In the City of Madison, building permits come from the Building and Design Division of the Office of Planning, Preservation and Design at City Hall, 101 West Main Street (812-265-8324). The city prefers applications through its OpenGov permit portal but accepts paper, holds every permit until all contractors and subcontractors are registered ($50 a year), and charges a residential application fee of $50 plus $0.10 per square foot. Exterior work downtown needs a Certificate of Appropriateness first, and the Unified Development Ordinance adopted on March 17, 2026 sets the zoning rules.
What requires a building permit in Madison?
Section 7.10 of the Unified Development Ordinance (UDO) requires a building permit to erect, build, install, move, add to or alter any structure unless the UDO exempts it, and no change of use may happen without the required permits.
Permit required
- All new primary structures
- Accessory structures over 200 square feet
- Any structure with a component that needs a permit under other codes, such as electrical work
- Wireless facilities, new towers, small cells and collocations
- Permanent signs
- Non-residential fences, walls and retaining walls
- Temporary uses and structures, including construction trailers and storage containers
No building permit
- Landscaping
- Accessory structures of 200 square feet or less, such as swing sets and mailboxes
- Temporary signs allowed by the UDO
- Home utility installations such as cable, fiber and Wi-Fi (solar and wind are not exempt)
- Ponds and drainage installations
- Residential fences, walls and retaining walls
Exempt work must still meet the UDO’s standards. Separate permits cover temporary uses and structures, dumpsters, and any development in the Hillside (HS) district.
What the city decides and what the state holds
The Madison City Council approved the UDO on second reading on March 17, 2026, replacing outdated regulations with a single development code. It applies inside the city and in the extraterritorial jurisdiction allowed by state law and the city’s Ordinance 1963-66, and its subdivision rules reach that area too because the Jefferson County Plan Commission has not adopted subdivision control there. The Jefferson County Plan Commission has rescheduled its public hearing on the Two-Mile Buffer Zone to December 9, 2026 at 5:30 p.m. at the county fairgrounds. Building codes themselves come from the state: commercial and industrial projects need all state approvals, including the design release, before the city permit.
Madison building department: who handles permitting
The Office of Planning, Preservation and Design brings together the Building Inspector, who reviews plans, issues building permits and inspects, a Code Enforcement Officer who is also the city’s Floodplain Administrator and stormwater (MS4) coordinator, a Historic Preservationist who processes Certificates of Appropriateness, and a Planner who supports the Plan Commission and the Board of Zoning Appeals.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Planning, Preservation and Design, City Hall, 101 West Main Street, Madison, IN 47250 |
| Phone | 812-265-8324 (City Hall 812-265-8300) |
| Hours | 8 a.m. to 4 p.m., Monday through Friday |
| Online | OpenGov permit portal; contractor registration report on ViewPoint Cloud |
| Plan Commission | 5:30 p.m., second Monday, City Hall Council Chambers |
| Board of Zoning Appeals | 6 p.m., second Monday, City Hall Council Chambers |
| Historic District Board of Review | 5:30 p.m., fourth Monday (third Monday in December) |
The Plan Commission’s nine members include two county appointees, and one Board of Zoning Appeals member is appointed by the Plan Commission for the buffer zone. Outside that area, the rest of Jefferson County is handled by the county’s Planning, Zoning & Building Inspection office.
Madison permit types
Forms PPD-B-01 and the related applications can be submitted on the OpenGov portal or on paper at City Hall. The building permit application lists the building types it covers: accessory building, addition, electric service, HVAC, new structure, plumbing service, remodel and sign.
Residential permits
A house or remodel needs a plat or sketch of the site showing the lot boundaries, plans and specifications, the cost of construction and the square footage, an 811 utility-locate confirmation number and any approval dates from the Historic District Board of Review, the BZA or the Plan Commission. Foundations can be permitted separately on a Residential Foundation Permit Application, and manufactured or mobile homes use a placement application.
Building or remodeling a home here? Alliance handles residential permit filing, so the crew isn't waiting on the counter.
