Ozark, Missouri Building Permit Guide

To get a building permit in Ozark, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Ozark’s Planning & Development Department at 203 E. Brick St. reviews, permits and inspects construction inside city limits, and every permit, contractor licence and business registration is applied for in the SmartGov portal.

Authority: Ozark Planning & DevelopmentCode: 2018 I-Codes, 2017 NECPhone: 417-581-5976
Authority
Planning & Development203 E. Brick St.
Apply
SmartGov portalUp to 10 business days’ review
New house
$0.25 per sq ft + $20Plus $196 plan review (2026 fees)
Inspections
Book in SmartGovBefore 7 a.m. for same day

Ozark permits are issued by the City’s Planning & Development Department, whose building official is Community Development Director Randall Whitman, and are applied for and paid in the SmartGov portal. Under the fee schedule adopted for 2026 (Ordinance 25-075), a new house or duplex costs $0.25 per square foot under roof plus a $20 technology fee and a $196 plan review fee, and sewer connection fees rose on January 1, 2026.

What requires a building permit in Ozark?

The City says its ordinances require permits for new construction, plumbing, electrical and HVAC work, signs, commercial fences, accessory buildings and some remodeling projects. Its list of building permit types includes:

Homes and duplexes

  • New single-family homes, duplexes and patio homes
  • Additions and alterations, including remodels that upgrade electrical, plumbing or HVAC systems
  • Trade permits
  • Accessory structures and detached garages (sheds, shops)
  • Decks, swimming pools and solar
  • Fences, demolition and moving a structure

Commercial, industrial, multi-family

  • New buildings, infill, additions and alterations
  • Footing and foundation permits (commercial only)
  • Redevelopment review for a new occupant of an existing building
  • Trade permits and fire sprinkler permits
  • Signs, special events, vendor sites and site plans

Public Works issues the grading/land disturbance, right-of-way, street or curb cut, driveway approach and water and sewer connection permits through the same portal.

Ozark building department: who handles permitting

Planning & Development oversees subdivision, zoning, building codes and nuisance abatement, issues building permits and runs building inspections and code compliance. Its Building Department approves and inspects all new private construction, and Randall Whitman, the Community Development Director, is the building official. Commercial plans and new business occupancies are also reviewed by the Ozark Fire District and Public Works.

Short on time to read all of this?

Get a free quote →
Ozark permit contacts
DetailInformation
OfficePlanning & Development Department (Building Department)
Address203 E. Brick St., Ozark, MO 65721
Phone417-581-5976; fax 417-581-0575
New-business site visits417-581-2407
Online filing and paymentSmartGov permit and licence portal

The City warns that it never asks for permit or licence payments by wire transfer; pay in SmartGov or in person.

Ozark online filing, plans and licences

Create a SmartGov account (verify the email first), choose Apply, pick the department and permit, and enter the address and project details. Required plans and photos must be uploaded as one combined document, not sheet by sheet; incomplete applications are not processed, and the City allows up to 10 business days for review. Payment is due once review is complete.

New house or duplex: submit a scaled site plan with setbacks to the foundation, a full drafted plan set (footing and foundation with girders and double-joist layout, floor plan, all elevations, engineered material specifications), and the square footage, bedrooms, bathrooms, heat type, electric service size and location, gas meter location, lumber sizes, valuation and zoning. Engineered truss specifications go to the Building Department.

Contractors: contractors apply for a City contractor licence ($52) in SmartGov under the Licensing Department and upload the documents listed for their licence type; a new business also needs a business registration ($45).

Moving a business into an existing building: request a site visit (417-581-2407) so the building inspector can decide whether a design professional is needed and which permit applies (Commercial Alteration or Redevelopment Review, $204). The Fire District and Public Works review life safety and backflow assemblies, and the business registration is released only after the certificate of occupancy.

Ozark permit fees (2026)

The Board of Aldermen adopted the 2026 fee study as Ordinance 25-075 (Bill 3698), effective January 1, 2026.

Not sure this scope needs a permit?

Get a free quote →
Ozark Planning and Development fees, effective January 1, 2026
ItemFee
New single-family home or duplex$0.25 per sq ft under roof + $20 technology fee; plan review $196
Residential addition or remodel$0.25 per sq ft + $15, or $115 if greater
Residential inspections: electrical / mechanical / framing / plumbing$89 / $89 / $108 / $145
Residential final (Planning) / final (Public Works)$107 / $350
Water and sewer inspection (Public Works)$168 each
Commercial new, addition, infill or multi-family$0.20 per sq ft for the first 50,000 sq ft + $50, or $350 if greater; then $0.15, $0.10 and $0.05 per sq ft
Commercial plan review25% of the permit fee + $10, or the third-party review fee if greater
Accessory structure / detached garage (residential)$126 / $153
Deck; fence (residential)$124; $170
Pool: above-ground / in-ground$89 / $185
Demolition: residential / commercial$373 / $387
Solar: residential / commercial$155 / $169
Reinspection (third inspection and later)$219
Work without a permit$175
Permit renewal: residential / commercial$77 / $97
Floodplain development permit$99

For example, a 2,000 sq ft house under roof pays 2,000 × $0.25 = $500, plus the $20 technology fee and $196 plan review, or $716, before inspection, utility and impact fees for the scope of work. The City’s older single-family handout still quotes a $130 re-inspection fee; the 2026 schedule sets $219. Applicants also pay the cost of any third-party architectural, engineering, stormwater or traffic review the City requires ($154 an hour for third-party architectural review).

