Skip to main content

Peoria County, Illinois Building Permit Guide

To get a building permit in Peoria County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Peoria County Planning and Zoning issues building, trade and floodplain permits for land outside the county’s cities and villages, with residential reviews usually done in two to three business days.

Authority: Peoria County Planning and ZoningFiling: Email or counter, 324 Main StreetPhone: 309-672-6915
New home fee
$0.50 per sq ft$750 minimum, plan review included
Residential review
2 to 3 business daysCommercial averages 14
Technology fee
$45 per permitJune 2026 schedule
Office hours
8:30 a.m. to 4:30 p.m.Weekdays, courthouse Room 301

In unincorporated Peoria County, building, electrical, HVAC, plumbing, pool, fence and floodplain permits come from the county’s Planning and Zoning Department in Room 301 of the courthouse, 324 Main Street, Peoria (309-672-6915). Plans can be emailed to buildingpermits@peoriacounty.org or handed in at the counter. A new house costs $0.50 per square foot with a $750 minimum, plus a $45 technology fee on each permit, under the schedule revised June 1, 2026. The City of Peoria and the villages issue their own permits.

What requires a permit in unincorporated Peoria County?

The county asks for a permit for new construction and for additions, alterations, renovations and repairs to a building or structure. Its residential and commercial pages list the projects it sees most:

Permit needed

  • New homes, additions, remodels, alterations and repairs
  • Attached and detached garages
  • Sheds over 200 square feet, prebuilt or site-built
  • Decks over 25 square feet, docks, pergolas, pavilions, gazebos and carports
  • Fences and pools, above-ground or in-ground
  • Electrical, HVAC and plumbing work
  • Demolitions
  • Commercial change of use, signs, telecommunication towers and antenna co-locations
  • Solar arrays and battery storage, sized by kilowatts

No permit

  • Sheds of 200 square feet or less, which still must meet setbacks and the accessory size limits in the ordinance
  • Re-siding
  • Re-shingling
  • Cosmetic work such as new carpet and paint

Every permit needs a site plan; the county suggests printing an aerial view of the lot from its GIS map. Work in a mapped flood hazard area also needs a floodplain development permit, and starting construction or disturbing soil before the permit is issued can bring fines and a stop-work order.

What the county decides and what the state holds

The county board sets the building code, the zoning ordinance, the fee schedule and the floodplain rules for unincorporated land. Plans are reviewed under the 2018 International codes and the 2017 National Electrical Code, which the county has enforced since July 1, 2021, and the 2021 Illinois Energy Conservation Code, enforced since January 1, 2024. Plumbing follows the state plumbing code, plumbers and roofers hold state licenses, and septic systems and wells are permitted by the Peoria City/County Health Department.

Peoria County building department: who handles permitting

The Planning and Zoning Department, led by Director Andrew Braun, reviews plans, issues permits and inspects construction in unincorporated areas, and also handles code enforcement, floodplain management and applications to the Zoning Board of Appeals. Appointments are encouraged for zoning questions and counter visits.

Short on time to read all of this?

Get a free quote →
Peoria County offices for rural and suburban projects
OfficeContact
Planning and Zoning (building, trade, floodplain permits)Courthouse, 324 Main Street, Room 301, Peoria, IL 61602; 309-672-6915; buildingpermits@peoriacounty.org; Monday to Friday 8:30 a.m. to 4:30 p.m.
Peoria City/County Health Department, Environmental Health (septic, wells)2116 N. Sheridan Road, Suite A, Peoria, IL 61604; 309-679-6161; eh@peoriacounty.org
Highway Department (entrances, utilities on county roads)6915 W. Plank Road, Peoria, IL 61604; 309-697-6400, ext. 3

Cities and villages

The county office covers only unincorporated land; use the county’s GIS viewer to see whether a parcel sits inside municipal limits. The City of Peoria (110,920 people) issues its own building, electrical, plumbing, floodplain and stormwater permits (see the Peoria city guide). The other municipalities are separate governments as well: Chillicothe (6,033), Bartonville (5,804), the Peoria County part of Peoria Heights (5,767), West Peoria (4,187), Elmwood (2,030), Bellevue (1,888), Princeville (1,713), Dunlap (1,588), Hanna City (1,238), Glasford (842), Brimfield (764), Norwood (431), Kingston Mines (259) and Mapleton (251). Census tables also show small unpopulated pieces of Farmington and Pekin inside the county line.

Peoria County permit types

Each kind of work has its own application, and trade work gets separate permits: on a new home, subcontractors apply for their own electrical, HVAC and plumbing permits.

