Romeoville, Illinois Building Permit Guide

To get a building permit in Romeoville, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Romeoville’s Building Division, part of Community Development at Village Hall, issues building and trade permits inside the village through its OpenGov online portal, and every contractor on the job must be registered with the village.

Authority: Village of Romeoville Building DivisionFiling: OpenGov online portalPhone: 815-886-5163
Permit office
Building DivisionVillage Hall, 1050 W. Romeo Road
New house minimum
$1,250Building fee, plus 15% each for plumbing, electrical and HVAC
Remodels and accessories
$25 per inspectionPlus a $50 plan review for additions and accessory structures
Inspection slots
7–11 a.m. and 1–3 p.m.Plumbing 1–4 p.m.; book by phone, email or portal

In the Village of Romeoville, building permits come from the Building Division of the Community Development Department at Village Hall, 1050 W. Romeo Road (Building Division 815-886-5163, Village Hall 815-886-7200, weekdays 7 a.m. to 4 p.m.). Applications are filed online through the village’s OpenGov portal. Under the village fee schedule a new house pays at least $1,250 for the building permit, while remodeling and accessory work is charged $25 for each inspection the job needs.

What requires a building permit in Romeoville?

The village’s position is that most construction needs a permit, and its permit page asks owners to call the Building Division before starting any construction, alteration or repair; building without one can bring a fine or a stop-work order. The building ordinance (Chapter 150) narrows the usual exemptions. For houses and two-flats it deletes most of the standard residential-code list of permit-free work, so sheds of any size, fences, retaining walls, sidewalks and driveways, water tanks and small decks all need a permit in Romeoville.

Permit needed

  • New homes, additions, sunrooms and three-season rooms
  • Sheds, garages, decks, porches and gazebos of any size
  • Fences, retaining walls, patios, sidewalks and driveways
  • Kitchen or bath remodels that remove any drywall
  • Roofing, siding, pools, solar panels and EV chargers
  • Electrical, plumbing and HVAC work

No permit (Level 1 work)

  • Repairing drywall without removing any
  • Repainting walls and ceilings
  • Replacing interior trim, doors and flooring
  • New countertops or cabinets with no drywall removed
  • Swapping a toilet or sink with no drywall removed

The ordinance sorts remodeling into levels. Level 1 work, shown above, needs no permit. Level 2 is any job that removes drywall from a wall or ceiling, such as removing cabinets, countertops and drywall in a kitchen or pulling out a tub or shower. Level 3 applies when 50% or more of the drywall in a building is removed or the work costs half or more of the building’s replacement value after a fire, flood or major remodel, and then the whole building must be brought up to all current village codes.

What Romeoville decides and what the state holds

The village writes its own building ordinance. Chapter 150, last amended by Ordinance 22-1812 on December 7, 2022, adopts the 2021 International Building Code for commercial and industrial buildings, the 2021 International Residential Code for one- and two-family homes, the 2021 mechanical, fuel gas, existing building, property maintenance and swimming pool codes, the 2020 National Electrical Code and the Illinois Energy Conservation Code, each with local amendments. The 2014 Illinois Plumbing Code and the Illinois Accessibility Code are adopted as the state publishes them. The village’s codes web page lists a shorter set and omits the residential code, so read the ordinance itself (linked below) when a detail matters.

Short on time to read all of this?

Get a free quote →

Romeoville building department: who handles permitting

The Building Division reviews plans, issues permits and inspects remodeling, new residential, commercial and industrial construction throughout the village. Under the ordinance the building official is the Director of Community Development, the Building Commissioner or a designee named by the Village President and Board of Trustees, and the Fire Chief acts as fire code official. Appeals of a building official’s decision go to the Village Administrative Hearing Officer.

The village permits only inside its own limits. Unincorporated land around Romeoville is permitted by the Will County Land Use Department (see the Will County guide); neighboring Joliet and Bolingbrook run their own offices.

Romeoville permit contacts
DetailInformation
OfficeBuilding Division, Community Development, Village Hall, 1050 W. Romeo Road, Romeoville, IL 60446
PhoneBuilding Division 815-886-5163; Village Hall and inspection requests 815-886-7200
HoursMonday to Friday, 7 a.m. to 4 p.m.
ApplicationsOpenGov online permit portal
Inspectionsbuildinginspections@romeoville.org, 815-886-7200 or the portal

Romeoville permit types

Building permit applications are opened in the OpenGov permit portal, and contractor licenses are also handled there. The ordinance asks for complete plans with the application, drawn to at least ¼ inch per foot, along with a plat of survey from a registered land surveyor showing where the work sits on the lot.

