Winnetka, Illinois Building Permit Guide

To get a building permit in Winnetka, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Winnetka’s Community Development Department at 510 Green Bay Road issues the village’s building permits, charges $30 per $1,000 of construction cost for remodels and new buildings, and since September 2026 takes only minor permit applications by email.

Authority: Winnetka Community DevelopmentFiling: In person; minor permits by emailPhone: 847-716-3527
Authority
Community Development510 Green Bay Road, first floor
Remodel or new build
$30 per $1,000$100 minimum for remodels
Fence or roof
$85Can be emailed as PDF
Right-of-way bond
$25,000No village contractor license

In the Village of Winnetka, building permits are issued by the Community Development Department on the first floor of Village Hall, 510 Green Bay Road (847-716-3527), led by Director Scott Mangum. Remodels, decks, sheds and new construction cost $30 per $1,000 of construction cost, and fence and roof permits are $85. Under a notice posted September 21, 2026, the village accepts only minor permit applications by email to buildingpermit@winnetka.org; major projects must be filed in person with scaled plan sets.

What requires a building permit in Winnetka?

Winnetka says licenses, permits and inspections are required for most construction, including many repairs and replacements. Its permit list covers additions of any size, basement finishing, foundation repairs other than minor work such as epoxy injection, outdoor fire pits and kitchens, trampolines, water heaters and removing trees more than 8 inches in diameter.

Permit needed

  • New buildings, additions, decks, balconies, garages, sheds and other accessory structures
  • Remodels that build or remove walls or replace 100 sq ft or more of drywall or plaster
  • New circuits, devices, services, EV chargers, generators and solar panels
  • Furnaces, air conditioners, gas lines, water heaters, sewers and new plumbing lines
  • Roof replacement, fences and walls, retaining walls and impermeable surfaces such as driveways and patios
  • Pools deeper than 18 inches, all spas and hot tubs, irrigation and grading
  • Sump pump discharge or downspout changes, tents and demolition

No permit

  • Replacing cabinets with no electrical work and existing plumbing lines
  • Siding repair or replacement, unless the new siding is stucco or EIFS
  • In-kind window replacement in existing openings
  • Replacing plumbing or light fixtures on existing lines, carpet, painting and refinishing floors
  • Minor fence repairs, flag poles, basketball goals and open playground equipment

Retaining walls 48 inches or taller must be designed by an Illinois licensed engineer or architect and set back at least 2 feet from the right-of-way and 1 foot from other lot lines. A demolition permit is issued only after the permit for the new building or for site restoration is approved.

What Winnetka decides and what the state holds

Winnetka adopts its own codes with local amendments. Applications filed since November 4, 2024 are reviewed under the 2021 International Residential, Building, Existing Building, Fire, Fuel Gas, Mechanical, Property Maintenance and Swimming Pool and Spa codes, the 2020 National Electrical Code, NFPA sprinkler and life safety standards and the Illinois Plumbing and Accessibility codes, all with Winnetka amendments where listed; since January 1, 2026 the 2024 Illinois Energy Conservation Code applies. The village also enforces the Metropolitan Water Reclamation District’s Watershed Management Ordinance and its own steep slope rules along Lake Michigan.

Short on time to read all of this?

Get a free quote →

Winnetka building department: who handles permitting

Community Development handles building permits and construction, zoning, subdivisions and special approvals, planning, property maintenance and food service inspections. Its permit desk processes applications and books inspections, and it supports the Zoning Board of Appeals and the Historic Preservation Commission. The village’s own Water and Electric Department installs electric and water services. Land in unincorporated Cook County is permitted by the county’s Department of Building and Zoning instead.

Winnetka permit contacts
DetailInformation
OfficeCommunity Development, Village Hall, 510 Green Bay Road, first floor, Winnetka, IL 60093
Phone847-716-3527 (permit desk and inspections); 847-716-3520 (permit fees); fax 847-716-3588
Emailbuildingpermit@winnetka.org (permits and inspections); planning@winnetka.org (zoning)
HoursMonday to Friday, 8:30 a.m. to 5:00 p.m.
DirectorScott Mangum, Director of Community Development

Winnetka permit types

Winnetka publishes a separate application for almost every kind of work, from additions and basements to trampolines and outdoor pizza ovens, plus a general building permit application, a contractors of record form, an authorized designee form and permit extension requests. Remodels and additions also need a written scope of work.

