Skip to main content

White County, Illinois Building Permit Guide

To get a building permit in White County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

White County has no zoning and requires no building permit for homes or farm buildings on unincorporated land; builders check the flood map with the Supervisor of Assessments, and only commercial solar and wind farms take a county building permit.

Authority: No county building permit for homesFlood check: Supervisor of AssessmentsPhone: 618-382-2332
County building permit
NoneNo zoning ordinance on file
Flood plain
County ordinanceCheck the site before building
Septic permit
Egyptian Health DepartmentCarmi office, 618-382-7311
Solar or wind farm
$5,000 per MWBuilding permit, capped at $75,000

The White County Clerk’s office states plainly that the unincorporated county has no zoning ordinances and requires no building permits of any kind. The one county step for a rural building is to check with the Supervisor of Assessments in Carmi (323 East Main Street, 618-382-2332) that the site is outside the flood plain, and to follow the county’s flood plain ordinance if it is not. Septic systems are permitted by the Egyptian Health Department under the county’s 2018 sewage ordinance, and large solar and wind farms need county permits.

What requires a permit in unincorporated White County?

For an ordinary house, garage, barn or shop outside the towns, White County asks for no building permit and has no zoning rules. The county does regulate a few things on rural land, through its own ordinances and through the health department it shares with neighboring counties:

County and health approvals

  • Building in a flood plain: comply with the county’s flood plain ordinance
  • New or renovated private sewage system: Egyptian Health Department permit
  • New water well or sealing an abandoned well: Egyptian Health Department
  • Commercial solar farms and wind farms: county ordinances and construction permits
  • Energy-project traffic on county roads: road use agreement with the county

Not required by the county

  • A building permit for a house, farm building or ordinary commercial building
  • Zoning approval, setbacks or a zoning board
  • County electrical, plumbing or mechanical permits
  • A septic construction permit for routine cleaning, a new tank cover or rodding lines

The County Clerk’s letter says the county requires no building permits of any type. The solar siting ordinance adopted May 19, 2026 is the one exception in county law: it requires a single county building permit for a commercial solar energy facility, and the wind ordinance of the same date lets the county require one for a wind facility.

What the county decides and what the state holds

The county board has chosen not to adopt zoning or a building code, but it has adopted a flood plain ordinance, a private sewage ordinance (May 8, 2018) and solar and wind farm ordinances, last amended on May 19, 2026. The state note below explains the statewide structural minimums. Septic work also follows the state’s private sewage licensing act and code, plumbing follows the Illinois Plumbing Code with state-licensed plumbers, and roofers hold a state license.

White County building department: who handles permitting

No county office issues building permits for homes or farm buildings. The offices a rural builder deals with are the Supervisor of Assessments for the flood plain check, the Egyptian Health Department for septic and wells, the County Engineer for county roads, and the county board for solar and wind farm permits, with its records kept by the County Clerk.

Short on time to read all of this?

Get a free quote →
White County offices for rural projects
OfficeContact
Supervisor of Assessments (flood plain check, parcels, GIS map)323 East Main Street, P.O. Box 44, Carmi, IL 62821; 618-382-2332; Monday to Friday, 8 a.m. to 4 p.m.
Egyptian Health Department, Carmi office (septic)1705 College Avenue, Carmi; 618-382-7311, fax 618-382-7552; 8 a.m. to 5 p.m. Monday, Wednesday and Friday, 8 a.m. to 8 p.m. Tuesday and Thursday
Egyptian Health Department, Eldorado main office (well permits)1412 U.S. 45 North, Eldorado; 618-273-3326
County Engineer (roads and bridges)1103 E. Main St., P.O. Box 396, Carmi; 618-382-4811, fax 618-384-5021
County Clerk (ordinances, board records)323 E. Main St., P.O. Box 339, Carmi; 618-382-7211
911 administrative office (address requests)618-382-8911

Cities and villages in White County

The county seat, Carmi (population 4,623), is the largest town, followed by Norris City (1,083), the White County part of Grayville (835), Enfield (771), Crossville (605), the White County part of Mill Shoals (167), Springerton (114), Maunie (91), Phillipstown (39) and Burnt Prairie (32); one resident of New Haven also lives in the county. The Clerk’s no-permit statement covers only the unincorporated area: each city and village is a separate government with its own ordinances, and the county’s pages do not say which of them issue building permits, so ask the town hall for a lot inside a town.

