Strafford County, New Hampshire Building Permit Guide

Strafford County issues no building permits: each of its 13 cities and towns has its own building inspector or code enforcement office, and you apply to the one where the property sits.

Authority: City and town building officesCounty role: None for permitsLargest city: Dover
Authority
City or town building officeEach handles its own permits
Dover
603-516-6038Online portal
Durham
603-868-8064Inspections Tuesdays and Thursdays
Rochester
$9.00 per $1,000.00Plus a $10.00 application fee

Strafford County has no building department. All 13 of its municipalities, the cities of Dover, Rochester and Somersworth and the towns of Barrington, Durham, Farmington, Lee, Madbury, Middleton, Milton, New Durham, Rollinsford and Strafford, issue their own building permits through a local building inspector or code enforcement office. By the Census Bureau’s 2025 estimates the largest are Dover (34,623), Rochester (33,716), Durham (15,346) and Somersworth (12,171).

This guide lists every city and town in Strafford County with its permit office, phone and, where published, its fees. Dover and Rochester also have their own guides: Dover building permits and Rochester building permits.

What requires a building permit in Strafford County?

There are no county building rules, and the municipalities’ own lists of what needs a permit differ:

  • Somersworth treats all work as needing a permit unless the code office says otherwise, naming fences, roofing, windows and doors, sheds, water heaters and furnaces among others.
  • Farmington does not require a permit for roofing, siding, exact-size window and door replacements, sheds under 120 square feet, fences of 7 feet or less, or retaining walls under 4 feet.
  • Middleton lists siding, roofing, sheds over 120 square feet, fences and walls over 42 inches, and insulation replacement over 200 square feet among the projects that need one.
  • Rollinsford exempts only a yard fence and painting, repair or maintenance of an existing structure costing less than $2,500.
  • Rochester permits expire one year from the issue date, and renewal means reapplying and paying again.

Every building in New Hampshire must meet the state building and fire codes (the 2024 codes since July 2026). Only towns that have adopted an enforcement mechanism issue local permits, and any local amendment must be administrative and confirmed by the state. New Hampshire rules

Who handles permitting in Strafford County?

Every city and town in the county issues its own building permits through a local office:

Short on time to read all of this?

Get a free quote →
Building permit offices in Strafford County
MunicipalityWho issues permitsContact
Barrington (town)Building and Code Enforcement, 4 Signature Drive (off Route 125); online permitting(603) 664-5183; Monday to Thursday, 8:00 am to 4:00 pm
Dover (city)Division of Inspection Services, Planning and Community Development, 269 Mast Road; online portal(603) 516-6038; Monday to Friday, 8:00 am to 4:00 pm
Durham (town)Building office (Code Enforcement), 8 Newmarket Road(603) 868-8064; Monday to Friday, 8:00 am to 5:00 pm, closed 1:00 to 2:00 pm
Farmington (town)Building & Codes, Planning and Community Development, 356 Main Street; applications in person or by email(603) 755-2774; 8:30 am to 5:00 pm; inspector by appointment
Lee (town)Planning & Zoning Administration and Building Inspection, Lee Town Offices, 249 Calef Highway(603) 659-6783; Monday to Friday, 8:00 am to 4:00 pm, call ahead
Madbury (town)Town Building Inspector, Town Hall, 13 Town Hall Road(603) 742-5131; one evening hour and Thursday 8:00 to 9:00 am, dates on the town calendar
Middleton (town)Building code officer, Municipal Office, 182 Kings Highway; building, trade and shoreland permits(603) 473-2261 (town office)
Milton (town)Building Inspector, Town Hall, 55 Industrial Way; applications Monday to Friday, 8:00 am to 4:00 pm(603) 652-4501, ext. 5 (Land Use Clerk)
New Durham (town)Building Official; applications on the town website (form dated August 11, 2026)(603) 520-3715
Rochester (city)Department of Building & Licensing Services, City Hall Annex, 33 Wakefield Street; online or paper applications(603) 332-3508; Monday to Friday, 8:00 am to 5:00 pm
Rollinsford (town)Building Inspector, with Select Board zoning review, Town Hall, 667 Main Street(603) 742-2510
Somersworth (city)Code Enforcement Office, One Government Way; SmartGov online portal(603) 692-9520
Strafford (town)Building Inspectors, Town Hall, 12 Mountain View Drive; online applications(603) 664-2192, ext. 104 or 106; Tuesdays 4:00 to 7:00 pm and by appointment

