Greene County, Illinois Building Permit Guide

To get a building permit in Greene County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Greene County has no building or zoning department; on unincorporated land the county board’s floodplain, solar and wind ordinances and the health department’s septic and well permits are the approvals that apply; only commercial solar and wind facilities need a county building permit.

Authority: No county building permitSeptic and wells: Greene County Health DepartmentPhone: 217-942-6961
County building permit
None for homesNo building or zoning office
Septic permit fee
None at presentApplication still required
Solar or wind facility
$5,000 per MWSpecial use fee, up to $125,000
Floodplain permit
County Board ChairmanOr his designee

Greene County’s government in Carrollton has no building, zoning or planning department, and its posted county ordinances cover only floodplain development, commercial solar and commercial wind. A rural builder deals with the Greene County Health Department (310 Fifth St., Carrollton, 217-942-6961), which approves septic systems before installation, currently with no permit fee, and permits wells; development in a floodplain needs a permit from the county board chairman or his designee. Carrollton, White Hall, Roodhouse, Greenfield and the villages handle building inside their own limits.

What requires a permit in unincorporated Greene County?

The county board’s ordinance page lists three sets of rules: the flood damage prevention ordinance (approved in July 2023), the commercial solar energy ordinance and the commercial wind ordinance. There is no county zoning ordinance or building code on the list, and the county posts no building permit application for ordinary buildings. In practice, the approvals for a rural project are these:

Approval needed

  • Any development in the floodplain, including buildings, additions, fill and accessory structures
  • A new or altered private sewage (septic) system, before construction
  • A new water well, a change to an existing well, or the sealing of an abandoned well
  • Commercial solar energy facilities and commercial wind energy facilities
  • Floodway construction on larger streams, through the state

No county permit published

  • Houses, garages, sheds and farm buildings outside the floodplain
  • Remodels and additions outside the floodplain
  • County electrical, plumbing or mechanical permits

Because the floodplain ordinance covers every kind of development in the floodplain, check the flood maps before building near a stream. Its building protection rules apply to a new building, or an alteration or addition to an existing one, valued at more than $1,000 or larger than 70 square feet, to improvements that add more than 20% to the floor area or reach 50% of the market value (counted cumulatively since the ordinance was adopted), and to manufactured homes and to travel trailers kept on a site more than 180 days a year. Protected buildings must be safe from flooding up to the flood protection elevation, which the ordinance sets at the base flood elevation plus one foot of freeboard.

What the county decides and what the state holds

The county board adopts the floodplain and energy ordinances; in 2026 it replaced its 2023 solar and wind ordinances with new versions that took effect on June 1, 2026, to comply with Public Act 104-0458, a new state law on county siting of these facilities. The health department enforces the state private sewage and water well codes through agreements with the Illinois Department of Public Health. The state also holds plumbing and roofing licensing and the statutory building minimums described in the code section below.

Greene County building department: who handles permitting

The only county building permit is the one the energy ordinances require for a commercial solar or wind facility. These are the offices a rural project goes through:

Short on time to read all of this?

Get a free quote →
Greene County offices for rural projects
OfficeRoleContact
Greene County Health Department, Environmental Health DivisionSeptic and well permits, inspections, water sampling310 Fifth St., Carrollton, IL 62016; 217-942-6961 (ext. 102 for septic); Monday to Friday 8 a.m. to 4 p.m.
County Board Chairman or his designeeFloodplain development permitsAsk the County Clerk’s office (217-942-5443) for the designee
Highway DepartmentCounty highways and bridges; help to townships and towns377 E. State Route 108, Carrollton; 217-942-6941; Monday to Friday 7:30 a.m. to 3:30 p.m.
County Clerk & RecorderBoard minutes, ordinances, recorded deedsCourthouse, first floor; 217-942-5443; Monday to Friday 8 a.m. to 4 p.m.

Aaron Haverfield, P.E., is the County Engineer. His department maintains 109 miles of county highway and 18 bridges, and assists the 13 townships, which maintain about 650 miles of road and 103 bridges, and the county’s municipalities. Each township has a road commissioner, listed on the Highway Department page.

Cities and villages in Greene County

Building inside the incorporated places is governed by each town, not the county: the cities of Carrollton (2,349 people), White Hall (2,159), Roodhouse (1,484) and Greenfield (997), and the villages of Kane (274), Rockbridge (170), Eldred (141), Hillview (91) and Wilmington (86). The county’s pages do not say which of them issue building permits; the Highway Department page lists a contact for each city and most villages, and the city or village hall can say what it requires.

