Douglas County, Minnesota Building Permit Guide

To get a building permit in Douglas County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Douglas County Land and Resource Management in Alexandria issues land use permits for building, moving or enlarging structures outside city limits and Alexandria Township, online through the county’s permit portal or at the courthouse counter.

Authority: Douglas County Land & Resource ManagementCode: Douglas County Zoning Ordinance (land use permits)Phone: 320-762-3863
Office
Land & Resource Management305 8th Ave W, Alexandria (courthouse, first floor)
House permit
$25 per 100 sq ft2026 fee schedule, $75 minimum
Processing
Up to 15 business daysWork starts once the permit is on site
Near Alexandria
City building permit tooWithin two miles of city limits

Douglas County Land and Resource Management, on the first floor of the courthouse at 305 8th Avenue West in Alexandria, issues the land use permit that the county calls a building permit for structures outside city limits and Alexandria Township. Apply through the county’s online portal or in person; the 2026 fee schedule charges $25 per 100 square feet for a dwelling or addition, processing can take 15 business days, and land within two miles of Alexandria also falls under the city’s building code enforcement.

What requires a permit in Douglas County?

Outside city limits and Alexandria Township, a land use permit is needed to build, move or add onto a structure, to remodel in a way that changes its footprint, or to make a structural alteration such as excavating for footings, pouring foundations or slabs, setting posts, building basements or walls, or changing a roof line or pitch. The county defines a structure broadly: dwellings, decks, patios, attached and detached garages, gazebos, playhouses, tree houses and sidewalks wider than four feet all count.

Land use permit needed

  • New houses and additions
  • Garages and storage sheds
  • Decks and patios (outside non-platted agricultural land)
  • Gazebos, playhouses and tree houses
  • Moving a structure onto a lot
  • Roof pitch changes and other structural work
  • Rooftop and ground-mounted solar
  • Landscaping, dirt work or clearing in the shore or bluff impact zone (shoreland alteration permit)

Usually no permit

  • Re-shingling and re-siding
  • Replacing windows or doors outside the floodplain
  • Remodeling that does not change the exterior footprint
  • Satellite dishes, sprinklers and hot tubs that meet setbacks
  • Pump houses no larger than 4 by 4 by 4 feet
  • Grain bins, decks and patios in non-platted agricultural districts, if setbacks are met
  • Agricultural fences

Fences outside agriculture may sit on the property line if they are maintenance-free or can be maintained from inside, otherwise 2 feet back, and the zoning ordinance caps them at 6 feet unless they hold livestock. Livestock in a residential district needs a conditional use permit, and because all shoreland is treated as residential, that can reach horses kept within 1,000 feet of a body of water.

What the county decides and what the state holds

The county decides zoning districts, setbacks, impervious coverage, septic compliance and shoreland rules under its Zoning Ordinance, whose posted copy lists amendments through one effective October 1, 2018. Its land use pages describe a zoning review rather than building-code plan review or construction inspections. The City of Alexandria is different: land inside the city or within two miles of its limits must also meet the city’s permitting and building code enforcement requirements, as shown on the county’s 2019 enforcement-area map. Electrical permits come from the state Department of Labor and Industry unless a local program applies, and contractors hold state licenses.

⚠️ Septic rules under review. The Planning Advisory Commission has a public hearing set for November 10, 2026 at 7:30 p.m. on proposed amendments to the zoning ordinance’s sanitation and administration sections, covering effluent screens, water use metering, Type II operating permits, compliance-inspection triggers and compliance at property transfer. The current rules apply until the County Board adopts any change.

Short on time to read all of this?

Get a free quote →

Douglas County building department: who handles permitting

Land and Resource Management runs land use, subdivision, shoreland, septic, feedlot and solid waste regulation, the excavator license and the aquatic invasive species program; Dave Rush is the director. The zoning ordinance applies outside the corporate limits of cities, and since January 1, 2007 Alexandria Township has issued its own permits through the township office. Public Works issues county road permits and, through its Surveyor’s Office, rural E911 addresses.

Douglas County permitting contacts
OfficeContact
Land & Resource Management (land use, shoreland, septic, feedlots)Douglas County Courthouse, first floor, 305 8th Ave W, Alexandria, MN 56308; 320-762-3863; landresmngmt@douglascountymn.gov
Public Works (driveway, right-of-way and E911 address permits)526 Willow Drive, Alexandria, MN 56308; 320-762-2999
Alexandria TownshipTownship office issues permits inside the township
City of Alexandria (city and two-mile area building code)320-763-6678, the number the county gives
ElectricalMinnesota Department of Labor and Industry

Cities in Douglas County

Each city sets its own zoning and decides whether it enforces the State Building Code. Osakis straddles the Todd County line. The flood-program column is from FEMA’s Community Status Book.

