The City of Washington’s Building Commission, led by Building Commissioner Jon Casper at 2113 Memorial Avenue ((812) 254-8208), permits new construction, additions, re-roofs, storage sheds, fences, pools, signs and demolitions both inside the city and within the two-mile extraterritorial area the city zones. Either the owner or the contractor may take out the permit, and it must be in hand before work starts. The city lists its minimum permit fee as 10 cents per square foot of first-floor area, and siding, replacement windows and doors and remodeling need no permit at all.
What requires a building permit in Washington?
The Building Commission names the work it permits: all new construction, additions, storage sheds, re-roofs, fences, pools, signs and demolitions. It also names what does not need a permit: new siding, replacement windows, replacement doors and remodeling. The rule covers the city limits and the two-mile ring outside them, where the city also administers zoning.
Permit required
- New houses and commercial buildings
- Additions
- Storage sheds and other new accessory buildings
- Re-roofing
- Fences and swimming pools
- Signs
- Demolition
No permit needed
- Siding
- Replacement windows
- Replacement doors
- Remodeling
A pool 18 inches deep or more must be enclosed by a wall or fence at least 5 feet high with lockable latches, and both the pool and the fence need permits. An electrical service that has been red-tagged goes back through the Building Commissioner, who inspects it and tells the owner or electrician what must be fixed.
What Washington decides and what the state holds
The city decides which projects need a permit, sets its fees, zones the city and the two-mile area, and enforces its own ordinances; its code enforcement officers work inside the city limits only, not in the outlying ring. Building standards are the statewide codes of the Fire Prevention and Building Safety Commission. A Class 1 building — anything open to the public, with three or more tenants, or used by employees — needs a Construction Design Release from the Indiana Department of Homeland Security or a certified local unit before construction starts, unless 675 IAC 12-6-4 exempts the work. The city’s code of ordinances is published on American Legal.
Washington building department: who handles permitting
The Building Commission handles planning, zoning, permits, inspections and city ordinance enforcement in one office. Its staff process Plan Commission and Board of Zoning Appeals cases, prepare documents, set hearings and publish legal notices, and the commission’s secretary keeps both boards’ records. Outside the two-mile ring, Daviess County’s Building & Compliance Department and Advisory Plan Commission handle improvement location permits, so check which side of the line a parcel is on before applying. Because both city boards rule on cases in the ring as well as inside the city, the County Commissioners appoint two members of each board who live outside the city limits but within the two-mile area.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Building Commission, 2113 Memorial Avenue, Washington, IN 47501 |
| Phone | (812) 254-8208 |
| Hours | Monday to Friday; the department page says 7:00 a.m. to 4:00 p.m. and the permits page 7:30 a.m. to 4:00 p.m. |
| City Hall | 101 N.E. Third Street; Mayor’s Office and Council Chambers at 200 Harned Avenue |
| Building Commissioner | Jon Casper |
| Area served | City limits and the two-mile extraterritorial zoning area |
| Plan review support | City Engineering Department, 2100 Memorial Avenue, (812) 254-5171, for subdivisions, commercial and industrial sites and stormwater |
| Boards | Plan Commission, second Wednesday; Board of Zoning Appeals, fourth Wednesday; both 6:30 p.m. at 200 Harned Avenue, as needed |
Washington permit types
Permits are issued at the Building Commission counter; the city publishes zoning applications online but no building permit form, so call (812) 254-8208 or stop in to start. Either the owner or the contractor may sign for the permit.
Residential permits
- New houses and additions. Priced from first-floor square footage; ask the office for the lot’s zoning before drawing the site layout, since setbacks and lot size are zoning rules.
- Sheds and garages. Storage sheds are on the commission’s list of permitted work, along with all new construction.
- Fences and pools. Each needs a permit, and a pool at least 18 inches deep needs a 5-foot enclosure with lockable latches.
- Roofs. A re-roof needs a permit even though siding and replacement windows do not.
- Mobile homes. Mobile home placement is one of the conditional uses the Board of Zoning Appeals hears.
- Rental units. Since September 1, 2026, a residential rental in the city needs a rental permit and inspection under Chapter 158.
Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
Commercial and industrial projects follow the same counter process, with plans and stormwater runoff calculations reviewed by the city’s Engineering Department for the Building Commissioner and Plan Commission. Sites in the US 50 Overlay Zone, the I-69 corridor overlay zone or the EZ zoning district go to the Plan Commission for improvements, waivers and conditional uses, using the city’s overlay application. Signs need their own permit, and sign size and placement variances go to the Board of Zoning Appeals.
Not sure this scope needs a permit?
Get a free quote →For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning. Call (812) 254-8208 to learn a parcel’s zoning. A rezoning goes to the Plan Commission; variances for lot size, setbacks, fences, signs and building height or size, and conditional uses such as a business in a residential zone, go to the Board of Zoning Appeals.
- Hearing notice. Under the board’s rules of August 26, 2026, owners near the site must be sent notice at least 10 days before the hearing by certified mail or certificate of mailing, using an adjoiner list from the Daviess County GIS no older than 90 days, and a legal notice runs in the Washington Times Herald.
- Stormwater. Development plans must meet the Washington Stormwater Technical Standards Manual of October 11, 2024, reviewed by the Engineering Department; the Storm Water Department (169 South 200 West, (812) 254-2792) bills monthly fees on impervious area.
- State design release. Class 1 projects need the state Construction Design Release before construction begins.
- Utilities. Washington Power & Light, the water department and the wastewater department are city utilities, with meters and billing handled by the Utility Office at 2100 Memorial Avenue.
- City streets. For a road problem outside the county’s jurisdiction, such as a city street, the Daviess County Highway Department lists the City of Washington at 812-254-4564.
Washington permit costs and fees
The Building Commission’s permits page gives one building permit figure: a minimum fee of 10 cents per square foot for the first floor. The page lists no separate charges for fences, pools, signs or demolition, so ask the office for the amount when you apply. The figures below are the ones the city publishes.
| Item | Fee |
|---|---|
| Building permit, minimum basis | $0.10 per sq ft of first-floor area |
| Variance or conditional use application | $50, paid to the City of Washington (Ordinance 392, Sec. 24, per the application) |
| Rental permit (Chapter 158) | $5 per structure |
| Rental inspection | $75 per rental unit, due by the inspection date |
| Landlord of record on January 1, 2026 not registered by September 1, 2026 | $100 per day, up to $1,000 |
| Stormwater user fee | Monthly, based on impervious surface area |
Rather talk it over?
Call 1-855-478-4290 →Example from the published rate: a house with a 1,600-square-foot first floor works out to 1,600 × $0.10, or $160, on the minimum basis. Because the page calls this a minimum fee, the actual permit can be higher once the office applies the full ordinance; get the figure from the Building Commission before you budget. The application says the variance fee offsets the cost of advertising the hearing. The Sidewalk Replacement Program splits a sidewalk job: the city removes the old walk, prepares the area and pays for materials, and the owner pays a city-approved contractor for the labor.
Trade permits and who may pull them
The Building Commission’s pages describe one permit per project and say that either the owner or the contractor may obtain it. They do not list separate electrical, plumbing or mechanical permit forms or fees, so ask the office which trade work your permit covers and which inspections it needs.
- Electrical. A red-tagged electrical service is cleared by the Building Commissioner, who inspects it and tells the owner or electrician what to fix. Washington Power & Light is the city’s municipal electric utility.
- Plumbing. Plumbing contractors need an Indiana plumbing contractor license from the Plumbing Commission; new sewer and water service comes from the city’s wastewater and water departments.
- Contractors. The city’s published pages do not describe a local contractor license or registration; the city code on American Legal is where one would appear, so ask the Building Commission before work starts.
- Owners. The city lets an owner take out the permit for the owner’s own project, in the same way as a contractor.
How to apply for a Washington building permit
Check that the parcel is inside the city or the two-mile ring; beyond it, Daviess County handles the improvement location permit.
Call (812) 254-8208 for the parcel’s zoning and setbacks.
File a variance, conditional use, rezoning or overlay application and get the deadline date from the office; hearings are held as needed on the second (Plan Commission) and fourth (BZA) Wednesdays.
Commercial and other Class 1 buildings need the state Construction Design Release first.