Greene County permit types

The county-level permits are the health department’s and the floodplain permit.

Residential permits

  • Private sewage system: the department’s permit packet includes the application, a list of approved local soil classifiers and a homeowner maintenance guide. A subsurface seepage system needs an approved soil investigation, which goes to the department before approval; if the soil will not take a seepage field, a sand filter or aeration system is the alternative. The site plan must show the lot, house, sewage system and every water supply within 75 feet of the property.
  • Water well: the state application to construct, modify or abandon a well, plus a separate application for closed-loop geothermal wells and a pump installation report.
  • Floodplain development: the application needs scaled site drawings with property lines, existing grades and any fill, the location and size of buildings and additions, the lowest floor elevation of new buildings, and a cost estimate by a licensed engineer or architect (a signed contractor’s estimate also qualifies).
  • Garage or shed in the floodplain: allowed as an accessory to an existing home on a single-family lot if it is non-habitable, used only to store vehicles and tools, worth less than $10,000 or smaller than 500 square feet, anchored, built of flood-resistant materials below the base flood elevation, with utilities above the flood protection elevation and at least one opening on each wall within a foot of grade (one square inch per square foot of floor area).

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

Commercial buildings have no county building permit; the statewide minimums in the note below apply. Commercial solar and wind facilities are regulated by the county ordinances in force since June 1, 2026, which replaced the May 11, 2023 ordinances and the 2025 solar application-fee amendment. A solar facility is allowed only by special use permit and building permit, on land used for agricultural or industrial purposes. The process starts with a pre-application meeting booked at least five business days ahead; the applicant then files at least 10 copies of the special use application with the County Clerk plus an electronic copy, the board chairman names a county representative within five business days, and that representative’s written finding that the application is complete sets its filing date. Solar arrays must stand 150 feet from homes and community buildings on non-participating land and 50 feet from non-participating property lines and public road rights-of-way, unless the neighbor signs a recorded waiver. The board has held public hearings on solar projects in 2026, for N Main Solar, LLC on May 7 and Pumpkin Patch Solar, LLC on September 29, and its October 8 and November 12, 2026 agendas list solar and wind ordinance items, so ask the County Clerk for the current version before applying.

What comes before construction

  • Check the parcel and the town line. If the land is inside a city or village, that town’s rules apply.
  • Check the floodplain and, for floodway work on a rural stream draining ten square miles or more, get the Illinois Department of Natural Resources permit first.
  • Get the soil investigation done before applying for the septic permit; a preliminary site visit by the health department is available on request.
  • Road access: talk to the Highway Department or the township road commissioner about work along a county or township road.

Greene County permit costs and fees

A house or farm building on unincorporated land pays no county building permit fee, and the health department currently charges nothing for a septic permit. The fees the county does set are in Article 10 of its commercial solar and wind ordinances, effective June 1, 2026:

Rather talk it over?

Call 1-855-478-4290 →
Greene County fees for rural projects
ItemFee
Private sewage disposal permitNo permit fee at present; the application must still be approved before installation
Water well permitEntered on the state application; ask the health department
Water testing and samplingCharges given by phone, 217-942-6961
Floodplain development permitNo fee in the ordinance or on the county site; ask the County Clerk
Solar or wind special use permit application$5,000 per megawatt of nameplate capacity, up to $125,000, paid to the County Treasurer before processing
Solar or wind facility building permit$5,000 per megawatt of nameplate capacity, up to $75,000, deposited with the County Treasurer before the permit is issued
County costs above either feeBilled to the applicant, due within 15 calendar days of the county’s request

Nameplate capacity is counted in direct-current terms and includes any battery storage. Worked example: a 10-megawatt solar project pays $50,000 for the special use application and $50,000 for the building permit; a 40-megawatt project reaches both caps, paying $125,000 and $75,000. No hearing is held and no building permit is issued while any fee is unpaid, and the wind ordinance adds that the owner pays all county costs of hearings, permitting, inspections, decommissioning and disputes.

On a rural home site the real costs are the soil classifier’s investigation, the installer’s and well driller’s prices and, in a flood area, the engineer’s or architect’s elevation and cost work. The health department notes that its no-fee septic policy applies “at this time”, so confirm before you budget. Inside the cities and villages, local permit fees apply.

