In Zionsville, the Planning & Building Department at Town Hall, 1100 W. Oak St. (317-873-8247, weekdays 8 a.m. to 4 p.m.), reviews and issues improvement location permits (ILPs), which include the building permit, and serves as the town’s Building Commissioner. Under Town Council Ordinance 2024-22 a new house costs $700 plus $0.10 a square foot with five inspections included, and town ordinance gives reviewers up to 5 business days for a residential application and 15 for a commercial one.
What requires a building permit in Zionsville?
The town’s fee ordinance is the clearest list of what it permits: every job it prices needs an ILP, and the department’s forms page adds separate applications for electrical and solar work, re-roofs, sanitary sewer connections and repairs, grading, demolition and construction trailers.
ILP required
- New single-family, two-family and town homes, and multifamily buildings
- Additions, and interior or exterior remodeling
- Detached garages, carports and sheds, including small ones of 200 square feet or less
- Decks at any height, swimming pools and hot tubs
- Roof replacement: the town’s roofing FAQ says shingle replacement needs a permit and an inspection
- Patios and electrical work (priced as “other residential”), demolition and sewer repairs
- New commercial, industrial and special-use buildings, additions, tenant finishes and parking lots
No ILP
- Fences: the fee ordinance says no ILP is required and no fee is charged
A permit from the town does not replace approval from a homeowners association, which the department tells owners to get separately. Construction noise is limited to 7 a.m. to 7 p.m.: Monday to Sunday in the rural district, where the Boone County Sheriff enforces it, and Monday to Saturday with no Sunday work in the urban district, where Zionsville Police enforce it.
What Zionsville decides and what the state holds
Zionsville sets its own zoning, subdivision and architectural review rules, adopts its permit, fire, park and road impact fees by ordinance, runs its own sewer utility and stormwater program, and adopted a new comprehensive plan, Uniquely Zionsville, on June 15, 2026. The construction codes come from the state; the town’s forms commit the applicant to follow the Building Commissioner’s directions under them, and Class 1 buildings still need the state Construction Design Release.
Zionsville building department: who handles permitting
One department reviews Plan Commission and BZA filings, ILPs and sign permits, assigns addresses, handles easement encroachment requests, enforces building, town and zoning code, staffs the Plan Commission, BZA and Architectural Review Committee, and acts as Building Commissioner. Two other town units inspect alongside it: the Zionsville Fire Department for Class 1 buildings and Public Works for stormwater and erosion control.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Planning & Building Department, Town Hall, 1100 W. Oak St., Zionsville, IN 46077 |
| Phone | 317-873-8247 (Town Hall main line 317-873-5410) |
| Hours | Monday to Friday, 8 a.m. to 4 p.m.; paper filings at the front desk in those hours |
| Inspection requests | inspectionrequest@zionsville-in.gov; inspection times 317-832-6135, 8 to 9 a.m. on the day |
| Boards | Plan Commission (rules adopted June 15, 2026), Board of Zoning Appeals, Architectural Review Committee |
Zionsville runs its own building office, so the Boone County Area Plan Commission, which covers unincorporated land and Advance, does not permit work inside the town (see the Boone County guide).
Zionsville permit types
Residential permits
Homes use two writable ILP forms: one for new single-family, two-family and town homes, and one for additions, remodels and accessory structures. The new-home form asks for the sewer provider and permit number (Town of Zionsville, TriCo Regional Sewer Utility, Whitestown Municipal Sewers, or a Boone County Health Department septic permit), any stormwater, drainage and driveway permit numbers, BZA or Plan Commission docket numbers, floor area including the attached garage, lot coverage, setbacks and height, the energy code path, and the flood zone. The plan review checklist calls for scaled drawings, a plot plan, an erosion and sediment control plan, footing, slab, foundation and framing details, elevations, floor plans, a wall section, a roof framing plan and a stair section.
- Electrical and solar: the town’s electrical permit covers new services, upgrades and ground- or roof-mounted solar; roof systems need a written structural evaluation of the roof.
- Re-roof and sewer repair: issued on a walk-in basis.
- Owner authorization: needed when the applicant is not the owner.
Building or remodeling a home here? Alliance handles residential permit filing, so the crew isn't waiting on the counter.
