Inside the City of Fenton, permits come from the city’s Protective Inspection Department (building, zoning and code enforcement) at City Hall, 301 South Leroy Street (810-629-2261). It issues building, electrical, mechanical and plumbing permits as well as zoning permits, and forms can be returned in person, by mail, fax or email. Under the fee schedule effective July 1, 2026, a $20,000 project pays a $297 building permit fee, and a new house also posts a $1,500 cash bond. Fenton Charter Township is a separate government with its own program.
What requires a building permit in Fenton?
Fenton applies the state construction code’s permit rules and its own ordinances. Its forms and fee schedule show the permits and approvals it issues:
Building and trade permits
- New houses and duplexes, additions and detached garages (each with a plan review fee)
- Commercial and industrial buildings, priced by value and reviewed by building volume
- Electrical, mechanical and plumbing work, each on its own city form
- Signs (with a city sign permit and a sign erector’s license)
- Temporary construction trailers, with a $600 deposit
Zoning approvals
- Zoning permits for one- and two-family homes and for other uses
- A certificate of occupancy where no construction permit is involved
- Site plans, special land uses, temporary land uses and planned unit developments
- Lot splits and combinations, and rezonings
- Variances from the Zoning Board of Appeals
Grading plans are required for all new construction and for any project with a major grade change, and work in a street right-of-way needs a cash bond. If you are unsure whether a smaller job needs a permit, call the department before you start.
What the city decides and what the state holds
The construction code is the state’s and the city cannot amend it. Fenton chose to enforce all four parts itself, as its mission statement puts it, administering the state construction code and city ordinances, and it sets its own fees, bonds, zoning ordinance, rental inspection program and appeal boards.
Fenton building department: who handles permitting
The state’s Statewide Jurisdiction List (Bureau of Construction Codes, revised November 6, 2026) marks the City of Fenton LOCAL for building, electrical, mechanical and plumbing, and the city’s own electrical form says the city is responsible for electrical code enforcement within its limits. Genesee County has no county construction code program. Fenton Charter Township is a separate government that runs its own construction code program, so confirm which one your address is in.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | City Hall, 301 South Leroy Street, Fenton, MI 48430 |
| Phone / fax | 810-629-2261 / 810-629-2004 |
| Inspection line | 810-629-2261, 24 hours |
| Hours | Monday to Thursday 8 a.m. to 5 p.m.; Friday 8:30 a.m. to noon |
| Divisions | Building; Zoning; Code and Ordinance Enforcement |
The Genesee County part of Fenton had 11,749 residents in the Census Bureau’s 2025 estimate. Besides permits, the department runs rental housing and existing-building inspections under the property maintenance code and enforces city ordinances on junk cars, grass and weeds, trash, blight and nuisances.
Fenton permit types and what comes first
All city forms are on the Application Forms page; return them to City Hall in person, by mail, by fax to 810-629-2004 or by email. The building forms are split into residential and commercial applications, with separate electrical, mechanical and plumbing permit applications.
Residential permits
The city’s residential new construction plan review checklist sets out what a house submittal must show. Construction documents are submitted electronically, fully dimensioned, drawn at no less than 1/8 inch to 1 foot on sheets no larger than 24 by 36 inches, with the whole scope of work identified. Buildings of 3,500 square feet or more need an architect’s or engineer’s certification. The plans should show the foundation (footings, column pads, beams, drain tile, ground-water control and the concrete-encased electrode), each floor with room uses, joist and rafter sizes and spans, stairs, smoke and carbon monoxide alarm locations and egress windows, the garage slab, roof framing and wall sections.
Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
Commercial and industrial plan review is priced by the cubic feet of building area, and every project other than a detached single-family home and its accessory buildings puts down a cash deposit, set by the Building/Zoning Administrator, to pay the city’s engineering, planning, traffic, environmental, sound and legal consultants; unused money is refunded. New commercial buildings also post a performance bond of 5% of the building cost (minimum $7,000).
For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
What comes before the building permit
Zoning comes first: the city’s zoning permit application says zoning approval is required before any construction plan review. Attach a plot drawing that shows the lot size, every structure with its size, and the setbacks from all property lines and distances between structures, including porches, decks, pools, sidewalks and driveways. If the plan does not meet the zoning ordinance, the owner must either win a variance or change the plan, and a changed plan is reviewed again.