Commercial permits
For a commercial building the city needs a copy of the state Construction Design Release and a full set of plans identical to the released plans, a stormwater drainage plan by a design professional for the Building Inspector and the Plan Commission, the acreage to be disturbed and the date of any Construction Stormwater General Permit. The applicant signs a Commercial Construction Authentication Agreement certifying that the plans include all the work, and must file any state-approved plan changes before that part of the work proceeds. A Commercial Foundation Permit Application is also on the city’s forms list.
For tenant improvements and new commercial builds, Alliance handles commercial permit expediting through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Historic district. Every exterior change visible from a street or alley in the Madison Historic District, which covers all of downtown from the toe of the hill to the Ohio River, needs a Certificate of Appropriateness before the building permit. The Historic District Board of Review has seven members appointed by the mayor with Common Council approval; staff can approve some applications, and the rest are heard monthly. File at least 15 days before the board meets.
- Hillside. In the Hillside district, new primary and accessory structures need development plan approval, buildings needing a permit must be designed and stamped by an Indiana-licensed engineer or architect, and no clearing, filling or driveway work may start without a hillside permit.
- Septic. A parcel on a septic system needs the septic permit first; the Jefferson County Health Department charges $200 and requires a certified contractor.
- Zoning relief. Variances and special exceptions go to the BZA; setback applications, rezonings and preliminary subdivisions to the Plan Commission.
- Riverfront and floodplain. In the Riverfront district, no enclosed occupiable space may sit below the Flood Protection Grade, two feet above the IDNR Base Flood Elevation, except quickly cleared parking, storage or utility space; Chapter 156 of the city code holds the floodplain regulations.
Madison permit costs and fees
Madison prints its building fees on its permit forms (Form PPD-B-01, revision 2 of January 12, 2024), and the UDO says building permit fees are paid under the adopted fee schedule. Planning and zoning fees are on a separate Plan Commission and BZA fee schedule.
| Permit | Fee |
|---|---|
| Residential new structure or remodel | $50 application fee + $0.10 per sq ft |
| Commercial new structure or remodel | $100 application fee + $0.10 per sq ft |
| Residential / commercial foundation permit application | $50 / $100 |
| Manufactured or mobile home placement | $25 + $0.10 per sq ft |
| Demolition permit application | $25 |
| Contractor registration, new or yearly renewal | $50 |
| Certificate of Appropriateness: staff review / board hearing | $10 / $25 + $15 ad fee + $2 per street for signs |
| Variance or special exception | $200 rural and residential districts; $400 other districts |
| Solar, battery storage or wind special exception | $1,000 + $5 per acre over 10 acres |
| Zone map change / planned unit development | $500 / $750 |
| Development plan / for solar, battery storage or wind | $300 / $1,000 |
| Primary plat / minor subdivision plat | $500 + $25 per lot / $300 |
| Hillside application / zoning verification / administrative appeal | $50 / $25 / $50 |
Rather talk it over?
Call 1-855-478-4290 →Worked example from the form: a new house of 2,000 square feet is $50 + (2,000 × $0.10) = $250; a 400-square-foot residential remodel is $50 + $40 = $90. Plan Commission and BZA applications can be resubmitted three times free; the fourth and later resubmittals cost $125 each. BZA fees may be paid in cash, by check to the City of Madison or online.
Trade permits and who may pull them
Electric service, HVAC and plumbing service are building types on the same city application rather than separate permits, and the form lists the business doing each trade. What Madison adds is contractor registration:
- Who must register: every general and specialized contractor doing new construction, or alterations or repairs on structures over 100 square feet or costing the owner more than $500, registers with the Plan Commission each year for $50 with a certificate of insurance. Handymen whose repair or maintenance work needs no building permit are exempt.
- Plumbers: must give the city a copy of their State of Indiana plumbing license when they register or renew.
- Timing: registrations last a year and must be renewed by 4:00 p.m. on the expiration date, and building permits are held until every contractor and subcontractor on the job is registered and current. A public contractor registration report is online.
The city’s pages do not describe a homeowner exemption from registration for owners doing their own work, so ask the office before you start.
How to apply for a Madison building permit
Find the parcel’s UDO district and whether it is in the historic, hillside, riverfront or flood areas.
Certificate of Appropriateness, BZA or Plan Commission decisions, hillside permit and septic permit as needed.
