In the Village of Cary, building permits come from the Community Development Department at 755 Georgetown Drive. Common home projects such as roofs, decks, fences and water heaters are filed in the village’s BS&A online portal; other work goes in by mail, by email or at Village Hall. Ordinance O24-06-03 sets mostly flat fees, from $100 for a residential re-roof to $1,250 for a new house of up to 3,200 square feet, and standard home-improvement permits are usually processed within 10 business days.
What requires a building permit in Cary?
Cary publishes two handouts, one listing projects that need a permit and one listing projects that do not. Its 2024 code ordinance also removed several of the International Residential Code’s exemptions, so accessory structures, fences, sidewalks, driveways and decks all need a permit, as does any retaining wall over 2 feet high.
Permit needed
- Fences, including replacing a whole side
- Driveways, even a same-size repave, and driveway ribbons
- Patios, walks, stoops, decks and sport courts
- Sheds, pergolas, gazebos and detached garages
- Roofing or siding over 100 square feet, or a whole slope or wall
- Window and door replacement, except vehicle garage doors
- Water heaters, furnaces, A/C condensers and generators
- Basement finishing and kitchen or bath remodels with drywall or fixture changes
- Fire, smoke or water damage repairs
No permit
- Painting, staining and flooring
- Sealcoating a driveway
- Replacing appliances or fixtures in the same place
- Replacing a couple of fence panels or a few shingles
- Gutter, soffit and fascia repair
- Cabinet-only kitchen or bath updates with no trade work
- Removing a shed, patio or walk
- Playground equipment and rain barrels
Retaining or landscape walls need a permit when they are over 2 feet high, sit in a drainage swale, stand within 6 feet of a side or rear lot line or are in a floodplain. Regrading, filling or changing a drainage swale counts as site work and also needs a permit. A contractor may apply, but the village holds the property owner responsible for making sure a permit is issued before work starts.
What Cary decides and what the state holds
Ordinance O24-05-06, adopted May 21, 2024, brought Cary onto the 2021 International Building, Residential, Mechanical, Fuel Gas, Fire, Existing Building, Property Maintenance and Swimming Pool and Spa codes and the 2023 National Electrical Code. Its local amendments delete the residential code’s requirement for fire sprinklers in single-family homes, make permits expire after 180 days with no activity and name the Village Board as the appeals board. The ordinance’s title lists the 2021 energy code, while the village’s code page lists the 2024 International Energy Conservation Code with Illinois amendments. Plumbing follows the 2014 Illinois State Plumbing Code, accessibility the 2018 Illinois Accessibility Code, and the plumbing, fire alarm, sprinkler, roofing, irrigation and radon licenses the village collects are issued by the state.
Short on time to read all of this?
Get a free quote →Cary building department: who handles permitting
The Community Development Department reviews plans, issues building permits and inspects all work in the village. The department is led by Director of Community Development Brian Simmons, and John Fitch is the village’s Building & Zoning Official. McHenry County does not permit work inside Cary, and since November 19, 2015 the county’s stormwater permit is no longer needed either: Cary is a certified community that enforces the countywide stormwater ordinance itself.
| Detail | Information |
|---|---|
| Office | Community Development, Village Hall, 755 Georgetown Drive, Cary, IL 60013 |
| Phone | 847-639-1100 |
| permits@caryillinois.com (project address in the subject line) | |
| Counter hours | Monday to Thursday, 8:30 a.m. to 5:00 p.m.; Friday, 8:30 a.m. to 12:00 p.m. |
| Online portal | BS&A Online (applications, fees, contractor registration and inspections) |
Cary permit types
The BS&A portal currently takes 14 permit types: air conditioner, chimney, deck, deck restoration, driveway, fence, furnace, patio, re-roof, re-siding, shed, walk or sidewalk, water heater and windows or doors. The village’s permits page says the list will be expanded further in 2026. Every other permit is filed on a paper application by mail, at Village Hall, through the drop box or by email.
Residential permits
- Applications. Separate forms cover repairs, alterations and additions, a new house or duplex, and new multi-family buildings, with a lot coverage calculation form for site projects.
- What to include. A plat of survey marking the work area, dimensions and the structure’s location; a description of the work; contractor contact details; and drawings. More than 30 project handouts list the specific items for decks, pools, sheds, roofs, solar panels, generators, egress windows and other jobs.
- Over-the-counter permits. Re-roof, re-siding, water heater, water or sewer line repair, window and door, and furnace and air-conditioner replacements can be issued at the counter when the submittal is complete.
- Portal accounts. Contractors, design professionals and agents need a BS&A account; a homeowner may apply without one.