White County permit types

Because the county issues no building permits for homes or ordinary buildings, the permit types on rural land are the health department’s and the energy-project permits.

Residential permits

  • Private sewage system: any new or renovated system must be permitted through the Egyptian Health Department, which needs an application and a construction plan from the contractor or homeowner before it issues the permit. Under the county ordinance, the department acts on applications within 15 days, and a permit can be refused where a public sewer is available: within 300 feet of a single-family home, or 1,000 feet of a commercial building, subdivision or multi-family dwelling.
  • Changes to a system: the health department must be told of any modification, change or repair so it can decide whether a permit is needed.
  • Water wells: new well permits are issued at the Eldorado office, and the department also permits the sealing of abandoned wells.
  • Flood plain: a home in the flood plain must meet the county’s flood plain ordinance.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

Ordinary commercial buildings on rural land have no county permit either. Utility-scale energy projects are the exception: a solar farm needs a solar farm construction permit petition and application, a signed acknowledgment, hold harmless and indemnification agreement, and a road use agreement, and the county posts the permits it has issued, including Invenergy, Crooked Creek Solar, Carmi Affordable Solar and Pivot Energy. Wind farms follow the separate wind ordinance. Under the May 19, 2026 solar ordinance, the arrays must sit 150 feet from homes and community buildings on non-participating land, measured to the outside wall, and 50 feet from non-participating property lines and public road rights-of-way, inside a fence 6 to 25 feet high. The building permit application includes geotechnical boring reports for the County Engineer, substation grading plans go to the White County Soil and Water Conservation District before the permit is issued, and the owner must give the county a written notice to proceed before any site work. Within 60 days of completion the operator files as-built plans stamped by a professional engineer and a licensed surveyor, then an annual operations report. Businesses on private septic systems use the same health department sewage permit.

What comes before construction

  • Flood plain check: ask the Supervisor of Assessments whether the site is in the flood plain before buying or building.
  • Subdivisions: a developer dividing land must give the health department lot sizes, soil and topography maps and water supply details; the department reviews the plat within 15 working days and reports to the developer, the White County Plat Officer and the County Highway Engineer.
  • Surface discharge: any effluent leaving the owner’s property needs an NPDES permit from the Illinois Environmental Protection Agency, and the discharge point must be at least 50 feet from property lines.
  • Address: the 911 office handles new address requests on its own form.

White County permit costs and fees

A house, barn or ordinary commercial building on unincorporated land pays no county building permit or zoning fee. The fees White County does set are in its commercial solar and wind siting ordinances adopted May 19, 2026:

Rather talk it over?

Call 1-855-478-4290 →
White County fees and charges
ItemFee
Siting approval or special use permit application, solar or wind facility$5,000 per megawatt of nameplate capacity, not to exceed $125,000
Building permit, commercial solar or wind facility$5,000 per megawatt of nameplate capacity, not to exceed $75,000
County processing costs above either maximumReimbursed by the applicant
Third-party costs (application review, inspections, permit enforcement)Reimbursed by the applicant or owner where the law allows
Private sewage permit, alteration or extensionSet by a Board of Health fee schedule, paid when the application is filed; amount not published online (Carmi office, 618-382-7311)
Building permit for a home or farm buildingNone; the county requires none

Worked example: a 12-megawatt solar facility pays $60,000 with its special use application and $60,000 for its building permit. At 30 megawatts the per-megawatt figure would be $150,000 for each, so the caps apply: $125,000 for the application and $75,000 for the building permit, plus any county expenses beyond those caps. Wind facilities use the same figures.

For a rural home, the government charges are the septic and well permits, plus the installer’s and driller’s prices, which the county does not set. Building inside Carmi or a village costs whatever that town charges.

Trade permits and who may pull them

White County issues no electrical, plumbing or mechanical permits and publishes no contractor license or registration for unincorporated land. The rules on who may do regulated work come from the sewage ordinance and the state:

  • Septic systems: a permit may be issued only to a homeowner or an Illinois licensed private sewage disposal system installation contractor. The ordinance defines a homeowner as a person holding legal title, or a contract-for-deed buyer, of a home used as his or her own single-family residence.
  • Wells: wells are drilled under the state water well codes by licensed contractors, with permits from the Eldorado office.
  • Plumbing: follows the Illinois Plumbing Code, performed by state-licensed plumbers.
  • Roofing: roofing contractors carry a state license.

