Selectboard sets fees in the annual Schedule of Rates and Fees. The FY2027 schedule, adopted on June 15, 2026, covers July 1, 2026 to June 30, 2027, and it raised the minimum permit fee from $100 to $150.

Hanover zoning and building permit fees, FY2027
PermitFee
One- or two-family: finished dwellings and additions$100 + $0.75 per sq ft
One- or two-family: renovations and alterations$100 + $0.50 per sq ft
One- or two-family: non-habitable structures (porch, garage, shed, fence, pool, retaining wall and similar)$100 + $0.50 per sq ft
Commercial, institutional and multi-family$100 + $6 per $1,000 of construction cost
Minimum permit fee (all types)$150
Zoning permit only$50
Moving or demolition$150
Sign, awning or canopy$100
Septic design review (needed before NHDES review)$100
Driveway permit, zoning review$120
Driveway permit, Public Works review$120
Re-inspection or additional inspection$75 each
Revision plan review, partial submissions, deferred trade submissions$75 per hour, 1-hour minimum
Permit extension$100
Starting work without permits or approvals$300 administrative fee

For example, a new house with 2,000 sq ft of finished dwelling space costs $100 plus 2,000 × $0.75, or $1,600, for the building permit. Other FY2027 charges include $100 for a temporary construction controls permit, $100 per project for a blanket permit, $150 to reinstate a suspended building permit (reinstating the zoning permit is a separate, additional fee) and $150 to resubmit a rejected application (after six months a new application is needed). If the applicant asks for expedited review, or the Building Official sends a project out for third-party review, the applicant also pays the consultant’s cost.

Rather talk it over?

Call 1-855-478-4290 →

Trade work and fire permits in Hanover

Because Hanover permits by building type, the electrical, plumbing and mechanical work for a project goes on the same building permit application, with the responsible master licence listed. For one- and two-family projects the town may ask for electrical plans showing lights, switches, receptacles, services and feeders, plumbing fixtures on the floor plans with a riser diagram of drains and vents, and heating system data with venting details; small kitchen and bathroom renovations can often use a written description of the work instead. Commercial and multi-family projects often need plans from a registered architect or engineer, covering architectural, structural, mechanical, electrical, fire alarm, fire suppression and site work.

The Hanover Fire Department issues its own permits for installing gas or oil appliances: $85 for a stand-alone installation or replacement, $25 for each additional appliance and $120 for a re-inspection under FY2027 rates. LP gas and oil-burning equipment applications are filed in the same online portal, and the Fire Department publishes sprinkler regulations.

What to submit for a Hanover home project

Plans

  • Floor plans and elevations (they need not be drawn by an architect)
  • Site plan with setbacks, driveways, building footprints and wetlands, with a north arrow and scale if possible
  • Electrical, plumbing and heating information as described above
  • Fireplace and chimney details
  • Smoke detector locations and second means of escape

Approvals and forms

  • Approved driveway permit
  • Approved septic system permit and a plan showing the well location, where they apply
  • New Hampshire energy code compliance (EC-1 form): insulation, window values and window area
  • Fire Department review answers for sprinklers and alarms

Rather not deal with the building department?

Get a free quote →

How to get a building permit in Hanover

1. Check zoning first

Confirm setbacks and uses in the Zoning Ordinance; exempt work still needs zoning approval, and some projects need the Planning Board or Zoning Board first.

2. Get driveway, septic and utility approvals

Driveway permits from Public Works, septic design review by the town before review by the NHDES Subsurface Systems Bureau, and Water Department approval for a new or modified service.

3. Prepare plans

Gather the floor plans, elevations, site plan, trade information and EC-1 form.

4. Apply online

Choose the one- or two-family or the commercial application in the portal and complete every section.

5. Review and permit card

The town has 30 days for a complete one- or two-family application and 60 days for commercial, multi-family and condominium projects. Post the permit card where it can be seen from the road.

6. Inspections and completion

Book each inspection with the Planning, Zoning & Codes office before work is covered, then get the Certificate of Occupancy/Completion before using the building.

Hanover inspections and occupancy

Inspections and appointments are booked with the Planning, Zoning & Codes office by phone (603-643-0708) or email. The owner or the owner’s agent must book an inspection before any work is covered, and must uncover work on request if it was covered first. Missing a scheduled inspection can bring a fee, and if work goes ahead without the required inspections the Building Official suspends the permit until it is reinstated ($150, plus a separate fee to reinstate the zoning permit).

A building with a permit may not be used or occupied until the department issues a Certificate of Occupancy/Completion, which also requires compliance with zoning, subdivision and site plan approvals. A partial or temporary certificate can be issued for up to 30 days, and a life safety inspection to allow occupancy before the full certificate costs $100, paid before it is scheduled. Re-inspections and additional inspections are $75 each.

Local Hanover details

Combined zoning and building review: one application covers both, so exempt building work and changes to an approved permit still go through the department.

Want this handled start to finish?

Get a free quote →

Public hearings: from July 1, 2026, the notification fee for applications that need abutter notices is $36.04 per name on the notification list.

Other town permits: Public Works issues excavation and curb cut permits, the Water Department handles new or modified services, and the town’s noise ordinance can limit construction days and times.

Permit records: the online permit database shows building and zoning applications received from May 2020; for older files, email the Planning Department.

New Hampshire building code

Every building in New Hampshire must meet the state building and fire codes (the 2024 codes since July 2026). Only towns that have adopted an enforcement mechanism issue local permits, and any local amendment must be administrative and confirmed by the state. New Hampshire rules

Hanover building permit FAQ

Who issues building permits in Hanover, NH?

The Town of Hanover Planning, Zoning & Codes Department at Town Hall, 41 South Main Street (603-643-0708). Ryan Borkowski is the Building Official.

How much does a building permit cost in Hanover?

For a one- or two-family home, $100 plus $0.75 per sq ft of finished dwelling space or additions, or $0.50 per sq ft for renovations and non-habitable structures, with a $150 minimum. Commercial and multi-family work is $100 plus $6 per $1,000 of construction cost.

Do I need separate electrical and plumbing permits in Hanover?

No. Hanover permits by building type, so all trades go on one application; gas and oil appliance installations also need a Fire Department permit.

Do I need a permit for a shed or deck?

A detached one-story shed up to 400 sq ft, or a detached deck up to 200 sq ft and 30 inches high that does not serve a required exit, needs no building permit, but zoning rules still apply and a zoning permit may be required.

How long does Hanover take to review a permit?

Up to 30 days for a complete one- or two-family application and 60 days for commercial, multi-family and condominium projects.

Which building code does Hanover enforce?

New Hampshire’s State Building Code, which moved to the 2024 International Building and Residential Codes on July 1, 2026 alongside the 2018 energy code and 2023 National Electrical Code; until December 31, 2026 an applicant may file under the 2021 code set instead, without mixing the two.

Inspections are where schedules slip.

Get a free quote →

Official Hanover permitting resources

Simplify Hanover permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in New Hampshire. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Hanover sooner?

Let Alliance prepare, file, and track your Hanover permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Hanover permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.