Ozark water impact and sewer connection fees (sewer fees from January 1, 2026, Ordinance 25-088)
MeterFee
5/8-inchWater impact $100; sewer connection $2,691.98
1-inchWater impact $2,608.14; sewer connection $4,411.88
2-inchWater impact $6,085.67; sewer connection $10,294.41

Rather talk it over?

Call 1-855-478-4290 →

Larger meters cost more, and construction outside city limits pays twice the impact rate. A 5/8-inch water meter is listed at $442.78, subject to change.

Electrical, plumbing and mechanical work in Ozark

The Building Department enforces the City’s plumbing, electrical, mechanical and fire codes and issues trade permits for single-family, duplex, multi-family, commercial and industrial work. The 2026 schedule lists separate residential electrical ($89), mechanical ($89) and plumbing ($145) inspection fees. Ozark’s house requirements include carbon monoxide detectors where there is an attached garage or gas appliance, and a 4-inch schedule 40 sewer line at least 3 ft deep with no 90-degree turns or saddle taps. Fire sprinkler systems need their own permit ($213), and commercial work also has fire hood ($185) and sprinkler ($252) inspections.

How to get an Ozark building permit

1. Check zoning and the site

Confirm the lot is in Ozark and zoned for the use; new businesses start with a site visit.

2. Open a SmartGov account

Verify your email, then choose Apply and the right department and permit type.

3. Upload one combined plan set

Add the site plan and drawings as a single document; contractors need a City licence.

4. Wait for review

Allow up to 10 business days; Fire District and Public Works review where needed.

5. Pay and post the permit

Pay in SmartGov after review and keep the permit, plans and job card on site.

6. Inspect and get the certificate

Book inspections in SmartGov through the final for occupancy; all fees must be paid first.

Rather not deal with the building department?

Get a free quote →

Ozark inspections

Schedule inspections in SmartGov. The City’s single-family handout says requests made before 7:00 a.m. are inspected the same day and later requests the next working day. A new house is inspected at the footing, foundation walls or piers, under-slab plumbing, thickened slab, pre-backfill (basement homes), sewer, temporary electric, joists, structural framing, electrical, plumbing, mechanical, gas line test, permanent electric service, insulation, drywall and final for occupancy, plus any others required. A permit expires if no inspection is made within 180 days. All fees and penalties must be paid before a certificate of occupancy is issued.

Local Ozark rules

Accessory buildings: all accessory structures together may cover no more than 35 percent of the lot’s permitted building coverage, there may be no more than three on a lot, and none may exceed two-thirds of the main building’s coverage. Gable or hip roofs are limited to 16 ft and flat or single-slope roofs to 12 ft.

Floodplain: Ozark takes part in the National Flood Insurance Program, with flood maps effective November 2, 2023. Development in a flood hazard area needs a separate floodplain development permit ($99), and new or substantially improved homes must have the lowest floor, including any basement, 1 ft above the base flood elevation. A representative of Planning & Development appointed by the Mayor serves as floodplain administrator. The City Code also has a chapter protecting the Smallin Cave recharge area and the Finley River watershed.

Signs: a new business may hang a grand-opening banner for 30 days without a permit; permanent wall signs and window or door decals need a sign permit.

Ozark building codes

Title V of the Ozark City Code (Ordinance 19-004, January 22, 2019) adopts the 2018 International Building and Residential codes and the other 2018 ICC codes with the 2017 National Electrical Code. Local amendments set a 20 psf ground snow load, delete the garage sprinkler and testing rules, and let builders of four or fewer attached units choose separation instead of sprinklers.

Missouri has no mandatory statewide building code for private construction: a county, fire protection district or municipality may adopt one (usually by reference under RSMo 67.280), and in parts of the state none has. Building codes in Missouri

Ozark permit FAQ

Want this handled start to finish?

Get a free quote →

Who issues building permits in Ozark?

The City’s Planning & Development Department at 203 E. Brick St. (417-581-5976), through the SmartGov portal, for property inside city limits.

How much is a building permit for a new house in Ozark?

$0.25 per square foot under roof plus a $20 technology fee and $196 plan review, so $716 for 2,000 sq ft, before inspection, water and sewer fees.

How long does review take?

The City allows up to 10 business days for review of an application.

Do I need a permit for a shed, deck or pool?

Yes. Accessory structures ($126), decks ($124) and pools ($89 above-ground, $185 in-ground) are permitted through SmartGov.

How long is a permit valid?

The City’s handout says a permit is active for 180 days and expires if no inspection is made within that time; renewing a residential permit costs $77.

What does it cost to connect a new house to sewer?

Since January 1, 2026 the sewer connection fee for a 5/8-inch meter is $2,691.98, plus a $100 water impact fee.

Ozark permit search and official resources

These are the primary sources behind this guide. Codes, fee schedules and procedures change — confirm the position for your filing date.

Inspections are where schedules slip.

Get a free quote →

Simplify Ozark permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Missouri. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Ozark sooner?

Let Alliance prepare, file, and track your Ozark permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Ozark permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.