To get a building permit in Mount Vernon, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Mount Vernon’s Engineering and Inspections office at City Hall, 1100 Main Street, issues building permits inside the city, with applications filed online, by email or at the counter.

Authority: Engineering and Inspections, City of Mt. VernonFiling: Online, email or City HallPhone: 618-242-6830
Authority
Engineering and InspectionsCity Hall, 1100 Main Street
Permit fee
$7.50 at $1,000Rises $2.50 per $1,000 of cost
Electricians
City license, $90Renewed every May 1
Inspections
48 hours aheadCall 618-242-6830

Inside Mount Vernon, permits come from the city’s Engineering and Inspections office at City Hall, 1100 Main Street (618-242-6830, weekdays 8 a.m. to 5 p.m.). Apply online, email the application to buildinginspector@mtvernon.com or bring it to the office; the city says applications are reviewed by Engineering and Inspections, the Planning and Zoning Committee and the City Council before a permit issues. Fees follow the project cost, from $7.50 for a $1,000 job to $255 at $100,000, and electrical contractors need a $90 city license.

What requires a building permit in Mount Vernon?

Mount Vernon says many small repairs need no building permit but bigger projects often do, and all permitted work must be inspected. Its own examples are carports, garages, pools, storage buildings, new houses, porches and decks that are more than 30 inches high or have a roof, mobile homes and new commercial construction. The list is not complete, so projects outside it are checked with the Engineering and Inspections office before work starts.

Building permit

  • New houses and mobile homes
  • Garages, carports and storage buildings
  • Pools
  • Porches and decks over 30 inches high or with a roof
  • New commercial construction

Other city permits

  • Demolition of houses, garages, sheds, decks and commercial buildings
  • Signs, apart from the small exempt signs
  • Electrical, plumbing and excavation permits on the same application
  • Water deposit and hook-up for new services

Small signs need no sign permit: house numbers and resident names up to 1 square foot, one private-drive sign of 1 square foot per driveway, government and utility signs, security and no-trespassing signs, and one sign per street of up to 1 square foot on a home or 3 square feet on other property.

What Mount Vernon decides and what the state holds

The city chooses and adopts its own codes. Its current permit application binds work to the 2021 International Building, Existing Building, Residential, Mechanical, Fuel Gas and Fire codes, the 2023 National Electrical Code and the 2021 NFPA 101 Life Safety Code, together with chapters 91, 150 to 154, 159 and 161 of the city code and the Illinois smoke detector law. The Building Codes page gives the same list without the residential code and adds the Illinois energy, plumbing and accessibility codes. Mount Vernon sits in Seismic Design Category D, so earthquake-resistant design must be included where the codes require it.

Mount Vernon building department: who handles permitting

The Engineering and Inspections office, housed in City Hall with the City Clerk, City Manager and Finance, handles building permits, inspections, electrical contractor licenses and demolition and sign permits, and gives out the zoning application forms. Zoning hearings go to the Planning and Zoning Commission, and final zoning action rests with the City Council of the city’s mayor-council government. Outside the city limits, Jefferson County’s department list shows no building or zoning office; its County Engineer reviews permits for work on county highways (fax 618-242-3392 or countyengineer@jeffil.us).

Short on time to read all of this?

Get a free quote →
Mount Vernon permit contacts
DetailInformation
OfficeEngineering and Inspections, City Hall, 1100 Main Street, Mount Vernon, IL 62864
Phone618-242-6830
Emailbuildinginspector@mtvernon.com
HoursMonday to Friday, 8 a.m. to 5 p.m.
City Hall main line618-242-5000
Zoning filingsCity Clerk’s Office, City Hall

Mount Vernon permit types

One Application for Building Permit serves homes, garages, commercial businesses, manufacturing, warehouses and offices. It asks for the estimated project cost, owner, architect, contractor, electrician, plumber and roofer, the legal description and parcel number, the use and occupancy class, the type of construction, the floor area and the electric service size in amps, and whether the work is new, an alteration, an addition or storage.