Not sure this scope needs a permit?

Get a free quote →

Local rules town by town

Dover

The Division of Inspection Services has moved to 269 Mast Road, next to the public works complex. Permits and licenses are applied for through the city’s online portal.

Rochester

Applications go in online or on paper: a major permit for a new home, more units or any commercial building; a minor permit for residential additions, renovations, decks, garages, pools, solar and accessory apartments; and an express permit for fences, re-shingling, siding, sheds of 200 square feet or less and windows. The city waives building permit fees (section 40.15) for an honorably discharged veteran, National Guard or reserve member who builds a home or appurtenance for their own family’s exclusive occupancy.

Durham

Permits generally take 7 to 10 days after a complete application, up to two weeks in summer and up to 4 weeks for large residential projects. The fee is paid before plan review begins.

Somersworth

The Code Enforcement Office takes applications through the SmartGov portal or at Development Services and typically processes a building permit in five to seven business days. The owner or contractor schedules the inspections. Work in the public right of way, from the curb to the property line, such as a driveway, tree planting or a dumpster, needs its own permit.

Farmington

Farmington stopped taking new applications through Cloudpermit and, until its new online system is ready, accepts permits in person or by email to buildingpermits@farmington.nh.us. It allows up to 30 days for processing and returns incomplete applications.

Milton

The Building Inspector issues every building, electrical, plumbing, mechanical, occupancy and sign permit. Dropping off an application does not count as being permitted, and work started before approval costs $200 plus a double permit fee.

Rollinsford and Strafford

In Rollinsford the Select Board starts its setback and zoning review of each building application at its next meeting. In Strafford a new home needs an E-911 address before the town can issue a building permit; the 911 liaison (603-664-2192, ext. 102) assigns numbers free of charge in two to four weeks.

Strafford County permit costs and fees

Each city and town sets its own fees:

Rather talk it over?

Call 1-855-478-4290 →
  • Rochester: $9.00 per $1,000.00 of construction cost (rounded up to the nearest $1,000.00) plus a $10.00 application fee; $20.00 for work under $1,000. The city’s own example: $4,300 of work costs (5 × $9) + $10 = $55. After-the-fact permits pay two times the normal fee.
  • Durham (effective December 16, 2025): one- and two-family residential, $50 application fee plus $7 per thousand of construction cost; multi-family and commercial, $100 plus $10 per thousand; work done without a permit, minimum $100 or 200% of the fee. Septic system test pit inspection, plan review and final inspection after NHDES approval cost $100 per system.
  • Somersworth (fee notice revised May 4, 2026, effective July 1, 2026): residential building permits, a $50 application fee plus $10 per $1,000 of construction cost, or $12 per $1,000 when labor is not included; commercial and industrial, $50 plus $10 per $1,000; electrical, plumbing and mechanical permits, $50 plus $10 per $1,000 of that work; demolition $100 for structures up to 1,500 sq ft; re-inspection $50; permit renewal $50.
  • Barrington (schedule last amended April 8, 2024): $10 per $1,000 of construction cost, $50 minimum, plus flat fees of $25 for the building permit and $50 each for electrical, plumbing and mechanical permits as the job needs them.
  • Rollinsford: $10 per $1,000 of value plus a $25 administrative fee.
  • Strafford (effective March 1, 2025): houses $0.30 per sq ft finished and $0.20 per sq ft unfinished; porches and decks $0.20 per sq ft; garages and barns $0.30 per sq ft; commercial $0.60 finished and $0.40 unfinished.
  • Lee (effective August 10, 2022): $50 covers the first $2,000 of project cost, then $5 per $1,000 above that, for residential and commercial work.
  • How to get a building permit in Strafford County

    1. Find the municipality

    The office of the city or town where the parcel sits issues the permit; the table above lists all 13.

