Skip to main content
Municipal GuideMissouriDunklin County · Kennett

Kennett, Missouri Building Permit Guide

To get a building permit in Kennett, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Kennett’s Code Enforcement office, at 200 Second Street, takes building permit applications for the city and its Code Enforcement Officer acts as building official, inspector and floodplain administrator.

Authority: Kennett Code EnforcementCode: 2021 IBC and IRCPhone: 573-888-3005
Authority
Code Enforcement200 Second Street
Plan review
Up to 10 daysFor major projects
Rental licence
Required since 2025Renew every 2 years
Flood rule
1 footLowest floor above base flood elevation

Building permits in Kennett are handled by the City’s Code Enforcement office at 200 Second Street (573-888-3005), whose Code Enforcement Officer is the building official under the City Code. Kennett enforces the 2021 International Building and Residential Codes, allows up to 10 days for review of major projects, and has required rental licences since January 1, 2025.

What needs a permit in Kennett?

City Code Section 500.120 requires a building permit for any construction, alteration or repair of a structure, with a few exceptions.

Permit always needed

  • New buildings, additions and alterations
  • Repairs costing $500 or more
  • Any plumbing or electrical work in a commercial building
  • Any electrical work that adds a new circuit
  • Plumbing, including gas piping, that changes a connection to a public utility
  • Demolition

No permit needed

  • Painting
  • Driveways, parking areas and walks built at grade that do not alter a public street or curb
  • Other work under $500, apart from plumbing and electrical work

The permit must be posted on the front door, or where it can be seen from the front door, and on new construction where it is visible from the street before the building goes up. Work may not move past a stage on the inspection record until that stage has been inspected.

Kennett building department: who handles permitting

The City Code makes the Code Enforcement/Property Maintenance Officer the building official, plumbing official, mechanical officer and floodplain administrator, with authority to inspect building, electrical and plumbing work and to stop work that breaks the code. Victor Mode is the Code Enforcement Officer. The Fire Chief signs off on water supply for commercial and industrial permits.

Short on time to read all of this?

Get a free quote →
Kennett permit contacts
DetailInformation
OfficeCode Enforcement
Address200 Second Street, Kennett, MO 63857
Phone573-888-3005 (option 1 for code enforcement)
Fax573-888-0224
Emailkfdce@kennettfd.org
City Hall200 Cedar Street, 573-888-9001, 8:00 a.m.–5:00 p.m. weekdays

Applying for a Kennett permit

Use the City’s Application for Plan Examination and Building Permit, which records the location, zoning district and setbacks, whether the lot is in a flood zone, the type of work, the proposed use, the estimated cost of labor and materials, the construction details and the contractor’s licence, insurance and workers’ compensation numbers. The form still cites the 2012 International Building Code, although the City adopted the 2021 codes in March 2023.

The application sets these conditions:

  • Drawings of the proposed construction for nonresidential projects (they may not be needed for minor work), and two sets of plans sealed and signed by a Missouri registered architect or engineer for any commercial construction
  • Up to 10 days for plan review on major projects
  • A site plan, where applicable, with elevation data, fire protection data, existing and proposed utilities, a stormwater management plan and erosion control
  • Asbestos testing before demolition
  • A state land disturbance permit if 43,560 sq ft (one acre) or more of ground is disturbed
  • A pre-construction meeting before work begins
  • All inspections closed out by the Code Enforcement Officer with an occupancy permit

Commercial, industrial and subdivision applications must show all underground utilities and the nearest fire hydrant; new mains and hydrants are required if the nearest hydrant is more than 300 feet away, across a major road, hard to reach or below 1,000 gallons per minute, and the permit waits for the Fire Chief’s certification.

Not sure this scope needs a permit?

Get a free quote →

Kennett permit fees

The City Code does not list building permit fee amounts. Section 500.070 points to Section 500.120 for fees and authorizes the Code Enforcement/Property Maintenance Officer to set fees for permits and inspections not covered there, so permit fees are set by Code Enforcement (573-888-3005).

Street work does have Code fees. A permit to excavate in a paved street (City Code Section 515.030) costs $100 for an asphalt street, $150 for concrete, $250 for asphalt over concrete, $75 for a whole gravel street, $35 for half of a gravel street and $25 for an alley, and building or repairing a public sidewalk, curb or gutter needs a permit from the City Clerk, reviewed by the Street Superintendent.

For rentals, the City’s published inspection process sets the fees: a tenant’s move-in rental inspection costs $50, a second inspection after repairs is free, and the owner pays $50 for a third.