Residential permits

  • New homes. Need a site plan based on a boundary survey by an Illinois professional land surveyor, showing grades, top of foundation and corner elevations. A spotted plat of survey is due once the foundation is in, and framing cannot start until it is approved.
  • Additions, sunrooms and porch roofs. Drawings must be stamped, signed and dated by an architect or engineer for room additions, sunrooms, three-season rooms and any roof built over a patio and attached to the house.
  • Remodels and accessory structures. Decks, sheds, gazebos, porches, siding and roofing are charged by the number of inspections, with a $50 plan review for additions and accessory structures.
  • Solar and EV chargers. Residential solar is $50 plus a $50 review; a home EV charger is $75 plus $50.

Commercial permits

Commercial and industrial buildings, build-outs and remodels fall under the 2021 International Building Code. The fee schedule prices many items separately, including warehouse racking, cranes, demising walls, trash compactors, construction trailers, cell towers, parking lot re-striping and resurfacing, low-voltage wiring and commercial roofing. Applications for businesses that serve the driving public, such as filling stations, motels and drive-in restaurants, can be referred to the Planning & Zoning Commission for review of access, lighting, signs and utilities before the permit is decided.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Zoning. The fee schedule charges for zoning certificates: $50 for a new house, garage or room addition, $30 for a pool and $10 for other accessory structures.
  • Variances and hearings. A zoning variance for a single-family lot costs $150 plus public notice costs; other variances are $1,000.
  • Easements. Nothing but a fence may go on a utility, drainage or pipeline easement without written permission from every utility and the village, and those letters must be in hand before the permit is issued.
  • Utilities. Call JULIE (800-892-0123 or 811) before digging.

Romeoville permit costs and fees

Fees come from Section 43.02 of the Village Code, the Department of Community Development fee schedule. The village posts it as its 2023 fee schedule; the amendment history printed on it ends with Ordinance 21-1709, passed June 16, 2021. New buildings are priced from the International Code Council’s Building Valuation Data table as locally amended, multiplied by a regional cost modifier of 1.05 and a permit fee modifier of 0.0075, with a minimum charge.

Romeoville building permit fees (Village Code 43.02)
ItemFee
New house: building permitGreater of $1,250 or the valuation formula
New house: plumbing, electrical, HVAC15% of the building fee each
Residential plan review$500 per dwelling unit
Residential remodeling and accessory work$25 times the number of inspections
Plan review, accessory structures and additions$50
Commercial or industrial buildingGreater of $5,000 or the valuation formula; build-outs under 1,000 sq ft $2,500
Commercial plumbing, electrical, HVAC$500 each
Non-residential plan review$0.16 per sq ft, $1,200 minimum; expedited 2½ times
Commercial roofing (each roof level)$250 under 10,000 sq ft; $500 to 99,999 sq ft; $750 above
Residential water and sewer tap-ons$4,000 each
3/4-inch residential water meter$300
Rental inspection / reinspection$200 / $100
Temporary dumpster permit$25

Rather talk it over?

Call 1-855-478-4290 →

Worked example: if the valuation formula for a new house comes out below the minimum, the building permit is $1,250 and the plumbing, electrical and HVAC permits are $187.50 each (15% of $1,250), so permits total $1,812.50. Adding the $500 plan review and the $50 zoning certificate for a new dwelling brings it to $2,362.50 before the $8,000 in water and sewer tap-ons and the $300 meter. A deck needing three inspections costs $75 plus the $50 review.

Penalties, renewals and refunds

Work started without a permit pays the normal fee twice over when that fee is $1,500 or less; above that the surcharge is $1,500 plus 25% of the fee. Re-inspections for work not ready cost $50, $100, $200 and then $400 each on residential jobs, $75 to $600 on commercial jobs and $100 to $800 on industrial jobs. An expired permit can be renewed for 25% of the original fee (at least $25), and if a permit is cancelled before work starts the village keeps half of the fee. Where a review needs an outside engineer or consultant, the village bills that cost to the applicant before the permit is issued.

Trade permits and who may pull them

Plumbing, electrical and HVAC permits are issued by the same Building Division. On a new house each one is 15% of the building permit fee; on commercial work each is a flat $500. Plumbing follows the 2014 Illinois Plumbing Code and is done by a plumber licensed through the Illinois Department of Public Health.

  • Contractor registration: every contractor, subcontractor and plumbing contractor must be registered with the village before working; lists of registered firms are kept at Village Hall and can be requested by email.
  • Electrical contractors must be registered, bonded and insured with the village.
  • Homeowner electrical work: the owner of a single-family home, townhouse or two-family dwelling may do his or her own electrical work, except installing a new service or moving an existing one. Owners of commercial, industrial or retail buildings may not.
  • Mechanical: furnaces, rooftop units, ductwork and kitchen hoods are inspected under the 2021 mechanical and fuel gas codes.