Residential permits

  • Remodels: the building permit application, a trade-specific work form, the contractors of record form if known, four complete sets of architectural plans (two sealed and signed; five sets in the floodplain) and the scope of work. The plans must list the adopted codes and the village amendments of September 3, 2024.
  • By email: decks and fences (with plats and plans legible on 11 by 17 inch paper), minor electrical work including service upgrades, hardscape replacement, irrigation, minor interior remodels, minor mechanical and plumbing work, roof replacements, sewer and water service repairs, sump pump discharge, trampolines and temporary tents, as PDFs.
  • Sheds always need a permit; they may be 7 feet tall at most, may not sit in the required front yard, and need fire-rated walls within 5 feet of a lot line.
  • Floodplain development permits are filed together with the main permit for any work in the FEMA floodplain.

Commercial permits

New commercial, multi-family and institutional buildings, additions, alterations and demolitions each have their own applications, and installing or replacing building wiring and equipment such as panels, water heaters, furnaces and air conditioners needs a permit. Commercial remodels and new buildings are major projects, so they must be filed in person with the required scaled plan sets. Exterior changes to any commercial, multi-family or institutional building need a certificate of appropriateness, awnings and signs need design review under the village’s design guidelines, and restaurants follow a separate restaurant application.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Zoning variations. Minor variations are decided by the Zoning Administrator, standard variations by the Zoning Board of Appeals (second Monday of the month), and major variations by the Village Council after the board’s review; file one paper and one electronic copy.
  • Historic review. Demolition permit review goes to the Historic Preservation Commission (first Monday) after the Winnetka Historical Society is asked to comment, and a historic and architectural impact study may be required. Landmarks and changes needing a certificate of appropriateness have their own packets.
  • Stormwater and slopes. Projects are checked against the MWRD Watershed Management Ordinance, and lakefront lots against the steep slope regulations.

Winnetka permit costs and fees

Winnetka does not post its full fee schedule; the Inspections and Permit Fees page gives a sampling and refers other questions to the permit coordinator at 847-716-3520. The sample fees are:

Sample Winnetka permit fees (Inspections and Permit Fees page)
PermitFee
Remodeling$30 per $1,000 of construction cost; $100 minimum
New construction$30 per $1,000 of construction cost
Deck / shed$30 per $1,000 of construction cost; $100 minimum
Fence / roofing$85 each
Impermeable surface (driveway, sidewalk, patio)$75
Furnace and air conditioning$100 base, plus $120 per unit
Plumbing$90 for up to 5 fixtures, plus $13 for each additional fixture
Pool$680

Two examples: a $40,000 remodel costs 40 times $30, or $1,200; a $3,000 shed works out to $90, so the $100 minimum applies. Trade and utility charges come from the village’s mechanical, electrical and plumbing fee worksheets dated January 12, 2024, filed with the building permit: premises wiring is $90 plus $1.40 per device, irrigation $105 plus $1.20 per sprinkler head, and a new or repaired sewer $150, with $200 for each right-of-way opening.

Because the village runs its own electric and water utilities, new services are priced on those worksheets too: a new 200-amp electric service is $13,200 and a 400-amp service $26,000, temporary service $450 overhead or $740 underground, a back-up generator connection $190 and a new 1-inch water meter $725. Three-phase service is priced by the Water and Electric Department.

Rather talk it over?

Call 1-855-478-4290 →

Trade permits and who may pull them

Winnetka does not run a contractor licensing program. Instead it accepts state licenses for plumbing, irrigation and roofing contractors and electrical licenses issued by other municipalities that test electricians. Electrical, plumbing, irrigation, roofing and fire suppression contractors must have a current license on file, or supply it, before the permit is issued.

  • Electrical: separate applications for miscellaneous work, service changes, EV chargers and generators; service upgrades also involve the village electric utility.
  • Plumbing and gas: permits for new or extended water lines, added fixtures, repairs under floors, gas lines, water heaters and sewers; replacing fixtures on existing lines needs none.
  • Mechanical: new, added or replacement furnaces and air conditioners; new condensing units need a site plan showing the distance to the lot line.
  • Fire protection: new or modified sprinkler and fire alarm systems need their own permit.

Before any permit is issued, the general contractor and any subcontractor working in the village right-of-way must file a $25,000 license and permit bond with Community Development. A change of contractor during the job is reported on the village’s change of contractor form.

How to apply for a Winnetka building permit

1. Find your application

Pick the form for your work from the village’s list of work requiring a permit.

2. Check zoning and history

Ask the permit desk whether the job needs a variation, design review or demolition review before you file.