Trade licences and electrical rules

Kennett requires a City tradesmen’s licence, issued by the City Collector, for electrical contracting; plumbing, including gas piping, sprinkler and standpipe piping and irrigation connected to City water; building contracting (other than painting or plastering without structural change); mechanical work; extermination; and tree work. Applicants show contractor’s liability and completed-operations insurance of at least $100,000 for property damage and $100,000 for bodily injury. A resident owner needs no licence for work on their own premises that involves no structural alteration or change to a utility connection.

Electrical permits are obtained from the City License Issuing Clerk by the person in charge of the work, and a person doing their own electrical work needs the permit but not a licence or bond. Kennett adopted the National Electrical Code by reference to the 2005 edition “and any subsequent edition”, and it bars aluminum wiring inside buildings except from the meter base to the main panel. The plumbing, mechanical, fuel gas, fire and existing building codes are the 2021 editions; the energy code is the 2012 edition.

Rather talk it over?

Call 1-855-478-4290 →

How to get a Kennett building permit

1. Licence the contractors

Electrical, plumbing, building and mechanical contractors need a City tradesmen’s licence and insurance.

2. Check zoning and flood zone

Note the zoning district and setbacks, and whether the lot is in a mapped flood zone.

3. Complete the application

Fill in the plan examination and building permit form with costs and construction details.

4. Submit plans

Bring two sealed sets for commercial work to Code Enforcement at 200 Second Street; allow up to 10 days for major projects.

5. Pre-construction meeting

Meet with the City before beginning work and post the permit where it can be seen.

6. Inspections and occupancy

Pass each stage on the inspection record and get the occupancy permit before moving in.

Kennett inspections

The City publishes checklists of what is inspected for a one-story house, a two-story house and an accessory building. Footings for a one-story house must be at least 16 inches wide and 18 inches below grade, with two #4 bars and 10 inches of concrete; a two-story house needs 24-inch-wide footings with three #4 bars and 12 inches of concrete; an accessory building at least 12 by 12 inches. Inspectors also check anchor bolts, framing, rough and finished plumbing and electrical work, smoke detectors and the mechanical system. Houses need at least 100-amp service and arc-fault protection on bedroom circuits, and a house may not be lived in until it passes its final inspection.

Rather not deal with the building department?

Get a free quote →

Local Kennett rules

Rental licensing: since January 1, 2025 an owner may not rent or offer a rental unit without a City rental licence, renewed every two years and listing a local representative within 60 miles of Main and St. Francis Streets (Ordinance 3099, amended by Ordinance 3108 in July 2025). Code Enforcement inspects at least half of the licensed units each year at random, can inspect for cause, and may revoke a licence after a third failed inspection. Exempt are Housing Authority units, state-licensed facilities, owner-occupied lots of two units or fewer, new construction within two years of its certificate of occupancy, and religious orders. A tenant moving in applies for an inspection with a signed lease, and utilities are put in the tenant’s name by the Kennett Board of Public Works only after the unit passes.

Floodplain: Kennett takes part in the National Flood Insurance Program on a flood map dated June 4, 1980. Development in A and AE zones needs a floodplain development permit from the Code Enforcement Officer, and new or substantially improved homes must have the lowest floor, including any basement, 1 foot above the base flood elevation, certified by a Missouri licensed surveyor, engineer or architect.

Code changes: the City adopted a new Code of Ordinances (Ordinance 3112) in February 2026, and in July 2026 cut the Planning and Zoning Commission to seven members, ending the Code Enforcement Officer’s vote on it (Ordinance 3118).

Missouri building code

Missouri has no mandatory statewide building code for private construction: a county, fire protection district or municipality may adopt one (usually by reference under RSMo 67.280), and in parts of the state none has. Building codes in Missouri

Kennett building permit FAQ

Who issues building permits in Kennett?

The City’s Code Enforcement office at 200 Second Street (573-888-3005); the Code Enforcement Officer is the building official.

Want this handled start to finish?

Get a free quote →

Do I need a permit for small repairs?

Not for painting or for work under $500, unless it involves plumbing or electrical work that needs a permit, such as a new circuit.

How long does plan review take?

The application allows up to 10 days for major projects.

Which building codes does Kennett use?

The 2021 International Building, Residential, Plumbing, Mechanical, Fuel Gas, Fire, Existing Building and Property Maintenance Codes, with the Group R sprinkler section (903.2.8) excepted.

Do landlords need a licence in Kennett?

Yes. Rental units have needed a City licence since January 1, 2025, renewed every two years.

How much is a rental inspection?

$50 for the move-in inspection; the first re-inspection is free and a third costs the owner $50.

Kennett permit search and official resources

Inspections are where schedules slip.

Get a free quote →

Simplify Kennett permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Missouri. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Kennett sooner?

Let Alliance prepare, file, and track your Kennett permits while your crew stays on the job.