    2. Apply the way that office takes it

    Online in Dover, Rochester, Somersworth (SmartGov), Barrington and Strafford; by email or in person in Farmington; through the Building office in Durham, paying the fee before plan review.

    3. Settle local prerequisites

    An E-911 address in Strafford, Select Board zoning review in Rollinsford, and NHDES septic approval wherever a new system is needed.

    4. Check for a fee waiver

    Rochester waives fees for qualifying veterans and Guard or reserve members building their own family home.

    5. Allow time

    Five to seven business days in Somersworth, 7 to 10 days in Durham (longer in summer and for large houses), up to 30 days in Farmington.

    6. Build within the permit’s life

    Rochester permits expire one year from issue; renewal means a new application and fee.

    Rather not deal with the Strafford County building department?

    Get a free quote →

    Inspections in Strafford County

    Each office books its own inspections. Durham inspects on Tuesdays and Thursdays from 8:00 am to 4:00 pm, first come, first served (603-868-8064), with electrical work inspected by the town’s electrical inspector; a septic system there gets a test pit inspection and a final inspection after NHDES approval. Milton inspects Monday to Thursday from 8:00 am to noon and Friday until 11:00 am, booked through the Land Use Clerk. Farmington needs 48 hours’ notice, Rochester inspects in person except for express permits, and in Somersworth the owner or contractor books inspections using the contacts on the application.

    Want this handled start to finish?

    Get a free quote →

    Official Strafford County permitting resources

    Frequently asked questions

    Does Strafford County issue building permits?

    No. Each of the 13 cities and towns in the county issues its own building permits.

    Inspections are where schedules slip.

    Get a free quote →

    Which towns in Strafford County issue their own building permits?

    All of them: Barrington, Dover, Durham, Farmington, Lee, Madbury, Middleton, Milton, New Durham, Rochester, Rollinsford, Somersworth and Strafford each have a building inspector or code enforcement office.

    How much is a building permit in Rochester or Somersworth?

    Rochester charges $9 per $1,000 of construction cost plus a $10 application fee, and $20 for work under $1,000. Somersworth charges a $50 application fee plus $10 per $1,000 of construction cost ($12 per $1,000 when labor is not included).

    Do I need a permit for a shed?

    It depends on the town. Farmington and Middleton draw the line at 120 square feet, Rochester covers sheds up to 200 square feet with an express permit, and Somersworth lists sheds among the work that needs a permit.

    Does Rochester waive permit fees for veterans?

    Yes. Under section 40.15 fees are waived for an honorably discharged veteran, National Guard or reserve member building a home or appurtenance for their own family.

    How long does a Durham building permit take?

    Generally 7 to 10 days after a complete application, up to two weeks in summer and up to 4 weeks for large residential projects.

    Which building code applies?

    The state building code applies in every town: since July 1, 2026, the 2024 international codes with the 2018 energy code and the 2023 electrical code. Applications filed through December 31, 2026 may use the previous 2021 set instead, as a whole. New Hampshire code editions

    Simplify Strafford County permitting with Alliance Permitting

    250K+Permits approved
    All 50States covered
    21+ YearsJurisdictional depth
    Done-for-youWe file, you build
    • Confirm which of the 13 town and city building offices has the parcel and the project type
    • Prepare the town application with any driveway, septic or fire department approvals it needs
    • Schedule the town’s inspections and close out the permit

    Alliance Permitting is a permit documentation and submission company in New Hampshire. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

    Ready to break ground in Strafford County sooner?