Durham, New Hampshire Building Permit Guide

Durham’s Building Inspector at 8 Newmarket Road issues building and trade permits for the town, and the permit fee is paid up front, before plan review begins.

Authority: Town of Durham Building InspectorCode: 2024 IBC/IRC, 2018 IECC, 2023 NECPhone: 603-868-8064
Authority
Durham Building Inspector8 Newmarket Road, 603-868-8064
Review time
About 7–10 daysUp to 2 weeks in summer, 4 for large homes
Inspections
Tuesdays and Thursdays8 a.m. to 4 p.m., first come, first served
Home fee
$50 + $7 per $1,000Effective December 16, 2025

Durham’s Building Inspector (Code Enforcement, 8 Newmarket Road, 603-868-8064) issues building, electrical, plumbing, mechanical and fire protection permits for the town. A one- or two-family project pays $50 plus $7 per $1,000 of construction cost, due before plan review starts, and a complete application is generally approved in a week to ten days.

What requires a building permit in Durham?

Durham requires a building permit for most construction and renovation work. The building application also covers fire alarm and fire sprinkler systems, and separate permits are needed for electrical, plumbing, heating, ventilating or air conditioning work, signs and driveway access.

Permit needed

  • New single-family, two-family and multi-family homes
  • Residential additions and renovations, re-roofing and window replacement
  • Accessory apartments and home occupations
  • New commercial buildings, additions, renovations and tenant fit-outs
  • Demolition
  • Electrical, plumbing, gas, mechanical and septic work
  • Fire alarm and fire sprinkler systems
  • Signs, sidewalk cafes and outdoor displays
  • Short-term or overnight rentals of less than 30 days (Zoning Administrator)

No building permit (zoning review still needed)

  • Up to two accessory buildings per lot for single-family use, such as sheds
  • Each no more than 200 sq ft and 14 feet high
  • No water, sewer or heat unless approved by special exception
  • Not in front of the house, at least 10 feet from property lines and 20 feet from a house on an abutting lot

A shed that meets those limits still needs a Building Permit Application so the town can check the zoning setbacks, at no charge.

Who issues building permits in Durham?

The Town of Durham’s Building Inspector issues building permits for the town and carries out every inspection except electrical, which is done by Durham’s Electrical Inspector. Audrey Cline, CBO, is the Building Inspector. Strafford County does not issue building permits.

Durham Building office contacts
DetailInformation
Office8 Newmarket Road, Durham, NH 03824
Phone603-868-8064 (also 603-868-1858)
HoursMonday to Friday 8:00 a.m. to 5:00 p.m., closed 1:00 to 2:00 p.m.
Driveway permitsDepartment of Public Works
Short-term rentalsZoning Administrator

Short on time to read all of this?

Get a free quote →

Durham permit applications

Durham posts its applications as downloadable forms on the Code Enforcement Permit Application Forms page:

  • Building Permit Application (updated August 1, 2025), also used for fire alarm (IBC Section 907) and fire sprinkler (IBC Section 903) permits. It splits the cost of the work into building, electrical, plumbing, mechanical and other, and includes an Owner’s Statement of Understanding on parking limits and short-term rentals.
  • Electrical Permit Application, signed by a master electrician; a journeyman needs a letter from the master electrician to pull a permit.
  • Plumbing, Gas, Mechanical, Fire and Septic Permit Application (updated December 17, 2025).
  • Residential Energy Code Application and Checklist.
  • Demolition, Driveway and Change in Commercial Tenant applications.
  • Transfer of Building Permit: an issued permit cannot be assigned, so a new owner uses this form.
  • Home Occupation, Short-Term Rental, Sign, Sidewalk Cafe, Outdoor Display, Special Events and Street Vending applications.

Electrical, plumbing and mechanical permits must be taken out by New Hampshire master-licensed contractors, or by the owner when the owner does the work.

Durham building permit fees

Durham’s building construction permit and inspection fees took effect on December 16, 2025. The permit fee is paid before the permit is issued and before plan review begins, and the town asks applicants not to round the fee up.