Make sure every contractor and subcontractor holds a current Madison registration.
Note the 811 confirmation number and gather the site sketch, plans and, for commercial work, the state release and drainage plan.
Submit through OpenGov, or on paper at City Hall, with the fee.
Keep the permit displayed on the property and schedule the required inspections.
Rather not deal with the building department?
Get a free quote →Review, corrections and what causes delay
A common hold-up is an unregistered or expired contractor, since the city will not release a permit until all are current. Commercial jobs wait for the state release and the drainage plan, and historic and hillside approvals add a board cycle. Under the UDO, construction must start within six months of issue and be substantially complete within 18 months; the Administrator may grant one extension of up to six months if work has begun, and an expired permit needs a new application and fee. Amendments to an approved permit can be filed at any time and may carry an extra fee.
Inspections and certificates of occupancy
The Building Inspector inspects permitted work for code compliance, and the UDO requires every inspection on a permit to be completed. Call the office at 812-265-8324 to book inspections and to confirm the stages for your project.
A certificate of occupancy is issued only when all work, including required site improvements, is finished, and no building may be occupied or used before then. The certificate confirms that the use meets the UDO and that the property has been inspected. A temporary certificate may be issued for up to six months while modifications are completed. Separately, the city enforces its unsafe building and vacant and abandoned structure rules (Ordinance 2025-4); code enforcement fines run $150, $250 and $350 for repeat violations within a year. The city also takes requests for an unsafe structure determination on its own form.
Indiana building code in Madison
Madison issues permits under its Building Regulations chapter and enforces the state codes, keeping copies of the code books at City Hall for review. FEMA’s Community Status Book lists the City of Madison (community 180107) as participating in the National Flood Insurance Program, with flood maps effective April 2, 2015, and the Code Enforcement Officer administers the floodplain rules.
Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana
Want this handled start to finish?
Get a free quote →Madison permit search and official resources
The UDO requires the Administrator to keep a public record of every building permit under state retention rules. Ask the Office of Planning, Preservation and Design for permit history on a property, and use the online contractor registration report to check whether a contractor is registered.
- Building and Design Division
- Planning, Preservation and Design
- OpenGov permit portal
- Building permit application (fees printed)
- Contractor registration application
- Contractor registration report
- Residential foundation permit application
- Manufactured or mobile home placement application
- Demolition permit application
- Unified Development Ordinance (adopted March 17, 2026)
- Plan Commission and BZA fee schedule
- Historic District Board of Review
- Certificate of Appropriateness application
- Plan Commission
- Board of Zoning Appeals
- Code enforcement
- Jefferson County Health Department septic permits
- FEMA Community Status Book, Indiana
Inspections are where schedules slip.
Get a free quote →Madison building permit FAQs
How much is a building permit for a new house in Madison?
$50 plus $0.10 per square foot under the city’s application form, so a 2,000-square-foot house is $250.
Do contractors need to register?
Yes. Contractors doing work on structures over 100 square feet or costing over $500 register yearly for $50; permits are held until every contractor is registered.
Do I need a permit for a fence or a shed?
A residential fence needs no building permit, and neither does an accessory structure of 200 square feet or less; larger sheds do. Fences in the historic district still need a Certificate of Appropriateness if visible from the street.
What is a Certificate of Appropriateness?
Approval for exterior changes visible from a street or alley in the downtown historic district, required before the building permit; staff review costs $10 and a board hearing $25 plus fees.
Can I apply online?
Yes. The city prefers applications through its OpenGov permit portal, though City Hall still accepts paper forms.
How long is a permit good for?
Work must start within six months and be substantially complete within 18 months, with one extension of up to six months.
Does the city handle land outside its limits?
Its UDO applies in the extraterritorial jurisdiction allowed by state law and city Ordinance 1963-66; the county handles the rest of Jefferson County.
Simplify Madison permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Madison sooner?
Let Alliance prepare, file, and track your Madison permits while your crew stays on the job.
More Indiana permitting guides
Jefferson County
Read guide →Jennings County
Read guide →Ripley County
Read guide →Madison County Building Permit Guide
Read guide →Marion Building Permit Guide
Read guide →Marion County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Madison permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.