3. Assemble the packet

Add the scope of work, plans, plat of survey, contractor list and the fee worksheet; incomplete packets are not accepted.

4. Email minor permits

Send minor permit types as PDFs to buildingpermit@winnetka.org.

5. File major projects in person

Bring everything else, with the required scaled plan sets, to Community Development at 510 Green Bay Road.

6. Respond and pay

The permit desk tells you the next steps when the permit is approved.

Review, corrections and what causes delay

The village does not publish a review time. The biggest delay today is format: Winnetka cannot currently review plans electronically or print large plan sets, so major projects sent by email will not be reviewed. Incomplete packets are refused and the applicant is told what is missing. Projects that need a variation, historic review of a demolition or a planned development approval go through their board or commission first, which meets on a fixed monthly schedule.

Rather not deal with the building department?

Get a free quote →

Inspections and certificates in Winnetka

Call the permit desk at 847-716-3527 at least 24 hours ahead, giving a contact name and phone number, the job address, the type of inspection and the village permit number; inspection questions can also go to buildingpermit@winnetka.org. The village says inspection requirements vary with the type of project, so confirm the stages for your permit with the permit desk when it is issued.

Certificates of occupancy are governed by chapter 15.36 of the Village Code, construction hours by section 15.32.140 and construction site management by section 15.32.150. The village’s construction site management requirements, in effect since January 18, 2023, add rules that inspectors check on every job:

  • Post the permit card where it can be seen from the street and keep all plans, including engineering plans, on site.
  • Work only from 7 a.m. to 7 p.m. on weekdays and 9 a.m. to 6 p.m. on Saturdays; no demolition, excavation or foundation concrete on weekends, and no work on Sundays or the six listed holidays.
  • Before work starts, install the tree protection fencing in the Village Forester’s plan, a 6-foot chain link security fence with lockable gates and any required silt fencing.
  • Park trade vehicles on site where possible and at least 2 feet from driveways, never stage excavation or concrete trucks on residential streets, and keep streets broom clean.
  • Use water to control dust when cutting masonry and during demolition, and keep grass on the site under 8 inches.

Site management questions go to code enforcement at 847-716-3521. Tree preservation and protection rules in chapter 15.28 apply during construction.

Illinois building code in Winnetka

Winnetka enforces the 2021 International codes and the 2020 National Electrical Code with its September 3, 2024 local amendments, the 2024 Illinois energy code and the MWRD Watershed Management Ordinance through Community Development. FEMA’s Community Status Book lists the Village of Winnetka (community 170176) as participating in the National Flood Insurance Program, with its current flood map dated September 10, 2021, and in the Community Rating System since May 1, 2015, at class 5 (a 25% premium discount) effective October 1, 2026.

Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline

Want this handled start to finish?

Get a free quote →

Winnetka permit search and official resources

Permit records are public records. Winnetka takes Freedom of Information Act requests through its online records request portal linked from the village website; the permit desk at 847-716-3527 can answer questions about an open permit.

Inspections are where schedules slip.

Get a free quote →

Winnetka building permit FAQs

How much does a building permit cost in Winnetka?

Remodels, decks, sheds and new construction cost $30 per $1,000 of construction cost, with a $100 minimum for remodels, decks and sheds. Fences and roofs are $85 and driveways or patios $75.

Can I email my permit application?

Only for minor permits such as roofs, fences, decks, small remodels and trade work, as PDFs to buildingpermit@winnetka.org. Major projects must be filed in person with scaled plans.

Do I need a permit to replace siding or windows?

No for in-kind window replacement and ordinary siding repair or replacement; yes if the new siding is stucco or EIFS.

Does a shed need a permit?

Yes, every shed. Sheds may be up to 7 feet tall and must stay out of the required front yard.

Does Winnetka license contractors?

No. It accepts state licenses and electrical licenses from testing municipalities, and requires a $25,000 bond for work in the right-of-way.

How do I schedule an inspection?

Call 847-716-3527 at least 24 hours ahead with the permit number, address and type of inspection.

Can I tear down a house in Winnetka?

A demolition permit application goes through the village’s demolition permit review: staff ask the Winnetka Historical Society for comment and the Historic Preservation Commission acts at its first-Monday meeting. Demolition can begin only after the permit for the new building or for site restoration is approved.

Simplify Winnetka permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Winnetka sooner?

Let Alliance prepare, file, and track your Winnetka permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Winnetka permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.