Building or remodeling a home here? Alliance handles home building permits, so the crew isn't waiting on the counter.
Commercial permits
Commercial applications go in by email or through the drop box at the Cary Municipal Center, using the commercial and industrial application, the site work application or the repairs, alterations and additions form, with handouts for interior and restaurant alterations, new buildings, cellular equipment and fire sprinkler submittals. Every new business, including one moving within the village, needs a certificate of occupancy application, and the village posts a life safety checklist with it. Commercial build-outs and interior alterations start at $750, and new commercial, office and multi-family buildings at $2,000 plus any direct costs the village pays for professional review.
Not sure this scope needs a permit?
Get a free quote →For tenant improvements and new commercial builds, Alliance handles commercial permit filing through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning. Projects must meet the Cary Unified Development Ordinance. Zoning requests go before the Board of Zoning, Planning and Appeals, which the Planning and Zoning Division supports.
- Stormwater. Work that crosses the disturbed-area, location or work-type thresholds in Section 17.60.020(B) of the McHenry County Stormwater Management Ordinance needs a stormwater permit, which Cary now processes alongside the building permit; its fees depend on the classification of the development.
- Water and sewer. New services pay tap-on fees: $5,864 for water and $6,656 for sewer on a 1-inch service, plus $483 for a 3/4-inch residential meter, on the village’s development fee sheet.
- HOA rules. Subdivision covenants are separate from village approval.
Cary permit costs and fees
Ordinance O24-06-03, adopted by the Mayor and Board of Trustees on June 18, 2024, replaced Cary’s fee schedule (Appendix A, Section 15.36.010 of the village code). Most permits are a flat fee by type. Each fee is a minimum: the village adds any direct expenses it pays for professional services such as consultant review.
| Work | Fee |
|---|---|
| Fence under 25 linear feet; certificate of occupancy | $50 |
| Residential roofing, siding, A/C, furnace, water heater, door, fence over 25 feet, walk or stoop, fewer than 10 windows | $100 |
| Driveway, shed, patio or fire pit, electrical panel, residential solar, residential EV charger, more than 10 windows | $150 |
| Deck, generator, retaining wall, electric service upgrade, minor kitchen or bath remodel, hot tub | $200 |
| Gazebo, above-ground pool, masonry fireplace, minor basement remodel, house demolition | $350 |
| Detached garage, in-ground pool, major kitchen, bath or basement remodel, addition under 350 sq ft | $500 |
| Residential addition over 350 sq ft; commercial build-out | $750 |
| New single-family detached home | $1,250 up to 3,200 sq ft, plus $0.20 per sq ft above that |
| New commercial, office or multi-family building | $2,000 up to 5,000 sq ft, plus $0.50 per sq ft above that |
| Tree replacement fee, new dwelling | $425 per unit |
| Reinspections | First free; second $50; third $100; later $125 each |
Rather talk it over?
Call 1-855-478-4290 →Worked example: a new single-family house of 3,800 square feet of gross floor area pays $1,250 plus $0.20 for each of the 600 square feet over 3,200, or $120, for a $1,370 permit, and the $425 tree replacement fee brings the total to $1,795 before tap-on, impact and any consultant charges. Impact fees for a three-bedroom house reach $10,440.50 for school, park, fire and library districts on the 2019 development fee sheet; the library share applies only to land annexed after April 2, 1991.
Residents aged 65 or older get a one-third discount on permits for alterations to their own home, and disabled veterans pay no fee for improvements that accommodate a disability. One extension of up to 180 days is free; later extensions cost 50% of the original fee. If work has not started within 90 days, a written refund request returns the fee minus $100 and any direct costs. Work stopped for lack of a permit pays the permit fee plus 50%.
Trade permits and who may pull them
Every general contractor and subcontractor working in Cary registers with Community Development for $75 a year ($38 after July 1) and files a $10,000 surety bond each year. State-licensed plumbing, fire alarm and fire sprinkler contractors are exempt from both. Plumbing contractors instead submit copies of their state license and registration and an original letter of intent for each project, signed by the plumber named on the registration and notarized or corporate-sealed. A licensed plumbing contractor must do the sanitary service within 5 feet of the building and the whole water service from the building to the main, including the tap.
Roofers provide a copy of their state license, and work on commercial buildings or multi-family buildings with more than eight units requires an unlimited roofing license. Fire alarm and sprinkler contractors show their state licenses, lawn irrigation contractors their state registration and radon mitigation contractors their state license. Electricians are asked for a municipal electrician’s license or an ICC electrical contractor certificate, and siding, window and interior remodeling contractors for their Illinois lead paint certification. Registration and fees can be paid through the BS&A portal.
