Burton, Michigan Building Permit Guide

To get a building permit in Burton, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Burton’s Building Division, part of the Department of Public Works at 4093 Manor Drive, issues building, site and occupancy permits; electrical, mechanical and plumbing permits come from the State of Michigan.

Authority: Burton Building Division (DPW)Trades: State of Michigan permitsPhone: 810-742-9230
Building permits
City of BurtonDPW Building Division
Trade permits
State of MichiganElectrical, mechanical, plumbing
Processing
2–3 days residential7–10 days commercial
DPW hours
Mon–Fri 8–4810-742-9230

The City of Burton issues building, site and occupancy permits through the Building Division of its Department of Public Works, 4093 Manor Drive (810-742-9230, weekdays 8 a.m. to 4 p.m.). It does not issue electrical, mechanical or plumbing permits: under the state’s jurisdiction list those trades are permitted and inspected by the state, and the city wants proof of the state approvals before its rough or final building inspection. Fire alarm and suppression systems are permitted by the Burton Fire Department. The city says a residential application normally takes 2 to 3 days to process and a commercial one 7 to 10 days.

What requires a building permit in Burton?

Burton requires a permit from anyone who plans to construct, enlarge, alter, repair, move, demolish or change the occupancy of a building or structure. The Building Division lists additions, garages, pole barns, decks, porches, siding, roofing, fences, swimming pools and sheds as examples, and demolition of a structure also needs a building permit.

Permit needed (city answers)

  • Garages of 200 sq ft or more: building permit with construction details
  • Sheds (less than 199 sq ft in the city’s FAQ): a site permit
  • Pools holding more than 24 inches of water
  • Finished basements, which also need an egress window
  • Decks that are attached, closer than 10 feet to the house, or 200 sq ft or larger
  • Siding, roofing and fences (set fees)
  • Demolition

No permit (city answers)

  • Cosmetic interior work: painting, carpet or other floor coverings, interior doors
  • A free-standing deck at least 10 feet from the house and under 200 sq ft

If you are not sure whether a job needs a permit, the Building Division asks you to call before starting. Working without one can bring extra costs or a ticket requiring a court appearance.

What Burton decides and what the state holds

On the Bureau of Construction Codes’ Statewide Jurisdiction List (revised November 6, 2026) Burton is LOCAL for the building code and STATE for the electrical, mechanical and plumbing codes, and Genesee County has no construction-code program. The code is the state’s; Burton enforces it for buildings along with its own city ordinances, sets its building fees and zoning rules, and leaves the trade permits to the state.

Short on time to read all of this?

Get a free quote →

Burton building department: who handles permitting

Building permits are handled by the Building Division of the Department of Public Works, which sits beside the city’s Code Enforcement, Planning and Zoning Divisions. The inspector is in the office Monday to Thursday from 7 a.m. to 8 a.m. and in the field the rest of the day, so code questions may need a message; clerical staff answer permit-process questions all day.

Burton permit contacts
DetailInformation
OfficeBuilding Division, Department of Public Works, 4093 Manor Drive, Burton, MI 48519
Phone / fax810-742-9230 (Building Official ext. 3109) / 810-742-8015
DPW hoursMonday to Friday, 8 a.m. to 4 p.m.
City Hall810-743-1500, Monday to Friday, 9 a.m. to 5 p.m. (Clerk, FOIA)
Electrical, mechanical, plumbingState of Michigan, Bureau of Construction Codes
Fire alarm and suppressionBurton Fire Department

Burton permit types

The Building Division issues three kinds of city permit: building permits, site permits and occupancy permits. Applications are printed from the city’s document center, filled out completely and returned to the Department of Public Works on Manor Drive.

Residential permits

  • Houses, additions and garages take a building permit priced on the estimated cost of construction. An attached garage, or a detached one over 600 sq ft, needs 42-inch footings; where a garage attaches to a house that lacks them, it follows the house’s foundation.
  • Accessory buildings are limited by lot size and the buildings already on it; the city’s pamphlet shows how to work out the allowable floor area.
  • Interior work beyond cosmetic changes may need a permit (ask the Building Division), and any permitted interior improvement triggers hard-wired, interconnected smoke alarms in all bedrooms and hallways.
  • Decks 30 inches or more above the ground need rails, with spindles no more than 4¼ inches apart.
  • Roofing, siding, fences and sheds have set fees rather than a cost-based fee.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

Commercial building applications go to the same office, with a normal processing time of 7 to 10 days. Fire alarm and fire suppression systems are permitted separately through the Burton Fire Department, and electrical, mechanical and plumbing work through the state.

What comes before the building permit

  • Zoning. Setbacks, lot coverage and uses are set by the city zoning ordinance and handled by the Planning and Zoning Divisions of the Department of Public Works.
  • Septic and wells. Where no public sewer or water serves a lot, the Genesee County Health Department (810-257-3603) issues septic and well permits; it may deny a septic permit where sanitary sewer is available.
  • Soil erosion. For an earth change of an acre or more, or close to a lake, stream or drain, ask the Department of Public Works which agency issues the soil erosion permit for your site.

