The City of Milton Community Development Department reviews plans and issues building permits for construction inside Milton, and every building or renovation application is filed in the City’s CityView Web Portal. Permit fees follow a valuation table, plus a $25 administrative fee and, for a new house, a $350 site fee and $100 plan review; the City issues review comments or approval within 10 business days of accepting an application.
What requires a permit in Milton?
Permit generally required
- New single-family homes and townhomes
- Additions and renovations: bedrooms, bathrooms, kitchens, decks, garages, structural work and windows
- Basement, attic and bonus-room finishes
- Sheds and other detached accessory structures
- Pools and pool houses
- Moving or adding plumbing, appliances or electrical wiring and services
- Adding or replacing HVAC equipment
- Roof replacement and demolition
- Fences, signs and tree removal (separate CityView applications)
Not generally required
- Wallpapering and painting, inside and most exterior finishes
- Floor coverings
- Cabinets and countertops
- General maintenance, including appliance maintenance
Milton building department: who handles permitting
Community Development issues permits for all construction in Milton, reviews applications and plans, and inspects the work. Heah “Arthur” Tay is the Acting Building Official. The City keeps copies of the codes it enforces at City Hall.
| Detail | Information |
|---|---|
| Authority | City of Milton Community Development |
| Phone | 678-242-2545 (Permit Desk) |
| Permits@miltonga.gov; inspection requests to Inspectionrequest@miltonga.gov | |
| Office | 2006 Heritage Walk, Milton, GA 30004 |
| City Hall main line | 678-242-2500 |
| Online applications | CityView Web Portal |
| Acting Building Official | Heah “Arthur” Tay, 678-242-2567 |
Short on time to read all of this?
Get a free quote →Milton permit types and filing
All building and renovation applications are completed through the CityView Web Portal. The portal also takes Public Works, land disturbance and grading, planning, tree removal, sign, banner and special event applications, and shows the status of applications and inspections. Fees can be paid in CityView, by mail or in person at City Hall, by check or by card (MasterCard, Visa or American Express).
Forms the City publishes for building permits:
- Project checklists for residential new construction, additions, interior renovations, decks, accessory structures and pools, and for commercial interior remodels and commercial plan review.
- Homeowner Permit Affidavit – Letter of Indemnification, for an owner acting as their own general contractor.
- Residential Subcontractor Affidavit for each electrical, plumbing, HVAC, gas or low-voltage subcontractor, with copies of their business licence and state trade licence; it must be in before a Certificate of Occupancy is issued.
- CO/COC Application for a Certificate of Occupancy or Completion.
Permit costs and fees in Milton
Milton’s Community Development fee schedule bases the permit fee on project value, using ICC building valuation data as the minimum. Fixed charges are added by project type.
| Project value | Permit fee |
|---|---|
| $1–$500 | $23.50 |
| $501–$2,000 | $23.50 plus $3.50 per $100 over $500 |
| $2,001–$25,000 | $69.25 plus $14 per $1,000 over $2,000 |
| $25,001–$50,000 | $391.75 plus $10.10 per $1,000 over $25,000 |
| $50,001–$100,000 | $643.75 plus $7 per $1,000 over $50,000 |
| $100,001–$500,000 | $993.75 plus $5.60 per $1,000 over $100,000 |
| $500,001–$1,000,000 | $3,233.75 plus $4.75 per $1,000 over $500,000 |
| Over $1,000,000 | $5,608.75 plus $3.65 per $1,000 over $1,000,000 |
Not sure this scope needs a permit?
Get a free quote →| Project | Fee |
|---|---|
| New house or townhouse | $350 site, $25 administrative, $50 Certificate of Occupancy, $100 plan review up to 5,000 sq ft ($200 to 10,000; $350 above), plus the permit fee |
| Basement finish, kitchen or bath remodel, addition | $25 administrative and the same plan review scale, plus the permit fee; $350 site fee for an addition extending beyond the original house |
| Deck, pool house, garage, screened porch, shed or fence | $100 site and $25 administrative, plus the permit fee |
| Pool | $250 flat permit fee, $100 site and $25 administrative |
| Roof or replacement windows | $50 permit fee and $25 administrative |
| Demolition | $100 permit fee and $25 administrative |
| Electrical, plumbing or mechanical permit | $25 administrative, plus the permit fee |
| New commercial building | $350 site, $25 administrative, $50 CO, plan review at 50% of the permit fee, $125 fire review up to 5,000 sq ft |
| Re-inspection / fire re-inspection | $50 / $100 |
| Temporary Certificate of Occupancy (up to 60 days) | $200 |
| Residential erosion control | $200 per lot |
For example, a $40,000 kitchen remodel has a permit fee of $391.75 plus 15 × $10.10, or $543.25, before the $25 administrative fee and $100 plan review.
Impact fees: a new single-family house, apartment or townhouse pays a development impact fee of $7,757.85 per dwelling, most of it ($6,215.10) for parks and recreation, with smaller parts for fire, police and roads. If more floor area is built than the permit showed, the extra fee is based on the schedule in force when the interior finish permit or certificate of occupancy is issued.
An expired permit can be reinstated for $100 if the work is at least 90% complete, for half the original fee (minimum $200) if it is less complete, or for the full fee if no work was done.
Electrical, plumbing, mechanical and gas work
Electrical, plumbing and mechanical permits are each charged the $25 administrative fee plus the valuation-based permit fee. On a building permit, every electrical, plumbing, HVAC, gas and low-voltage subcontractor files a Residential Subcontractor Affidavit with copies of their current business licence and state trade licence, emailed to permits@miltonga.gov; the Certificate of Occupancy is not issued without them. Gas work is checked with a gas test before the temporary-to-permanent power and final inspections.