Commercial permits
Commercial ILPs cover multifamily buildings, new business, industrial and special-use buildings, additions, tenant finishes and parking lots. The Fire Department reviews construction plans and permits sprinklers, fire alarms and hood suppression, and inspects Class 1 buildings jointly with the town; commercial work also pays the Boone County Economic Development fee, which starts at $100 for a building under 20,000 square feet. Some commercial inspections still need two days’ notice. Before the 3% yearly increase that has applied to fire department charges each January since 2025, fire fees were $100 for each sprinkler riser or system, each fire alarm zone and each hood suppression system, $75 for a fire department occupancy permit, and $250 a day for occupying without one.
For tenant improvements and new commercial builds, Alliance handles commercial permit expediting through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Zoning approvals. Rezonings, plats and development plans go to the Plan Commission and variances and special exceptions to the BZA; the town publishes 2026 meeting dates and filing deadlines with public notice rules.
- Sewer or septic. Choose the right provider on the form; a septic system needs a Boone County Health Department permit.
- Stormwater and driveway. An individual lot stormwater permit and any right-of-way permit are charged under town code sections listed in the fee ordinance.
- Floodplain. A site in a flood zone needs an elevation certificate signed by a land surveyor, engineer or architect.
- Road impact fee estimate. The town has a request form for an estimate before you file.
Zionsville permit costs and fees
Permit fees come from the town fee schedule adopted as Town Council Ordinance 2024-22, effective September 4, 2024. ILP fees include the building permit and a set number of inspections; square footage means gross area above grade.
| Permit | Fee |
|---|---|
| New single- or two-family dwelling | $700 + $0.10 per sq ft (5 inspections) |
| Addition, or interior and exterior remodeling | $360, plus $0.10 per sq ft over 400 sq ft (4 inspections) |
| Large detached accessory building (garage, carport) / one of 200 sq ft or less | $200, plus $0.10 per sq ft over 200 sq ft (2 inspections) / $100 |
| Pool or hot tub | $350 + $0.10 per sq ft of pool and deck (2 inspections) |
| Deck up to 30 in. / over 30 in. above grade | $75 / $175 |
| Other residential (roofing, patio, electrical) | $75 |
| Residential demolition | $100 + $50 per additional building |
| Multifamily primary building | $500 + $100 per unit |
| New business, industrial or special-use building, or addition | $500 + $0.17 per sq ft |
| Interior remodel or tenant finish | $350 + $0.17 per sq ft |
| Certificate of occupancy | $50 per house or unit; $25 accessory |
| Re-inspection | $75 residential; $150 commercial |
| Permit extension / expired permit renewal | $50 (up to 6 months) / $250 |
| Fire plan review | $0.10 per sq ft, $75 minimum, plus 3% a year since 2025 |
| Park impact fee (2022 update) | $2,045 per single-family unit; $941 per multi-family unit |
| Road impact fee (Ord. 2023-23) | $278.35 per 24-hour generated trip |
Rather talk it over?
Call 1-855-478-4290 →Worked example: a new 3,000-square-foot house is $700 + (3,000 × $0.10) = $1,000 for the ILP, plus the $50 certificate of occupancy and the $2,045 park impact fee, before road impact, sewer and stormwater charges. Starting work before the ILP multiplies the fee by five, capped at $5,000 plus the normal fee, and covering work before a required inspection adds a late fee of $350 on a new house, $500 on a new commercial building, and $150 or $250 on other jobs. Churches and other nonprofits with 501(c)(3) papers pay half, and Zionsville Community School Corporation buildings pay no ILP fees except commercial inspection fees, which are halved. When the town hires an outside consultant to review plans, it may bill that cost, payable before the BZA or Plan Commission hearing or before the permit, whichever comes first.
Trade permits and who may pull them
Most trade work in Zionsville rides on the ILP: a new house fee covers the rough inspection of framing, plumbing, heating, electric, meter base and low voltage. Stand-alone jobs use their own forms.
- Electrical and solar: a separate electrical permit for services, upgrades and solar arrays; the white “approved” electric sticker must be on the temporary pole or meter base before Boone REMC or Duke Energy will energize.
- Plumbing and sewer: sewer connections and repairs use the town sanitary sewer permit, and the town inspects sewers on the Zionsville Sewer Utility; plumbing contractors carry the state license.
- Fire protection: sprinklers, alarms and hood suppression are permitted and inspected by the Fire Department; installing one without a fire protection permit brings a stop-work order and five times the normal fee.
- Contractors and owners: the applicant is listed as builder or contractor, with an owner authorization form when someone else applies; the fee ordinance sets no town contractor license fee.
Rather not deal with the building department?