Residential permits

  • New homes: building permit application, erosion control application (standard or site-specific), a one- or two-story cross section, the three trade applications and an address request form.
  • Room additions: building application, an addition cross section and any trade applications.
  • Garages and sheds: the building application, with cross-section sheets for buildings of 200 to 600 square feet and over 600 square feet that need plan review.
  • Decks: the building application with the county’s deck construction guide and freestanding or attached deck details.
  • Fences and pools: a fence application; a pool packet with barrier and electrical details. A pool permit is not issued until the barrier requirement is met, and a new fence or deck used as the barrier is permitted at the same time.

Plans for houses go in as one copy at a minimum scale of 1/4 inch to 1 foot unless filed digitally.

Commercial permits

Commercial and industrial work needs three sets of plans drawn to scale and stamped by an Illinois licensed design professional, the commercial checklist, a zoning verification application, an erosion control application, a signed COMcheck report, fire department approval and the trade applications. Telecommunication towers and sign projects have their own checklists. Review typically takes up to 14 business days once complete, code-compliant information is in.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Address: a new home needs a valid 911 address, requested through the county’s address form.
  • Water and sewer: well and septic permit numbers from the Health Department, or proof of service from a sanitary district or water company.
  • Road access: a road access permit is required in Jubilee, Medina and Limestone townships; elsewhere ask the township road commissioner, the County Highway Department or IDOT. A new access onto a county road needs a Highway Department entrance permit before construction.
  • Zoning relief: variances, special uses, rezonings and appeals go to the Zoning Board of Appeals.
  • Floodplain: development in the Special Flood Hazard Area along the Illinois River, Kickapoo Creek and other streams needs a floodplain development permit.

Peoria County permit fees

Fees come from the Planning and Zoning fee schedule revised June 1, 2026. Residential and accessory building fees include plan review, and a $45 technology fee is added to each permit, so a project with a building permit and three trade permits pays it four times.

Peoria County building fees (revised June 1, 2026)
ItemFee
One- and two-family new construction, additions, alterations$0.50 per sq ft; minimum $750 new, $250 additions and alterations
Partial basement (studs only)$0.25 per sq ft
Accessory structures$0.20 per sq ft; minimum $115 under 100 sq ft, $250 at 100 sq ft or more
Erosion control, standard / site-specific$185 / $240
Electrical, new dwelling unit / other residential work$55 / $45
HVAC, each heating or cooling unit / combination unit$55 / $65
Plumbing$55 base plus $15 per fixture
Residential solar, 0 to 10 kW$250
Pools: above-ground / in-ground / commercial$100 / $175 / $250
Fence / sign$55 / $110
Demolition: dwelling / accessory over 200 sq ft / commercial$165 / $160 / $250
Commercial new construction$7.50 per $1,000 of cost, $750 minimum
Commercial additions and alterations$0.60 per sq ft, $450 minimum
Commercial plan review$400 plus $50 per 50,000 cubic feet
Floodplain development permit / review$160 / $110
Reinspection (inspection not cancelled 4 hours ahead)$80
Technology fee$45 per permit

Rather talk it over?

Call 1-855-478-4290 →

Worked example: a 2,000-square-foot new house is 2,000 × $0.50 = $1,000, above the $750 minimum, plus the $45 technology fee, for $1,045. Its electrical permit adds $55 + $45 = $100, and one combination furnace and air conditioner adds $65 + $45 = $110, before plumbing fixtures and erosion control.

Work started without a permit draws a stop-work fee of $200 for residential work or $500 for commercial or industrial work, or a fee equal to 100% of the permit fee. A permit on which work has not begun within 180 days can be extended once for half the original fee if the plans are unchanged. Zoning cases cost $265 for a variance, $135 for an administrative variance, $690 plus recording for a special use and $65 per acre ($955 to $3,200) for a rezoning, plus newspaper notice. Commercial solar and wind facility permits cost $5,000 per megawatt, up to $75,000, and their special use filing is also $5,000 per megawatt, up to $125,000.

Do not send payment with applications that need plan review; the office tells you the amount when the permit is ready. The schedule accepts checks payable to Peoria County Zoning by mail, credit cards by phone or in person with a 3% service charge, and exact cash at the counter. The department’s web page still says it can take only checks or exact cash, so ask which applies before paying.

Trade permits and who may pull them

Electrical, HVAC and plumbing permits are issued by the same county office, each on its own application. On a new house the subcontractors apply for their own trade permits, and the checklist asks for a list of names and phone numbers for the builder, electrician, plumber, HVAC contractor, insulator, roofer, lawn sprinkler contractor and fire alarm or sprinkler contractor.