Rather not deal with the building department?
Get a free quote →How to apply for a Cary building permit
Confirm the project needs a permit and read its handout for the drawings and survey required.
Contractors register, post the $10,000 bond and open a BS&A account; homeowners can skip the account.
Use the portal for the 14 listed permit types; mail, email or hand in everything else at 755 Georgetown Drive.
Larger site work adds the Stormwater Management Application to the same submittal.
Pay in the portal or at Village Hall once the review is complete.
Give two business days’ notice for every inspection on the permit.
Review, corrections and what causes delay
Standard residential home-improvement permits are usually processed within 10 business days and new homes or additions within 15. Six replacement permits can be issued over the counter when everything is supplied. Email is accepted only for permit types the portal does not take, so the 14 portal types must be filed online or on paper. An application missing the plat of survey with the work’s size and location, or the plumber’s notarized letter of intent, is incomplete, and staff may ask for more items once it is submitted. A permit expires after 180 days with no activity on the project, and a change of scope after issuance is billed at $60 an hour for plan review plus $40 for each extra inspection.
Inspections and certificates in Cary
Every permit carries at least one inspection, and work cannot continue past a required inspection until it passes. Cary needs two business days’ notice. Building inspections run Monday to Friday from 8:30 a.m. to 3:30 p.m. and can be scheduled, changed or cancelled in the BS&A portal. A deck, for example, is inspected at the pier holes, at rough framing before the deck boards go on, and at final. The first reinspection is free; after that the charge rises from $50 to $125.
A certificate of occupancy or temporary certificate costs $50. Cary’s inspections page adds that each elevator must have a certified inspection twice a calendar year and post a current inspection certificate.
Illinois building code in Cary
Cary enforces the 2021 International codes and the 2023 National Electrical Code adopted by Ordinance O24-05-06. FEMA’s Community Status Book lists the Village of Cary (community 170475) as participating in the National Flood Insurance Program, with current flood maps dated November 16, 2006; the village is not in the Community Rating System. Floodplain and stormwater rules come from the McHenry County Stormwater Management Ordinance, which the village enforces as a certified community.
Want this handled start to finish?
Get a free quote →Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline
Cary building permit FAQs
How much does a building permit cost in Cary?
Most permits are flat fees: $100 for a residential re-roof or water heater, $150 for a driveway or shed, $200 for a deck and $1,250 for a new house up to 3,200 square feet.
Do I need a permit to repave my driveway in Cary?
Yes. Repaving the same size, expanding it or adding paver or concrete ribbons all need a $150 driveway permit, which can be filed online. Sealcoating does not.
Do I need a permit to replace windows?
Yes, for any window or door except a vehicle garage door. Fewer than 10 windows is $100, and the permit can be issued over the counter.
How long does plan review take in Cary?
Usually 10 business days for standard home improvements and 15 for new homes and additions.
Do contractors have to register with the village?
Yes. General contractors and subcontractors pay $75 a year and post a $10,000 bond; state-licensed plumbing, fire alarm and sprinkler contractors are exempt.
Can a homeowner apply for a permit?
Yes. A homeowner can apply in the portal without an account, or on paper. Plumbing that reaches the water main or the sanitary service near the building must still be done by a licensed plumbing contractor.
Is there a senior discount on permits?
Applicants 65 and older get one-third off permits for alterations to their own home, but not for a new house.
Cary permit search and official resources
Permit holders can follow applications, fees and inspections in their BS&A account. To obtain permit files or inspection records, send a written Freedom of Information Act request: by email to the FOIA Officer with the request in the body of the message (attachments are not opened), or on the village’s FOIA form by mail or drop-off at Village Hall. The village answers non-commercial requests within five business days, and the first 50 pages of copies are free.
Inspections are where schedules slip.
Get a free quote →- Cary permits – general information
- Projects that require a permit
- Projects that do not require a permit
- Residential permits and handouts
- Commercial permits
- Adopted building codes
- Ordinance O24-05-06, 2021 building codes
- Ordinance O24-06-03, building permit fees
- Contractors and bonds
- Inspections
- Stormwater Management Ordinance permits
- Development, tap-on and impact fees
- Planning and zoning
- Freedom of Information Act
Simplify Cary permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Cary sooner?
Let Alliance prepare, file, and track your Cary permits while your crew stays on the job.
More Illinois permitting guides
McHenry County
Read guide →Crystal Lake
Read guide →Huntley
Read guide →Cass County Building Permit Guide
Read guide →Centralia Building Permit Guide
Read guide →Champaign Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Cary permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.