Cities in Douglas County (Census 2025 estimates)
CityPermits and flood program
Alexandria (15,045)City permits and building code, also in a two-mile area outside its limits; no FEMA listing
Osakis (1,599 in Douglas County)City handles its own permits; participating in the flood program
Carlos (482)City handles its own permits; listed as not in the flood program
Evansville (584), Brandon (509), Miltona (454), Garfield (339), Kensington (270), Forada (187), Nelson (186), Millerville (97)Each city handles its own permits; no FEMA listing

Douglas County permit types

The county’s Citizen Services portal takes land use, shoreland alteration, conditional use, variance and sign permits online, plus the Public Works driveway, E911 address and sign, oversize load, service sign, special event and right-of-way permits. Septic permits must be applied for in person or by a mailed application, and metes and bounds subdivisions and common property line adjustments are handled in person.

Not sure this scope needs a permit?

Get a free quote →

Residential permits

Only the owner, with proof of ownership, or a contractor can apply for a land use permit. The packet needs a site plan with property dimensions and the distance from each proposed structure to the road centerline or right of way, side and rear lines, septic system, ordinary high water level, any bluff and wetlands, an impervious surface calculation on the county’s 25 percent worksheet, building plans with interior and exterior layouts, and a clearing and grading plan. For a house the plans show each level, covered porches, decks, the attached garage, stories, sidewall height and height to the midpoint of the highest gable; garages, sheds and farm buildings need use, size, stories, heights and roof pitch. Used buildings need approval before they are moved in.

Sewage is settled before the permit. A lot either connects to the Alexandria Lakes Area Sanitary District where it is available, submits a new septic design by a licensed designer, or shows a current certificate of compliance. A dwelling must be at least 24 feet wide and deep, except that agricultural parcels of 5 acres or more are exempt from the width rule.

Commercial and other permits

Commercial and industrial buildings pay by area under their own fee line. Solar farms, wind farms, substations and battery storage, gravel mining, planned unit developments and cellular towers carry special use permit fees, and community solar gardens have their own fee line. Signs and billboards need a sign permit, and feedlots over 50 animal units, or over 10 in shoreland, register with the county feedlot officer, who issues permits for new or expanding operations under the state feedlot rules.

What comes before the permit

  • Septic compliance. A system more than five years old needs an inspection or a compliance inspection within the past three years, and a failing system must be upgraded before the permit.
  • Driveway and culvert. A new driveway onto a county road needs a Public Works permit; on a township road the township handles access and culverts.
  • Address. The Surveyor’s Office assigns rural E911 addresses through the portal, usually in 7 to 10 working days.
  • Hearings. A variance or conditional use permit may be needed before the land use permit, and any conditions on earlier approvals must be met first.
  • Stormwater. Disturbing one acre or more needs the state construction stormwater permit.
  • Alexandria area. Inside the two-mile ring, check with the City of Alexandria about its building permit.

Douglas County permit fees

Land and Resource Management charges under its 2026 fee schedule, updated January 26, 2026. Fees are non-refundable, and the zoning ordinance says work begun before a permit still has to meet the ordinance and the fee schedule.

Rather talk it over?

Call 1-855-478-4290 →
Douglas County land use and septic fees (2026 schedule)
ItemFee
Minimum residential land use fee$75
Dwelling or addition$25 per 100 sq ft
Deck or patio: 100 sq ft and under / 101–400 / over 400$75 / $150 / $250
Accessory structure incl. ground-mount solar: 200 sq ft and under / 201–1,000 / 1,001–2,400 / over 2,400$75 / $125 / $275 / $400
Roof pitch change with no added living space$150
Commercial or industrial building$50 per 100 sq ft, $150 minimum
Shoreland alteration: minor / standard / major$150 / $300 / $500
Septic system installation, Type I or III–V, soil verification included$350
Homeowner self-installed septic system$850
Holding tank or privy$250
Cluster system / systems over 9 bedrooms or Class V well$1,250 / $500
Additional septic inspection, third or later visit$125
Conditional use permit / variance$600 / $600
Rezoning / planned unit development$850 / $850
Solar farm, wind, substation or battery storage use$1,200
Sign permit / billboard$100 / $300
Excavation and landscaping license ($10,000 bond)$125
After-the-fact land use permit2x, then 3x, then $1,000 plus the fee

Worked example from the schedule: a 24 by 40-foot detached garage is 960 square feet, inside the 201 to 1,000 square foot band, so the permit is $125; a 12 by 16-foot deck at 192 square feet adds $150. After-the-fact shoreland alteration penalties run from $50 to $2,500 depending on the permit class and how many notices it took to resolve.