Rather talk it over?
Call 1-855-478-4290 →Alliance handles electrical permit filing for contractors here. More on this: who pulls the electrical permit.
Application documents and plan review
Each project type has its own checklist. For a new house (checklist revised February 2, 2026), upload one collated PDF plan set to CityView and cloud any later changes on the revised pages.
Site plan
- Address on every page, setbacks, zoning buffers and easements
- Existing and proposed structures with distances to lot lines
- Tree protection fencing, and the location, diameter and species of trees to be removed
- Stream buffers: 25 ft state undisturbed, 50 ft City undisturbed and 75 ft impervious setback
- FEMA flood map panel and date, topography at 1–2 ft intervals and an 811 note
- Limits of disturbance and erosion control BMPs; a GSWCC checklist over 1 acre or within 200 ft of state waters
Building plans and licences
- Heated, unheated, garage, patio, deck and porch square footage
- Room uses, dimensions, door and window sizes, smoke and CO alarm locations
- Electrical service size, Manual J equipment sizing and REScheck or prescriptive energy compliance
- Foundation, braced wall and framing plans; engineering for anything not prescriptive in the IRC
- Contractor business licence; subcontractor licences and affidavits
- Homeowner affidavit if the owner is the general contractor
Once an application is accepted for review, the City issues approval or revision comments within 10 business days for all permit types. Over 5,000 sq ft of impervious coverage may need extra water quality treatment.
Under the City code, an application is not complete until all fees are paid and every reviewing agency has received it and given any required approval. Milton also runs a third-party inspection and plan review program: Community Development keeps a list of approved third-party inspectors and plan reviewers, and an applicant who hires one from that list still pays the City 50% of the inspection or plan review fees the City would have charged.
Rather not deal with the building department?
Get a free quote →How to apply: 6-step Milton process
Confirm the parcel is inside Milton and check zoning, stream buffers and flood zones on the site.
Use the City checklist that matches the exact residential or commercial scope.
Upload a single collated PDF with the application, licences and affidavits.
Comments or approval come within 10 business days of acceptance; cloud changes on revised sheets.
Build to the approved plans and request each inspection in CityView or by email.
Submit subcontractor affidavits and the CO/COC application, then pass the final site, arborist and combination inspections.
Milton inspections
Request inspections in CityView or by email to Inspectionrequest@miltonga.gov. The City’s Building Inspections Required list sets out the inspections for each permit type. A new house goes through a pre-construction site visit, temporary power pole, footings, foundation wall and damp-proofing, underground plumbing and electrical, slab, sheathing, moisture barrier, rough-in combination, insulation, drywall fastener, gas test, temporary-to-permanent power, and final arborist, site and combination inspections. Roof and window replacements need only a final; pools add plumbing tests, the pool steel and perimeter bonding.
Build to the approved plans: changes can fail inspection and need a plan-review resubmittal. A re-inspection costs $50 ($100 for a fire re-inspection). Apply for the Certificate of Occupancy or Completion with the CO/COC Application in CityView or by email.
Georgia building code
Georgia's State Minimum Standard Codes apply statewide: the 2024 International Building, Residential, Plumbing, Mechanical, Fuel Gas, and Swimming Pool and Spa Codes and the 2023 National Electrical Code, with Georgia Amendments, in force since 1 January 2026; the energy code is still the 2015 IECC with Georgia supplements. The Georgia State Minimum Standard Codes
Want this handled start to finish?
Get a free quote →Milton permit search and official resources
These are the primary sources behind this guide. Codes, fee schedules and procedures change — confirm the position for your filing date.
- Georgia DCA current construction codes
- Milton Building Forms and checklists
- Milton CityView Web Portal
- Milton Community Development: Building
- Milton residential permits
- Milton Community Development fee schedules
- Milton Residential New Construction Application Checklist
- Milton Building Inspections Required
- Milton Residential Subcontractor Affidavit
- Milton Certificate of Occupancy
- Milton Code: third-party inspection and plan review
- Milton Code Chapter 25: impact fees
Milton permit FAQs
Inspections are where schedules slip.
Get a free quote →Does Milton issue its own building permits?
Yes. Milton Community Development issues permits for all construction activity inside the City.
How much is a building permit in Milton?
The permit fee follows a valuation table, for example $391.75 plus $10.10 per $1,000 for a $25,001–$50,000 project, plus a $25 administrative fee and type-specific charges such as plan review and site fees.
What impact fee does a new house pay in Milton?
$7,757.85 per dwelling for a single-family house, apartment or townhouse.
How long does plan review take?
Milton states that approval or revision comments are issued within 10 business days once the permit is accepted for review.
Do I need a permit to replace my roof or windows?
Yes. Roof and replacement-window permits cost a $50 permit fee plus the $25 administrative fee, with a final inspection.
Can a homeowner act as their own contractor?
Yes. Submit the City’s Homeowner Permit Affidavit – Letter of Indemnification with the application.
Can I schedule inspections online?
Yes. Milton allows inspection requests through CityView and also publishes an inspection-request email.
Simplify Milton permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Georgia. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Milton sooner?
Let Alliance prepare, file, and track your Milton permits while your crew stays on the job.
More Georgia permitting guides
Fulton County
Read guide →Alpharetta
Read guide →East Point
Read guide →Monroe Building Permit Guide
Read guide →Monroe County Building Permit Guide
Read guide →Moultrie Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Milton permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.