Not sure this scope needs a permit?
Get a free quote →- Zoning permit: $70 for a one- or two-family home, $120 for other uses.
- Site plan review by the Planning Commission, which meets on the fourth Thursday of each month, for commercial, institutional and multi-family projects.
- Variances from the Zoning Board of Appeals, which meets on the fourth Tuesday and also hears appeals from decisions of the building inspector and zoning administrator.
- Soil erosion: the Genesee County Drain Commissioner issues soil erosion permits and waivers; its permits and construction office is at 810-732-7870.
- Right-of-way: work in a street right-of-way or touching the road needs a cash performance guarantee under Section 29-4 of the city code.
Fenton permit costs and fees
The city’s Building & Zoning fee schedule took effect on July 1, 2026. The building permit fee comes from a sliding table by construction value, and value is set from the city’s square-foot guideline table for each use group and construction type (for example $110 a square foot for a wood-frame house, type VB), regardless of the actual contract price.
| Item | Fee |
|---|---|
| Building permit, value up to $999 / $1,000 | $79 / $90 |
| Building permit, value $19,001 to $20,000 / $49,001 to $50,000 | $297 / $576 |
| Building permit, value $99,001 to $100,000 | $895, then $8 per $1,000 of value above that |
| Plan review: detached garage or addition under 50% of the house | $80 |
| Plan review: addition over 50% / one-family / two-family dwelling | $190 / $310 / $490 |
| Plan review, commercial | $240 up to 10,000 cubic feet, rising to $4,800 at 200,000 cubic feet, plus $55 per extra 10,000 |
| Zoning permit: one- and two-family / other uses | $70 / $120 |
| Certificate of occupancy only (no construction permit) | $120 |
| Cash bond: new house / addition over 50% / detached garage | $1,500 / $700 / $100 |
| Cash bond: new commercial building / major addition | 5% of cost (min. $7,000) / 3% (min. $3,000) |
| Right-of-way cash bond: residential / non-residential | $2,000 / $4,000 |
| Electrical, mechanical or plumbing application fee | $75 non-refundable, plus item and inspection fees |
| Zoning Board of Appeals, residential / commercial | $250 + $1,000 escrow / $650 + $1,500 escrow |
| Construction Board of Appeals | $750 |
| Rental program: landlord registration / single-family inspection | $50 per landlord / $150 |
Rather talk it over?
Call 1-855-478-4290 →Worked example: a $20,000 addition that is less than half the size of the house pays $297 for the building permit and $80 for plan review. Construction bonds are held for one year and refunded once the final certificate of occupancy is issued; if no certificate is issued within a year, the bond goes to the city.
Trade permits and who may pull them
The city issues electrical, mechanical and plumbing permits itself on its own applications, and its electrical inspector does the inspections. The electrical form starts with a $75 non-refundable application fee and adds items such as $5 per circuit, $6 for each 25 lighting fixtures and $7 per power outlet for ranges and dryers, with $75 for a final or additional inspection; checks are payable to the City of Fenton.
- Homeowners: the electrical form carries a homeowner affidavit for work the owner installs personally in a home he or she lives in or is about to occupy, inspected by the city electrical inspector.
- Contractors: the forms ask for the state license number and expiry, the federal employer number, workers’ compensation carrier and unemployment insurance number, or the reason for an exemption.
- Mechanical: the city’s mechanical form also has a homeowner affidavit, and it adds a rule for fuel tanks: a homeowner may install a tank only if he or she owns it; otherwise a licensed mechanical contractor must install it. Mechanical plans are not needed for a one- or two-family home whose heating and cooling input is 375,000 Btu per hour or less, or for minor alterations.
- Plans: electrical plans are not needed when the service is 400 amps or less and the building is 3,500 square feet or less; larger work needs plans sealed by a Michigan architect or engineer.
Rather not deal with the building department?
Get a free quote →How to apply for a Fenton permit
Check that the address is inside the City of Fenton, not Fenton Charter Township.
File the zoning permit, and a site plan or variance where the project needs one.
Follow the residential plan review checklist, including a grading plan for new construction.
Building and trade applications to City Hall in person, by mail, fax or email; plans electronically.
Plan review, permit fees and any construction or right-of-way bond.
Call 810-629-2261 at least 24 hours ahead.