Burton permit costs and fees

Burton prices a building permit on the estimated cost of construction, and charges set fees for roofing, siding, fences and sheds. Ask the office at 810-742-9230 for the current amounts and an estimate for your job before you apply.

How Burton permit fees are set
WorkPermit and fee basis
New buildings, additions, garages, alterationsCity building permit; fee based on estimated cost of construction
Roofing, siding, fences, shedsCity permit at a set fee
DemolitionCity building permit
Electrical, mechanical, plumbingState permit and state fee
Fire alarm and fire suppressionBurton Fire Department permit
New septic system (where no sewer)$220 residential, $280 commercial (county), plus the perc test
New private well (where no water main)$200 (county)

Rather talk it over?

Call 1-855-478-4290 →

The county figures come from the Genesee County Health Department, which charges the same $220 or $280 for the perc test as for the septic permit itself, $400 to replace a whole septic system and $100 to replace only a tank. Sewer and water connection permits depend on the provider: the Drain Commissioner’s Water & Waste Services notes that some communities issue their own, so ask the Department of Public Works which applies to your lot.

Trade permits and who may pull them

Electrical, mechanical and plumbing permits in Burton are state permits: the State of Michigan’s Bureau of Construction Codes issues them and its inspectors inspect the work. The city takes no trade applications, but its inspector will not do a rough or final building inspection until you can show the trade approvals for that stage.

  • Who applies. State-licensed electrical, mechanical and plumbing contractors take out the state permits for their work; an owner planning to do trade work personally should ask the Bureau of Construction Codes what it allows.
  • Fire systems. Fire suppression and fire alarm permits come from the Burton Fire Department, not the state.
  • Building permits. For residential work only the property owner or a licensed contractor can pull the city permit, and the permit holder is liable for violations, corrections and damage from faulty work.

The city advises owners who hire a contractor to see the permit before work starts, and warns that a licensed contractor should be able to get the permit and its inspections without asking the owner to take out a “home owners permit”.

How to apply for a Burton building permit

1. Check whether a permit is needed

Use the city’s list and FAQ, or call the Building Division.

2. Check zoning and lot coverage

Confirm setbacks and the allowable accessory floor area for your lot.

3. Print the right application

Pick the form for your work from the city’s document center and fill it out completely.

4. Return it to DPW

Take or send it to the Department of Public Works, 4093 Manor Drive.

5. Get the trade permits

Have your electrical, mechanical and plumbing contractors take out state permits, and the fire system contractor a Fire Department permit.

6. Pay and build to inspections

Pay the city fee and call for each inspection with the state approvals in hand.

Rather not deal with the building department?

Get a free quote →

Review, corrections and what causes delay

The city’s normal processing time is 2 to 3 days for a residential application and 7 to 10 days for a commercial one. Fill the application out completely, as the city asks, and get the state trade permits moving early: a rough or final building inspection cannot be passed until the matching state approvals are shown.

Inspections and certificates in Burton

The city inspector checks building work under the city permit, and the state’s inspectors check electrical, mechanical and plumbing work under the state permits. Bring proof of the trade approvals to the city’s rough and final inspections; the city will not sign off a building stage without them. The inspector is easiest to reach in the office between 7 a.m. and 8 a.m., Monday to Thursday.

The Building Division issues occupancy permits along with building and site permits. While a permit is open, or when a complaint describes a nuisance or a hazard to neighbors, the Building Inspector may enter the property to inspect.

Michigan building code in Burton

FEMA’s Community Status Book lists the City of Burton (community 260287) as a participating National Flood Insurance Program community since 1980, with flood maps dated September 25, 2009.

Michigan enforces one statewide construction code under the Stille-DeRossett-Hale Single State Construction Code Act (1972 PA 230); local units cannot amend it, and enforcement sits with the city, village or township, a county program or the state Bureau of Construction Codes, sometimes split by trade. Michigan rules

Burton permit search and official resources

Burton’s permit records can be searched online by name, address, permit number or parcel number; results show the permit number, applicant, contractor, description of work and estimated value. Copies of an application, permit or plans need a Freedom of Information Act request through the Clerk’s Office at City Hall.

Want this handled start to finish?

Get a free quote →

Burton building permit FAQs

Inspections are where schedules slip.

Get a free quote →

Who issues electrical permits in Burton?

The State of Michigan. Burton does not permit electrical, mechanical or plumbing work; the state issues and inspects those permits.

Do I need a permit for a shed in Burton?

The city’s FAQ calls a structure of less than 199 sq ft a shed, which needs a site permit; at 200 sq ft or more it counts as a garage and needs a building permit.

Do I need a permit for a deck?

Yes, unless it is free-standing at least 10 feet from the house and under 200 sq ft.

Can a homeowner pull a permit?

Yes. For residential work the property owner or a licensed contractor can pull the city permit, and the permit holder is liable for the work.

How long does a Burton permit take?

Normally 2 to 3 days for a residential application and 7 to 10 days for a commercial one.

Does finishing a basement need a permit?

Yes, and the city says an egress window is required.

How do I get copies of old permits or plans?

Search the online permit information, then file a FOIA request with the Clerk’s Office for copies.

Simplify Burton permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Michigan. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Burton sooner?

Let Alliance prepare, file, and track your Burton permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Burton permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.