Get a free quote →How to apply for a Zionsville building permit
Get any rezoning, plat, development plan, variance or architectural review approval and note the docket numbers for the ILP form.
Confirm the sewer provider or septic permit, the stormwater and driveway permits, and an elevation certificate in a flood zone.
Use the new-home form or the additions, remodels and accessory structures form, plus the owner authorization if needed.
Send the form, plans, plot plan and erosion control plan to the department staff named on the forms page, or mail or drop paper at the Town Hall front desk.
Applications are reviewed in the order received: up to 5 business days for residential and 15 for commercial. There is no paid expedited review.
A permit is valid for one year after issuance, with one extension of up to six months if you ask before it expires.
Review, corrections and what causes delay
A package without the plot plan, the erosion and sediment control plan or the energy code path does not meet the town’s basic plan review requirements, and the electrical and solar form warns that incomplete forms will not be processed, which includes roof-mounted solar without a structural evaluation. Re-roof and sewer repair permits skip the queue because they are issued over the counter. An amended ILP after issuance costs $125 for a home or $150 for commercial work.
Inspections and certificates of occupancy
Since January 1, 2023 inspections are booked only by email to inspectionrequest@zionsville-in.gov, one email per permit, with the permit number and address in the subject line and the inspection type, the requester’s name and phone, and the date wanted. Requests received by 3 p.m. are scheduled for the next business day. Staff set the time; call 317-832-6135 between 8 and 9 a.m. that day to hear it. Cancel by email before 9 a.m. or the inspection is charged.
The town’s green sheet lists the residential stages: footing (erosion control in place, do not pour first), foundation drainage tile, foundation and under-slab, temporary electric, sewer, exterior veneer, rough-in, energy, and final. Decks over 30 inches need footing, framing and final inspections, pools at least three, and re-roofs a final. No affidavits replace an inspection, each re-inspection is $75, and a certificate of occupancy is issued only after every inspection is passed and all fees are paid; do not move in, even furniture, before the final.
Indiana building code in Zionsville
The town enforces the adopted state building codes and holds roofers to the shingle manufacturer’s installation instructions as a code requirement. FEMA’s Community Status Book lists the Town of Zionsville (community 180016) as participating in the National Flood Insurance Program, with flood maps effective January 18, 2012.
Want this handled start to finish?
Get a free quote →Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana
Zionsville permit search and official resources
The department’s Reports page links its monthly and yearly reports. For the file on a particular address, such as a past ILP, inspection results or a certificate of occupancy, contact the Planning & Building Department at 317-873-8247; a zoning confirmation letter costs $90 and a zoning determination $100.
- Zionsville Planning & Building Department
- Permit applications and forms
- Permit information and guidelines
- Town fee schedule, Ordinance 2024-22
- ILP application for new single-family, two-family and town homes
- Basic requirements for residential plan review
- Electrical and solar energy system permit
- Inspections page
- How to schedule a residential inspection
- Required residential inspections (green sheet)
- Roofing FAQ
- Road impact fee ordinance 2023-23
- Park impact fee update (2022)
- Planning department FAQs
- FEMA Community Status Book, Indiana
Inspections are where schedules slip.
Get a free quote →Zionsville building permit FAQs
Do I need a permit to build a fence in Zionsville?
No ILP and no fee are required for a fence under the town fee ordinance, though your HOA may still need to approve it.
Do I need a permit to replace my roof?
Yes. A re-roof permit and a final inspection are required, and re-roof permits are issued on a walk-in basis.
How much is a permit for a new house?
$700 plus $0.10 a square foot of gross above-grade area, with five inspections included; a 3,000-square-foot house is $1,000 plus the $50 certificate of occupancy and impact fees.
How long does plan review take?
Up to 5 business days for residential and 15 for commercial applications, in the order received; the town does not offer expedited review.
How do I schedule an inspection?
Email inspectionrequest@zionsville-in.gov by 3 p.m. the business day before, one email per permit.
How long is my permit good for?
One year from issuance, with one extension of up to six months for $50 if you ask before it expires.
Can I work on Sunday?
In the rural district, yes, between 7 a.m. and 7 p.m.; in the urban district no construction work is allowed on Sunday.
Simplify Zionsville permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Zionsville sooner?
Let Alliance prepare, file, and track your Zionsville permits while your crew stays on the job.
More Indiana permitting guides
Boone County
Read guide →Lebanon
Read guide →Whitestown
Read guide →Adams County Building Permit Guide
Read guide →Allen County Building Permit Guide
Read guide →Anderson Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Zionsville permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.