Residential permits

  • New houses and additions. Plans list the adopted codes on the drawings (the local ordinances need not be listed), and the application covers the water deposit, water hook-up, excavation and plumbing permit charges for new services.
  • Decks and porches. A permit is needed once a deck or porch is more than 30 inches high or has a roof.
  • Roofs and solar. Roofing is inspected from photos: take pictures of the sheathing, ice and water shield, felt paper, vents, flashing and insulation during the work and send them to the inspector the same day; solar installers send photos of the electrical service, clearances, grounding and the full array.
  • Mobile homes. Placing a mobile home needs a building permit, and removing one needs a demolition permit.

Commercial permits

Buildings to be used for public purposes need plans and specifications, including a plot plan, approved by an architect or structural engineer licensed in Illinois. Commercial plans must show the city’s adopted codes and the Seismic Design Category D requirements. Building, electrical, excavation and plumbing permit fees can be waived for qualified Enterprise Zone projects.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Zoning. The city’s zoning page says it oversees zoning inside the city limits and up to 1.5 miles outside, across 15 districts whose rules sit in the Schedule of District Regulations; some uses are allowed only after Planning and Zoning Commission review. Rezoning, variance and conditional use applications are filed with the City Clerk’s Office with a $25 filing fee.
  • Public notice. The applicant mails notice to the owner (if different), publishes notice in a local newspaper and posts the city’s sign 15 to 30 days before the hearing; the sign carries a $50 refundable deposit.
  • Hearing and Council action. The Planning and Zoning Commission meets at 7 p.m. on the second Monday of each month at City Hall; approved requests go to the City Council, and variance applicants attend both readings. Neither a variance nor a conditional use replaces the building permit.
  • Hearing papers. Applicants bring the newspaper’s certificate of publication, the certificates of posting and mailing, copies of the forms filed with the City Clerk and, for a variance, a plot plan and proof of compliance with the Soil and Water Conservation District Act where it applies; a conditional use also needs three copies of the Commission resolution.
  • Conditional uses. The City Manager checks the application for completeness before the hearing, approvals often carry conditions or time limits, and permits for home daycares and homeless shelters belong to the applicant and do not transfer when the property is sold.

Signs and demolition

Sign rules apply to every sign in the city’s zoning area: staff review a sign proposal before it goes up, using the online form or a paper application brought to City Hall, under the city’s sign ordinance. Demolition permits are needed for houses, mobile homes, covered porches, decks, garages, carports, sheds and commercial buildings; apply online, by email or at the office, and pay in person or by phone.

Mount Vernon permit costs and fees

The city’s building permit fee is based on the cost of the project, from a table posted on its Building Permits page. Up to $100,000 the fee is $7.50 for the first $1,000 and $2.50 for each further $1,000; above that a flat rate per $1,000 applies.

Mount Vernon building permit fees by project cost
Project costPermit fee
$1,000$7.50
$5,000$17.50
$10,000$30.00
$20,000$55.00
$50,000$130.00
$100,000$255.00
$101,000 to $500,000$2.50 per $1,000
Over $500,000$1.50 per $1,000

Rather talk it over?

Call 1-855-478-4290 →

Worked example from the table: a garage costing $40,000 pays a $105 building permit fee. The two upper bands do not join the table smoothly: at $101,000 the $2.50 rate gives $252.50, less than the $255 listed for $100,000, so ask the office how a project just over a band edge is billed. Other city fees can apply on top: demolition permits cost $5 for a one-story structure or items such as fences, pools and sheds and $10 for two stories or more, zoning applications carry a $25 filing fee, and new connections pay the water deposit, hook-up and plumbing (meter, tap and inspection) charges shown on the application.

Trade permits and who may pull them

The building permit application also carries the office’s electrical, excavation and plumbing permit fees and names the electrician, plumber and roofer. The city’s own codes include chapter 153 (electrical) and chapter 154 (plumbing) of the city code, alongside the Illinois Plumbing Code.

  • Electrical contractors: must hold a Mount Vernon Electrical Contractor License, $90 a year, renewed each May 1 to April 30 period by June 1. The firm names a Supervising Electrician who is at least 21 and has journeyman-level qualifications, shown by a union journeyman wireman card or a journeyman certificate from an approved testing center (70% pass; the open-book exam is Pearson VUE test F17 on the 2008 or later NEC). The city must hear within 10 days if that electrician leaves, and the firm has 60 days to name a replacement. The license application can be filed online or brought to the Engineering and Inspections office, and a license that lapses for late renewal is terminated, so the firm must reapply and pay the fees again.
  • Plumbers and roofers: are named on the permit application; plumbing work follows the Illinois Plumbing Code and the city’s chapter 154.
  • On-site presence: the electrician must be on site for the rough electrical inspection.