Durham permit and inspection fees (effective December 16, 2025)
PermitFee
Building, one- and two-family residential$50 + $7 per $1,000 of construction cost
Building, multi-family and commercial$100 + $10 per $1,000 of construction cost
Electrical, plumbing, mechanical, fire suppression or fire detection, residential$50 + $7 per $1,000 of construction cost
Electrical, plumbing, mechanical, fire suppression or fire detection, commercial$100 + $10 per $1,000 of construction cost
Demolition, residential or commercial$50
Septic system (test pit inspection, plan review and final inspection)$100 per system
Sign, including sidewalk signs$25 per sign
Driveway, residential (Public Works)$100
Driveway, commercial or industrialActual review cost, $150 minimum
Re-inspection after a failed inspectionFirst follow-up free, then $50 each
Inspection outside 8:00 a.m.–5:00 p.m. weekdays$75 per hour; weekends $200 minimum
Work done without a permit$100 or 200% of the permit fee, whichever is greater
Fire Department fee, on top of the trade permitOil tank, oil burner, LP tank, LP or natural gas appliance, generator: $50 each; wood or pellet stove: $25 each

Not sure this scope needs a permit?

Get a free quote →

LP and natural gas piping carries neither the Building Department fee nor a Fire Department fee. For example, a $200,000 addition to a single-family home costs $50 plus 200 × $7, or $1,450, for the building permit. If the homeowner supplies the labor, the fee is figured on twice the cost of the materials; where the owner and the Building Official disagree, the Building Official uses the International Code Council’s Building Valuation Data. If a permit is withdrawn, the town keeps 20% of the fee.

School impact fee: a new single-family house pays $3,699. The fee applies to new dwelling units on vacant lots or where the number of units on a lot increases, is assessed automatically when the building permit is issued and must be paid before the Certificate of Occupancy; fees for other housing types come from the Administrative Assistant.

Electrical, plumbing, gas and fire permits in Durham

Trade work is permitted through Durham’s own applications. The electrical permit is inspected by the town’s Electrical Inspector, and a temporary service is listed on the electrical form at $10. Plumbing, gas, mechanical, fire and septic work share one application, and the town publishes a separate plumbing ordinance for properties on town water and an electrical ordinance for Durham.

Fire alarm and sprinkler systems are permitted on the building permit application; a sprinkled structure needs approval from both the Department of Public Works and the Durham Fire Department. Adding bedrooms, bathrooms or kitchens also needs Public Works approval.

Septic systems are handled in steps: the town inspects the test pits and the bed bottom, the NHDES Subsurface Systems Bureau inspects the installation and approves the system, and the town makes the final inspection once the area is loamed and seeded. A new house cannot be occupied until NHDES has approved the septic system for operation.

Rather talk it over?

Call 1-855-478-4290 →

Documents for a Durham building permit

Every application

  • Completed application signed by the owner, and the permit fee
  • Scaled site plan for any new or replaced footprint: streets, property lines, setbacks including wetlands, all buildings, paved areas and septic location (a Durham GIS printout or an as-built septic plan may be used)
  • Floor plan to scale with the surrounding rooms, doors, windows and the egress path
  • Framing plan and insulation plan
  • Clear opening sizes of replacement windows that serve as escape openings
  • Driveway application if the driveway changes

New buildings add

  • Two complete sets of plans and specifications
  • NHDES Approval for Construction and the septic designer’s plan, or plans for the sewer and storm drain connections
  • Energy code certification; the town’s Energy Considerations Checklist is strongly encouraged
  • State or town driveway permit
  • Road bond or road construction approval for a new road
  • Approved site plan and any Planning Board bond for commercial work

Once everything required has been submitted, a building permit generally takes a week to ten days, up to two weeks in summer and up to four weeks for large residential projects.

How to apply for a Durham building permit

1. Check zoning

Look up the zone, setbacks and any historic district rules for the lot, and whether the project needs Planning Board or Zoning Board approval first.

2. Line up utilities and the driveway

Get Public Works approval for sewer or water work, new bedrooms, bathrooms or kitchens, and any driveway change; for a septic system, get NHDES approval for construction.

3. Fill in the forms

Complete the Building Permit Application and the minimum documents list on its last page, plus the energy code form where it applies.