Trade permits and who may pull them

The county issues no electrical, plumbing or mechanical permits, and its pre-application checklist lists scheduling the electrical inspection as a separate step. Electrical permits are filed with the Department of Labor and Industry where its lookup shows the state as the authority, or with the city or township where it shows a local program.

  • Building contractors. The county asks for each contractor’s Minnesota license number on the application; it does not license builders.
  • Excavators and landscapers. These hold a Douglas County license backed by a $10,000 bond, and the license number goes on the application; the office will confirm whether a firm is bonded.
  • Septic professionals. Designers and inspectors are state licensed, and the county posts a local septic professionals list; homeowners who install their own system pay the higher $850 permit.

Rather not deal with the Douglas County building department?

Get a free quote →

How to apply for a Douglas County land use permit

1. Confirm who permits the parcel

Rule out city limits and Alexandria Township, and check the two-mile Alexandria ring.

2. Settle the septic question

Get a compliance inspection for a system over five years old, a new design, or proof of a sewer connection.

3. Draw the site plan

Show setbacks to roads, lot lines, septic, water, bluffs and wetlands, and fill in the impervious worksheet.

4. Line up access and address

Apply for the driveway permit and E911 address through Public Works, or the township for a township road.

5. File the application

Submit online through the Citizen Services portal or at the courthouse, with plans and contractor license numbers.

6. Pay and wait for the permit

Pay the non-refundable fee; no work may start until the permit is received and posted on site.

Review, corrections and what causes delay

Plan on up to 15 business days after a complete application is reviewed, approved and paid before the permit is mailed. Conditional use permits go to a Planning Advisory Commission hearing and then the County Board, which generally takes four to five weeks; variances go to the five-member Board of Adjustment, and applicants answer six findings-of-fact questions. The two bodies meet twice a month on Tuesday evenings. A septic system found failing must be upgraded first, inspections can be deferred in winter only until the following June 1, and a land use permit lasts one year, with yearly extensions only for diligent construction.

Inspections in Douglas County

The county’s inspections center on septic systems and site compliance. Septic installations are checked by Land and Resource Management, with a $125 charge for the third and any later visit; existing systems are checked by state-licensed inspectors whose compliance reports the county reviews before a land use permit, conditional use permit or variance.

When property changes hands, a point-of-sale form goes to the office with a county certificate of compliance from the last five years, an inspector’s report from the last three, or a plan to escrow funds, replace or abandon a non-compliant system. A winter transfer can defer the inspection until the next June 1. Electrical work is inspected under its own state or local permit.

Minnesota building code

Douglas County regulates land use, shoreland, septic systems and feedlots through its Zoning Ordinance and is an MPCA-delegated feedlot county. FEMA’s Community Status Book lists Douglas County as participating in the National Flood Insurance Program since September 1, 1988, with a current map dated November 18, 2009 that shows flood areas without base flood elevations; replacing windows or doors in the floodplain needs a permit.

Want this handled start to finish?

Get a free quote →

Minnesota has one State Building Code that applies statewide and overrides local building codes, but enforcement is local: whether a building permit is needed depends on whether the city, township or county enforces the code there. Electrical permits come from the Department of Labor and Industry unless the local government runs its own electrical inspection. Minnesota rules

Douglas County permit search and official resources

The fee schedule lists a land use permit list at $20 per report, and staff reports for Planning Advisory Commission and Board of Adjustment hearings are posted on the county calendar, with older reports sent by email on request.

Inspections are where schedules slip.

Get a free quote →

Douglas County permit FAQs

Is a Douglas County land use permit the same as a building permit?

The county calls it a building permit, but it is a zoning approval for structures outside city limits and Alexandria Township.

Do I need a permit to re-roof or replace windows?

Usually not: re-shingling, re-siding and window or door replacement outside the floodplain need no land use permit.

How much is a permit for a new house?

$25 per 100 square feet for a dwelling under the 2026 schedule, plus $350 for a standard septic installation.

I live near Alexandria. Which permit do I need?

Within two miles of Alexandria you may need the city’s building permit as well as the county land use permit.

Who issues permits in Alexandria Township?

The township office, which has handled permitting there since January 1, 2007.

Why does my septic system matter for a garage permit?

In most cases a system over five years old needs a compliance inspection from the past three years before the county issues a land use permit.

How long does a permit take?

Up to 15 business days after it is approved and paid, and work cannot begin until the permit is on site.

Can I clear trees along my lakeshore?

Limited clearing, up to 25 percent or 25 feet of frontage, is allowed with a shoreland alteration permit.

Simplify Douglas County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Minnesota. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Douglas County sooner?

Let Alliance prepare, file, and track your Douglas County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Douglas County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.