Rather not deal with the building department?

Get a free quote →

How to apply for a Mount Vernon building permit

1. Check the zoning

Confirm the parcel’s district on the city zoning map; a rezoning, variance or conditional use comes first.

2. Prepare plans

List the adopted codes on the drawings; public buildings need plans approved by an Illinois architect or structural engineer.

3. Complete the application

Fill in the online form or download the PDF application with cost, parcel and contractor details.

4. Submit

Send it online, email buildinginspector@mtvernon.com or bring it to City Hall.

5. City review

Engineering and Inspections, the Planning and Zoning Committee and the City Council review the application.

6. Pay and build

Pay the cost-based fee and book each inspection at least 48 hours ahead as work proceeds.

Review, corrections and what causes delay

The city posts no fixed review period, and both the online form and the downloadable PDF application are linked from its Building Permits page. Because applications pass through Engineering and Inspections, the Planning and Zoning Committee and the City Council, a project that also needs a rezoning, variance or conditional use waits for the Commission hearing (second Monday) and the Council readings that follow, plus the 15 to 30 days of required notice. Plans must list the adopted codes, and electrical work needs a city-licensed electrical contractor, so settle both before filing.

Inspections and certificates in Mount Vernon

Call 618-242-6830 at least 48 hours before you need an inspection, with the permit number, the project address and the inspection type; the permit holder or owner must make sure every required inspection is booked. Inspections cover concrete before footings, piers or foundations are poured (depth, width, location and reinforcing), rough electrical with the electrician present, rough framing before insulation or drywall, rough heating and cooling before walls or ceilings are closed, house wrap before siding, and finals for electrical, mechanical and the whole building once stairs, handrails, guardrails and accessibility items are in. Inspections are also needed when walls, floors or ceilings are opened during a remodel, after fire-rated walls are finished and before anyone moves in. Roofing and solar inspections are done from photos sent the same day. When the final inspection is approved, the city issues a certificate of occupancy.

Illinois building code in Mount Vernon

Mount Vernon enforces the 2021 International codes, the 2023 National Electrical Code and the local chapters named on its permit application. FEMA’s Community Status Book lists the City of Mount Vernon (community 170308) as participating in the National Flood Insurance Program, with a current flood map dated September 17, 2010; the city is not in the Community Rating System.

Want this handled start to finish?

Get a free quote →

Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline

Mount Vernon building permit FAQs

How much is a building permit in Mount Vernon?

It depends on project cost: $7.50 for $1,000, $30 for $10,000, $130 for $50,000 and $255 for $100,000, then $2.50 per $1,000 up to $500,000.

Do I need a permit for a deck?

Yes if the deck or porch is more than 30 inches high or has a roof.

How do I apply?

Online through the city’s application form, by email to buildinginspector@mtvernon.com, or in person at City Hall, 1100 Main Street.

Do electricians need a city license?

Yes. Electrical contractors need a $90 Mount Vernon license, renewed each year by June 1, with a qualified Supervising Electrician.

How much notice do inspections need?

At least 48 hours; call 618-242-6830 with the permit number, address and inspection type.

Do I need a permit for a sign?

Most signs need a city sign permit, but house numbers and names up to 1 square foot, security signs, government signs and one small sign per street frontage do not.

What does a demolition permit cost?

$5 for a one-story structure or items such as fences, pools and sheds, and $10 for buildings of two stories or more.

Does Jefferson County issue building permits outside the city?

The county’s department list shows no building or zoning office; its County Engineer handles permits for work on county highways.

Mount Vernon permit search and official resources

Ask Engineering and Inspections at 618-242-6830, weekdays 8 a.m. to 5 p.m., about an open permit. For copies of permits, plans or inspection records, file the city’s FOIA Request Form in person, by email or by mail to the FOIA Officer (the City Clerk) at Mt. Vernon City Hall, 1100 Main Street, PO Box 1708.

Inspections are where schedules slip.

Get a free quote →

Simplify Mount Vernon permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Mount Vernon sooner?

Let Alliance prepare, file, and track your Mount Vernon permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Mount Vernon permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.