4. Pay and submit

Pay the permit fee with the application; plan review does not start until it is paid.

5. Trades file their own permits

Licensed electricians, plumbers and mechanical contractors file their applications, or the owner does when doing the work.

6. Build and book inspections

Start within 180 days, book inspections for a Tuesday or Thursday and request the Certificate of Occupancy after the finals.

Rather not deal with the building department?

Get a free quote →

Durham inspections and certificate of occupancy

Inspections are done on Tuesdays and Thursdays between 8:00 a.m. and 4:00 p.m., booked first come, first served by calling 603-868-8064. The town’s inspection guidelines ask for at least two working days’ notice and allow three working days to carry out an inspection. Work covered with insulation or wall material before it is inspected must be opened up at the contractor’s expense.

The guidelines list the main stages: footing locations certified by a licensed surveyor before construction starts; the foundation after drains and damp-proofing and before backfill; basement and garage slab preparation before the pour; structural framing, ideally at the same visit as rough electrical, plumbing and mechanical; plumbing air or water tests; insulation before walls are covered; and pools and the septic bed bottom on site.

A building may be occupied only after the Building Inspector issues a Certificate of Occupancy. For a new building or major renovation, the town’s checklist includes: NHDES approval for operation of the septic system with a state-certified lab test of a private well (and the well driller’s mechanical permit), or Public Works approval of the sewer and water tie-ins, Public Works engineering and Tree Warden approvals, a backflow test report, a 911 address from the Fire Department, final trade inspections and a gas pressure test, the residential energy code application and a blower door test, the surveyor’s foundation certification when requested, Fire Marshal approval and payment of all fees.

A permit becomes void if work does not start within 180 days or stops for 180 days.

Local Durham details

Short-term rentals: overnight room rentals and rentals of less than 30 days need a permit from the Zoning Administrator, and the town asks owners to contact it before advertising.

Parking: in the Residence A and Residence B districts, no more than three vehicles may be parked regularly on a residential lot unless the owner shows they belong to lawful occupants, and parking areas must be graded, stabilized and clearly marked.

Want this handled start to finish?

Get a free quote →

Construction debris: the applicant or contractor must remove and dispose of it; it may not be left out for Public Works trash pickup.

Building guides: the town’s supporting documents include a deck construction guide, egress window rules, a table of dimensions, a solar ordinance and historic district information.

New Hampshire building code

Every building in New Hampshire must meet the state building and fire codes (the 2024 codes since July 2026). Only towns that have adopted an enforcement mechanism issue local permits, and any local amendment must be administrative and confirmed by the state. New Hampshire rules

Durham building permit FAQ

Who issues building permits in Durham, NH?

The Town of Durham Building Inspector at 8 Newmarket Road (603-868-8064); electrical work is inspected by the town’s Electrical Inspector.

How much is a building permit in Durham?

For one- and two-family homes, $50 plus $7 per $1,000 of construction cost; multi-family and commercial projects pay $100 plus $10 per $1,000. The fee is due before plan review.

How long does a Durham building permit take?

Generally a week to ten days once everything is submitted, up to two weeks in summer and up to four weeks for large residential projects.

Do I need a permit for a shed in Durham?

Not if it is one of no more than two accessory buildings, 200 sq ft or less, 14 feet high or less, unheated and without water or sewer, and meets the setbacks. You still submit a Building Permit Application for a free zoning setback review.

Is there an impact fee for a new house?

Yes. A new single-family house pays a $3,699 school impact fee, which must be paid before the Certificate of Occupancy is issued.

When are inspections done?

On Tuesdays and Thursdays from 8:00 a.m. to 4:00 p.m.; call 603-868-8064 to get on the schedule.

Can a homeowner pull electrical or plumbing permits in Durham?

Yes, when the owner does the work. Otherwise trade permits are taken out by New Hampshire master-licensed contractors.

Inspections are where schedules slip.

Get a free quote →

Official Durham permitting resources

Simplify Durham permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in New Hampshire. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Durham sooner?

Let Alliance prepare, file, and track your Durham permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Durham permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.