  • Plumbing: work must be done by a state-licensed plumber or by an owner who lives in the home. The fee schedule spells it out: an owner may plumb an existing home that is their primary residence, or a new home they will occupy as their primary residence; rental property needs a licensed plumber, and commercial plumbing needs a licensed plumbing contractor. A contractor’s permit application carries copies of the Illinois plumbing license and plumbing contractor license.
  • Electrical: an electrical permit lets county inspectors inspect a new service and release it to Ameren for temporary power.
  • HVAC: new-home HVAC applications include ACCA Manual J load calculations.
  • Roofing: a new-home file lists the roofer’s state roofing license number.

The county’s pages show no separate county contractor registration. Septic installers and pumpers register each year with the Health Department, which mailed its 2026 registration forms to contractors in January.

Rather not deal with the Peoria County building department?

Get a free quote →

How to get a Peoria County building permit

1. Confirm the parcel is unincorporated

Use the county GIS viewer; inside Peoria or a village, apply to that municipality.

2. Line up water, sewer and access

Get Health Department well and septic permit numbers, a 911 address and any road access permit.

3. Assemble the package

Follow the submittal checklist: application, site plan, plans or cross sections, REScheck or COMcheck, erosion control form.

4. File by email or at Room 301

Email readable digital plans to buildingpermits@peoriacounty.org, or bring them to the counter between 8:30 a.m. and 4:30 p.m.

5. Answer review comments

Incomplete packages are not sent to plan review; residential reviews usually finish in 2 to 3 business days.

6. Pay and receive the permit

Pay when notified; permits and receipts are emailed to the billing contact, with the inspector’s number on the sheet.

Review, corrections and what causes delay

The checklist warns that anything missing at the time of application delays review. For a new home the list includes the well and septic permit numbers, the signed REScheck report and certificates, beam calculations and the subcontractor list; truss layouts may follow at the rough-in inspection. Commercial files need the stamped plans and fire department approval before review can begin. Some permits that need no plan review can be issued the same day at the counter.

Inspections and final approval

Every county permit is inspected, though the number of visits depends on the project. To book, call the inspector whose number is printed on the sheet you received with the permit, giving at least 24 hours’ notice. Inspectors are usually in the office from 7 to 9 a.m.; if you leave a voicemail, give the permit number and the project address, and call the main line, 309-672-6915, if you cannot find your inspector’s number.

The county’s design criteria for unincorporated land include a 42-inch frost depth, a 20-pound ground snow load, seismic design category A and an assumed soil bearing pressure of 1,500 pounds per square foot unless tested, and ice-barrier underlayment is required on roofs. Cancel an inspection at least four hours ahead to avoid the $80 reinspection fee. After all final inspections pass, the county issues a certificate of compliance.

Septic installations follow a separate Health Department track: the signed septic application commits the applicant to notify the Health Department (309-679-6161) 48 hours before installation, so the system can be inspected before it is backfilled.

Illinois building code in Peoria County

Peoria County takes part in FEMA’s National Flood Insurance Program for its unincorporated areas (community 170533). Its first flood insurance rate map took effect February 15, 1980, the current map is dated June 1, 1983, and the county has been in the Community Rating System since October 1, 1992, now at class 5, which gives policyholders a 25% discount.

Want this handled start to finish?

Get a free quote →

Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline

Permit search and official resources

For copies of old permits or plans, file a Freedom of Information Act request through the county’s online FOIA portal. Requests are free unless paper copies are needed: the first 50 black-and-white pages are free and later pages cost 15 cents each, while records emailed electronically are free. Health Department septic and well records for systems installed after 2009 can be looked up online; older records need a FOIA request to the department.

Inspections are where schedules slip.

Get a free quote →

Peoria County permit FAQs

Does Peoria County issue permits inside the City of Peoria?

No. The county office covers unincorporated land only; the City of Peoria and the villages issue their own permits.

Do I need a permit for a shed in Peoria County?

Only if it is over 200 square feet. Smaller sheds need no permit but must still meet setbacks and accessory size limits.

How much is a permit for a new house?

$0.50 per square foot with a $750 minimum, including plan review, plus a $45 technology fee; trade permits are extra.

How long does review take?

Residential permits usually take 2 to 3 business days once the package is complete; commercial permits average 14 business days.

Can I do my own plumbing?

Yes, if you own the home and it is your primary residence, or it is a new home you will live in. Rentals and commercial work need a licensed plumber.

Do I need a permit to re-roof or re-side?

No. The county lists re-shingling and re-siding among the projects that need no permit.

Who issues septic permits?

The Peoria City/County Health Department; its onsite wastewater application costs $225, plus $75 if a variance is requested.

Simplify Peoria County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Peoria County sooner?

Let Alliance prepare, file, and track your Peoria County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Peoria County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.