Trade permits and who may pull them

Greene County issues no electrical, plumbing or mechanical permits on unincorporated land and publishes no county contractor license or registration. The trade rules that apply on rural projects:

  • Septic work: work done by anyone other than the homeowner, who must own and occupy the single-family residence, must be done by a licensed contractor.
  • Soil investigations: done by an approved soil classifier, from the list in the health department packet.
  • Wells and pumps: constructed under the state water well rules, with a pump installation report filed for new pumps.
  • Plumbing and roofing: plumbers hold licenses from the Illinois Department of Public Health, and roofing contractors licenses from the Department of Financial and Professional Regulation.

Rather not deal with the Greene County building department?

Get a free quote →

In the floodplain, the cost estimate on the development permit must come from a licensed engineer or architect, or be a contractor’s signed estimate.

How to get permits for a rural Greene County project

1. Confirm the land is unincorporated

Check the parcel against the town limits; inside a city or village, go to that town.

2. Check for floodplain

If any part of the work is in the floodplain, prepare the development permit application with drawings, grades, lowest floor elevation and cost estimate, and file it with the county board chairman or his designee.

3. Order the soil investigation

Hire an approved soil classifier and send the report to the health department.

4. File the septic application

Submit the private sewage permit application and site plan; wait for approval before any installation.

5. File the well application

Use the state well application for a new, modified or sealed well.

6. Call for inspection

Give the health department at least 48 hours’ notice so it can inspect the septic system before it is covered.

Review, corrections and what causes delay

The health department reviews the soil report and application and either approves the system or consults with the owner on a design that suits the soil, so a site unsuitable for a seepage field means a sand filter or aeration design and more time. Floodplain permits are refused if the development does not meet the ordinance, and the responsible official compares the site’s elevation with the base flood elevation before deciding. Commercial energy projects also go through public hearings before the county board.

Inspections in Greene County

There are no county building inspections or certificates of occupancy on unincorporated land. The inspections that do happen:

  • Septic: the health department inspects every installation before it is covered, after at least 48 hours’ notice, and investigates sewage complaints.
  • Wells: the department issues well permits following an inspection, sample and analysis reported to the owner, and offers a sampling and inspection service for existing private water supplies, including advice on disinfecting a contaminated well.
  • Floodplain: the ordinance has the responsible official perform site inspections to check compliance and make substantial damage determinations for buildings in the floodplain.

In the towns, inspections follow the city or village’s own rules.

Want this handled start to finish?

Get a free quote →

Illinois building code in Greene County

Greene County’s posted ordinances include no building code, so the statutory minimums described below apply to new homes and commercial buildings on unincorporated land, alongside the state private sewage and water well codes run by the health department. FEMA’s Community Status Book lists unincorporated Greene County (community 170901) as participating in the National Flood Insurance Program, with current flood maps dated April 2, 2009.

Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline

Greene County permit FAQs

Do I need a county building permit in rural Greene County?

Not for a house or farm building; the county has no building or zoning office. You need health department approval for septic and wells, and a floodplain permit in flood areas.

How much is a septic permit in Greene County?

The health department says there is no permit fee at this time, but the application must be approved before installation.

Can I install my own septic system?

Only if you own and occupy the single-family home; otherwise a licensed contractor must do the work.

Who issues floodplain permits?

Under the county’s flood damage prevention ordinance, the Greene County Board Chairman or his designee.

What does a solar or wind farm pay the county?

$5,000 per megawatt for the special use application (up to $125,000) and $5,000 per megawatt for the building permit (up to $75,000), plus county costs above those amounts, under the ordinances in force since June 1, 2026.

Who handles permits in Carrollton or White Hall?

The city, not the county; contact the city hall.

Is unincorporated Greene County in the flood insurance program?

Yes. FEMA lists it as participating, with maps dated April 2, 2009.

Greene County permit records and official resources

There is no county building permit search. Septic and well permits and inspection records are held by the health department, which has its own Freedom of Information Act page; floodplain permits and board actions by the county board office and the County Clerk, who keeps the board minutes; recorded deeds by the County Clerk & Recorder; and aerial mapping by the Supervisor of Assessment. The county posts a FOIA request form for county records.

Inspections are where schedules slip.

Get a free quote →

Simplify Greene County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Greene County sooner?

Let Alliance prepare, file, and track your Greene County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Greene County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.