The village’s electrical amendments are long: they delete several wiring methods that the national code allows, including service-entrance cable and nonmetallic tubing, so an electrician new to Romeoville should read them in Chapter 150 before pricing a job.

Rather not deal with the building department?

Get a free quote →

How to apply for a Romeoville building permit

1. Confirm the village has the parcel

Romeoville permits only inside its limits; unincorporated land goes to Will County.

2. Register your contractors

Every contractor and subcontractor on the job must be registered with the village.

3. Prepare drawings and survey

Use a land surveyor’s plat and, for additions and sunrooms, stamped drawings.

4. Apply in OpenGov

Open the building permit category, describe the work and upload the plans.

5. Clear easements and zoning

Get easement-holder letters and the zoning certificate where they apply.

6. Pay and build

Pay the permit, review and tap-on fees, then book each inspection as work is ready.

Review, corrections and what causes delay

The village does not publish a set review time. Applications stall most often when contractors are not registered, when a structure sits on an easement without the utilities’ letters, or when a commercial plan needs outside review, which adds consultant costs and can be expedited for 2½ times the review fee. A permit expires 12 months after issue if work has not started, and the Building Official may revoke it after work stops for six months in a row, in which case the owner must restore the site.

Inspections and certificates in Romeoville

Inspections can be booked three ways: by calling 815-886-7200, by email to the building inspections mailbox, or with a comment on the inspection step of the permit in the online portal. Have the address, record number, inspection type and a contact name ready. Inspections are not set for exact times. Building, mechanical and electrical inspections are made in a morning window from 7 to 11 a.m. or an afternoon window from 1 to 3 p.m., and plumbing inspections from 1 to 4 p.m., first come first served.

The approved plans must be on site or the inspection will not be done, and a re-inspection fee applies if the work is not ready and the request was not cancelled. The ordinance adds its own inspection list on top of the codes, from trench and footing pre-pours and spot surveys to ceiling grids, fire stopping, kitchen hood welds and warehouse racking, and the general contractor or permit holder arranges any testing. No new building or renovation that needed a permit may be occupied until a certificate of occupancy is issued.

Construction noise is limited by hours. The village’s building page allows work from 7 a.m. to 8 p.m. on weekdays and 8 a.m. to 6 p.m. on weekends, while the building code amendment allows Sunday work only from 9 a.m. to 6 p.m.; plan Sunday work around the later start.

Want this handled start to finish?

Get a free quote →

Illinois building code in Romeoville

Romeoville enforces the 2021 International Building and Residential Codes and the related 2021 codes adopted in Chapter 150, the 2020 National Electrical Code, the 2014 Illinois Plumbing Code, the Illinois Energy Conservation Code as the state amends it and the Illinois Accessibility Code. Violations of the chapter are fined $100 to $1,000, and each day counts as a separate offense. FEMA’s Community Status Book lists the Village of Romeoville (community 170711, Will County) as participating in the National Flood Insurance Program, with its first flood insurance rate map dated November 3, 1982 and the current map dated February 15, 2019; the village has no Community Rating System class.

Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline

Romeoville building permit FAQs

Do I need a permit for a shed or fence in Romeoville?

Yes. Romeoville deleted the residential code’s exemptions for small sheds, fences, retaining walls, sidewalks, driveways and small decks, so each needs a permit.

How much is a building permit for a new house?

The greater of $1,250 or the valuation formula, plus 15% of that for each of plumbing, electrical and HVAC, a $500 plan review and the zoning certificate.

What does a remodel permit cost?

Residential remodeling and accessory work is $25 for each inspection required, and additions and accessory structures add a $50 plan review.

Can I replace my kitchen cabinets without a permit?

Yes, if no drywall is removed. Once any drywall comes off a wall or ceiling the job becomes Level 2 work and needs a permit.

Can a homeowner do their own electrical work?

An owner of a single-family home, townhouse or two-family dwelling may, except for installing or relocating the service. Commercial owners may not.

How do I schedule an inspection?

Call 815-886-7200, email the building inspections mailbox or comment on the inspection step in the OpenGov portal; inspections run in morning and afternoon windows.

What if I started work without a permit?

The permit fee is doubled when it is $1,500 or less; above that you pay the fee plus $1,500 and 25% of the fee, and fines of $100 to $1,000 a day can apply.

How long is a Romeoville permit good for?

It expires 12 months after issue if work has not started, and renewal costs 25% of the original fee, at least $25.

Inspections are where schedules slip.

Get a free quote →

Romeoville permit records and official resources

Permit records are requested through the village’s Freedom of Information portal, which covers permit information, property information and zoning letters. A formal zoning or code verification letter for a parcel is $100.

Simplify Romeoville permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Romeoville sooner?

Let Alliance prepare, file, and track your Romeoville permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Romeoville permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.