Review, corrections and what causes delay
Plans that are not dimensioned, not to scale or missing the structural details on the checklist slow a house review. Commercial projects can wait on consultant reviews, which are paid from the applicant’s escrow, and a revised site plan resubmitted within 90 days costs 75% of the original fee.
Inspections and occupancy in Fenton
Call the 24-hour inspection line, 810-629-2261, at least 24 hours before you need an inspection, and give the job location, how the inspector can get in and a contact phone number. No work may be covered until it has been inspected. A trade permit is closed if no inspection is requested and done within six months of issue or of the last inspection, and closed permits cannot be refunded or reinstated.
The final certificate of occupancy also releases the construction bond, so finishing inspections within a year matters on new houses and large additions. Existing rental homes are inspected under the rental program for $150 a single-family unit, or $100 a unit for multi-family buildings inspected in groups of six or more on the same day.
Landlords register on the city’s landlord registration form, listing each rental address, parcel number and last inspection date. The rental inspection report follows the property maintenance code section by section, from exterior areas, pools, stairs and guardrails to plumbing, heating, electrical equipment, egress and fire protection. Every bedroom needs a working smoke detector, as does the main area of each floor, with a carbon monoxide detector near the furnace or sleeping area, and the landlord must send in a furnace inspection report from a licensed HVAC contractor before the rental inspection.
Michigan building code in Fenton
Fenton enforces the state code for all four disciplines through its Protective Inspection Department. FEMA’s Community Status Book lists the City of Fenton (community 260075) as participating in the National Flood Insurance Program, with flood maps effective September 25, 2009, so ask the department whether a lot is in a mapped flood area before you design.
Want this handled start to finish?
Get a free quote →Michigan enforces one statewide construction code under the Stille-DeRossett-Hale Single State Construction Code Act (1972 PA 230); local units cannot amend it, and enforcement sits with the city, village or township, a county program or the state Bureau of Construction Codes, sometimes split by trade. Michigan rules
Fenton permit search and official resources
For copies of permits, plans or inspection records, send a written Freedom of Information Act request to the City Clerk, the city’s FOIA Coordinator, on the city’s paper or online FOIA form. The city has five business days to respond (six if the request arrives by email or fax) and may extend that by 10 days in writing.
- Fenton Building Department / Protective Inspection
- Application forms (building, trade, zoning, sign)
- Building & Zoning fee schedule, effective July 1, 2026
- Residential new construction plan review checklist
- Electrical permit application
- Zoning information
- Planning Commission
- Zoning Board of Appeals
- Code enforcement and rental inspections
- Zoning permit application
- Landlord registration form
- Rental inspection report and guidelines
- Fenton FOIA information
- Genesee County Drain Commissioner: soil erosion permits
- State Statewide Jurisdiction List (Bureau of Construction Codes)
Inspections are where schedules slip.
Get a free quote →Fenton building permit FAQs
Is the City of Fenton the same as Fenton Township?
No. The city’s Protective Inspection Department covers only addresses inside city limits; Fenton Charter Township runs its own program.
How much is a building permit in Fenton?
It follows a value table: $79 under $1,000, $297 at $20,000, $895 at $100,000 and $8 per $1,000 above that, plus plan review.
Does a new house need a bond?
Yes, a $1,500 cash bond, refunded when the final certificate of occupancy is issued within a year.
Can I do my own electrical work?
Yes, in a home you live in or are about to occupy, by signing the homeowner affidavit on the city’s electrical form.
How do I schedule an inspection?
Call 810-629-2261 at least 24 hours ahead with the job location, access details and a contact number.
When do the Planning Commission and ZBA meet?
The Planning Commission on the fourth Thursday and the Zoning Board of Appeals on the fourth Tuesday of each month.
Do rental homes need inspections?
Yes. Landlords register with the city ($50) and each unit is inspected under the property maintenance code; a furnace report from a licensed HVAC contractor is due first.
How much is a zoning permit?
$70 for a one- or two-family home and $120 for other uses under the July 1, 2026 schedule.
Simplify Fenton permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Michigan. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Fenton sooner?
Let Alliance prepare, file, and track your Fenton permits while your crew stays on the job.
More Michigan permitting guides
Genesee County
Read guide →Flint
Read guide →Flint Charter Township
Read guide →Ferndale Building Permit Guide
Read guide →Flat Rock Building Permit Guide
Read guide →Flushing Charter Township Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Fenton permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.