Bring the plans, first-floor area and site details to 2113 Memorial Avenue; owner or contractor may apply.
Pay the fee the office calculates and keep the permit on site; work may not begin before it is issued.
Rather not deal with the building department?
Get a free quote →Review, corrections and what causes delay
Zoning cases are the usual source of delay: they are heard only when the boards meet, and a missed deadline or late notice to neighbors pushes the case to the next month. Commercial, industrial and subdivision plans wait on the Engineering Department’s review of stormwater calculations against the 2024 standards manual. Since January 1, 2026, Indiana gives units three business days to say whether a one- or two-family application is complete and seven business days to review its plans, and the applicant may hire a qualified private reviewer or inspector instead, at the applicant’s own cost.
Inspections and certificates in Washington
Inspections are scheduled with the Building Commission at (812) 254-8208. When the permit is issued, ask which visits your project needs and how much notice to give. The Building Commissioner also inspects red-tagged electrical services and tells the owner or electrician what must be corrected.
Rental housing has its own inspections under Chapter 158, adopted by Ordinance 21-2025 on January 29, 2026 and amended by Ordinance 8-2026. Owners renting a dwelling unit in the city need a rental permit or conditional rental permit from the Building Commissioner’s office, issued in the owner’s name for that unit, and pay $75 for each unit inspected. Single-family rentals listed for sale are not exempt; an inspection done before a sale transfers with the property for 90 days, and the new owner must schedule a new one within those 90 days. Affidavit forms cover family rentals under Section 158.05B and properties that are not rented.
Indiana building code in Washington
The Building Commission enforces the statewide codes alongside the city’s zoning ordinance and code of ordinances. FEMA’s Community Status Book lists the City of Washington (community 180037) among participating communities in the National Flood Insurance Program, with a regular-program date of August 8, 1979 and no flood map date shown in its row; ask the Building Commission whether a parcel lies in a mapped flood area.
Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana
Want this handled start to finish?
Get a free quote →Washington permit search and official resources
For an old permit, zoning decision or rental inspection, ask the Building Commission at (812) 254-8208; board minutes and the commission’s records are kept in its office, and the city’s document center posts council and board agendas. Property lines and owner names for hearing notices come from the Daviess County GIS.
- Washington Building Commission
- Permits and zoning information
- Building Commission staff and services
- Plan Commission
- Board of Zoning Appeals
- Rules and Procedures of the BZA (August 26, 2026)
- Variance application
- Conditional use application
- Rezoning application
- Overlay district applications
- Ordinance 21-2025, rental dwellings
- Ordinance 8-2026, rental permit deadline
- Rental structure registration form
- Engineering Department
- Storm Water Department and technical standards
- IDHS building plan review and design releases
- FEMA Community Status Book, Indiana
Inspections are where schedules slip.
Get a free quote →Washington building permit FAQs
Do I need a permit to replace windows or siding in Washington?
No. The city says siding, replacement windows, replacement doors and remodeling need no permit; a re-roof does.
How much is a building permit?
The published minimum is 10 cents per square foot of first-floor area, so a 1,600-square-foot first floor starts at $160; ask the office for the final figure.
Does the city permit land outside the city limits?
Yes, within two miles of the limits, where the Building Commission administers zoning and issues permits; beyond that, Daviess County does.
Do I need a permit for a fence or pool?
Yes, both. A pool 18 inches deep or more needs a fence or wall at least 5 feet high with lockable latches.
Can a homeowner get the permit?
Yes. The city says the owner or the contractor may obtain the permit.
Do rental properties need a city permit?
Yes. Since September 1, 2026, rentals need a rental permit ($5 per structure) and an inspection ($75 per unit) under Chapter 158.
When do the zoning boards meet?
As needed: the Plan Commission on the second Wednesday and the Board of Zoning Appeals on the fourth Wednesday, at 6:30 p.m. at 200 Harned Avenue.
Simplify Washington permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Washington sooner?
Let Alliance prepare, file, and track your Washington permits while your crew stays on the job.
More Indiana permitting guides
Daviess County
Read guide →Knox County
Read guide →Pike County
Read guide →Washington County Building Permit Guide
Read guide →Wayne County Building Permit Guide
Read guide →Wells County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Washington permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.