Inside Carmi and the villages, any trade permits or contractor registration are each town’s own.

Rather not deal with the White County building department?

Get a free quote →

How to get permits for a rural White County project

1. Confirm the land is unincorporated

Use the county’s GIS map or ask the Supervisor of Assessments whether the parcel is outside Carmi and the villages.

2. Check the flood plain

Ask the Supervisor of Assessments whether the site is in the flood plain; if it is, the county flood plain ordinance applies.

3. Plan the septic system

Hire a licensed installer, or do it yourself as the owner-occupant, and prepare the construction plan.

4. Apply to the health department

File the private sewage application and plan with the Egyptian Health Department and pay its fee; the department acts within 15 days.

5. Permit the well

Get the new well permit from the Egyptian Health Department’s Eldorado office.

6. Request an address

Use the 911 office’s address request form for a new home site.

Review, corrections and what causes delay

The main timing step is the septic review, which the ordinance limits to 15 days. A site within reach of a public sewer can be refused a private system, and a surface-discharging design needs Illinois EPA NPDES coverage, which is a separate process. For land being divided into a subdivision, the health department needs the plat, covenants, sewer and water availability, drainage features and flood information; if a developer does not supply them, the county Plat Officer and Highway Engineer are told.

Inspections in White County

With no building permit for homes or ordinary buildings, there are no county building inspections or certificates of occupancy on unincorporated land. The Egyptian Health Department inspects each permitted sewage system during and after construction, collects private and semi-private well water samples for the state laboratory, and monitors non-community water supplies. Under the county ordinance, the department can issue a written notice of violation with a deadline to correct it, and an owner who disagrees can ask for a hearing within 30 days, first before the Health Authority and then the Board of Health.

Inside Carmi and the villages, any building inspections are run by the town.

Building rules in White County

White County has no zoning ordinance and no building code for unincorporated land. Its building-related ordinances are the flood plain ordinance, the Private Sewage Disposal System Ordinance passed May 8, 2018, and the solar and wind farm ordinances passed April 17, 2024 and amended by the county board on May 19, 2026, after a public hearing the same evening. FEMA’s Community Status Book lists White County (community 170906, unincorporated areas) as participating in the National Flood Insurance Program, with its first flood map dated April 3, 1985 and its current map February 16, 2012.

Want this handled start to finish?

Get a free quote →

Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline

White County permit records and official resources

County Freedom of Information Act requests go to the White County State’s Attorney, 307 E. Cherry St., Carmi (618-382-7522), by mail or in person during business hours, on the county’s FOIA form if you like. County board minutes from 2025 and 2026 are posted on the county’s minutes page, and solar and wind permits on its solar page. Septic permits and inspection records are kept by the Egyptian Health Department.

Inspections are where schedules slip.

Get a free quote →

White County permit FAQs

Do I need a building permit in rural White County?

No. The County Clerk’s office states that the unincorporated area has no zoning ordinances and requires no building permits; you only need to check the flood plain and get health permits.

How do I check whether my land is in the flood plain?

Ask the Supervisor of Assessments at 323 East Main Street, Carmi (618-382-2332); if the site is in the flood plain, the county flood plain ordinance applies.

Who issues septic permits in White County?

The Egyptian Health Department, under White County’s 2018 private sewage ordinance; its Carmi office is at 1705 College Avenue (618-382-7311).

Can a homeowner install a septic system?

Yes, a homeowner installing a system for his or her own single-family home can get the permit; otherwise an Illinois licensed installation contractor must.

Where do I get a well permit?

At the Egyptian Health Department’s Eldorado office, which issues all new water well permits.

What do solar and wind farms pay?

$5,000 per megawatt for the siting or special use application (up to $125,000) and $5,000 per megawatt for the building permit (up to $75,000), under the ordinances of May 19, 2026.

Who handles permits in Carmi or Norris City?

The city or village itself; the county’s no-permit statement covers only unincorporated land.

Simplify White County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in White County sooner?

Let Alliance prepare, file, and track your White County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about White County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.