Municipal Guide Georgia Dunwoody · DeKalb County

Dunwoody Building Permit — Filed & Tracked For You

Everything contractors, builders, and developers need to pull a Dunwoody building permit — the 2025 move to CentralSquare, contractor accounts and agent forms, why photographs never substitute for an inspection, the insulation sequencing rule, and the fraud warning the city has published.

Authority: City of Dunwoody Community Development DepartmentCode: 2024 Georgia State Minimum Standard CodesSubmission: CentralSquare, with a Contractor Account
Authority
Community DevelopmentCity limits since 2008
System
CentralSquareReplaced iWorQ in 2025
Inspections
No photosPictures never substitute
Valuation
City calculatesFloor area by cost per square foot

Dunwoody building permits come from the Community Development Department, and all construction activities in the city require a permit. The department's stated purpose is to regulate building and construction, administer the Georgia State Minimum Standard Codes, and establish permitting and inspection procedures.

The system changed recently and both names still circulate. On August 4, 2025 Dunwoody's Community Development operations moved to CentralSquare, replacing iWorQ. A Contractor Account is required to apply.

Applies inside the Dunwoody city limits, incorporated 2008. Sandy Springs, Brookhaven, Chamblee, Doraville, and unincorporated DeKalb County each permit their own work.

📷

Pictures are not accepted in lieu of inspections. And insulation cannot be installed for the rough-in — it is a visual obstruction, so the insulation inspection follows the rough-in. Insulating early to keep a schedule means pulling it back out.

What requires a permit in Dunwoody?

Dunwoody incorporated in 2008, the first of the DeKalb County new cities. All construction activities in the city require a permit through the Community Development Department, whose stated purpose is to regulate building and construction in Dunwoody, administer and enforce the Georgia State Minimum Standard Codes, and establish procedures for permitting and inspection.

The system changed recently and both names are still in circulation. On August 4, 2025 Dunwoody's Community Development operations moved to CentralSquare, replacing the old system, iWorQ. Users with an account access CentralSquare to submit new permit applications and code complaints; anyone with an application or complaint that predates the move should contact staff to make sure their information transferred.

To apply through the portal you must have a Contractor Account. And after submitting, the city asks a small but important extra step: email the permits address to alert Community Development staff that you have uploaded your application and plans. An upload with no email can sit unnoticed.

The enforced code is the Georgia State Minimum Standard Codes — the 2024 International Building Code and 2024 International Residential Code with Georgia Amendments, alongside the 2024 International Plumbing, Mechanical, Fuel Gas, and Swimming Pool and Spa Codes and the 2023 National Electrical Code with the 2026 Georgia Amendments. Georgia turned its codes over on January 1, 2026. The Board of Community Affairs, acting on the recommendation of the State Codes Advisory Committee, adopted the 2024 editions of the building, residential, plumbing, mechanical, fuel gas, and swimming pool and spa codes, together with the 2023 National Electrical Code carrying the 2026 Georgia Amendments. A project drawn to the previous editions is drawn to a superseded code, and the Georgia Amendments — not the base I-Code text — are what the plan reviewer reads.

Permit required

  • All construction activities within the city
  • New construction, additions, deck replacement, retaining walls, swimming pools, permanent signs, and fire sprinklers — all of which require plan review
  • Land disturbance
  • Plumbing, electrical, low voltage, heating and air conditioning, and utility work
  • Development permits where the project went before a board or commission
  • Interior remodelling or additions, which trigger smoke and carbon monoxide alarm requirements
  • Work that may also need DeKalb County, Georgia DOT, or state environmental permits

Typically exempt

  • Painting, flooring, and other cosmetic work
  • Ordinary repairs that do not touch structure or a regulated system
  • Work outside the city limits — unincorporated DeKalb, Brookhaven, Chamblee, Doraville, and Sandy Springs all differ
  • Like-for-like replacements that do not alter a regulated system
⚠️ Dunwoody has published a fraud warning. Scammers posing as City staff have targeted residents and businesses with planning-related applications — zoning cases, variance requests, and special administrative permits — sending fake invoices and requesting payment by electronic wire transfer. The city is explicit that it never uses wire transfers for these matters. Treat any emailed change of payment instructions as false until confirmed by phone.

Dunwoody building department: who handles permitting

Community Development is reached on 678-382-6800, with the Permit Desk on 678-382-6821 and a dedicated permits email address. Code enforcement runs on its own line and address. The Permit Desk is also where you obtain construction specifications, the plan review checklist, details, buffer regulations, and stormwater regulations.

Permit fees are based on construction valuation, and Dunwoody calculates that valuation itself: the city derives it from the floor area of the project and a pre-determined cost per square foot based on the type of construction. That means the figure follows the city's table rather than your contract price, so quoting from a contract value can mislead a client.

Several approvals sit outside the city. Additional permits may be required from DeKalb County, the Georgia Department of Transportation, the Georgia Soil and Water Conservation Commission, the Environmental Protection Division, or the Dunwoody Public Works Department, and outside-agency review can add materially to the overall timeline.

Dunwoody permitting contact
DetailInformation
AuthorityCity of Dunwoody Community Development Department
ScopeInside the Dunwoody city limits — incorporated 2008
Community Development678-382-6800
Permit Desk678-382-6821
PortalCentralSquare — replaced iWorQ on August 4, 2025
AccountA Contractor Account is required to apply online
After uploadingEmail the permits address to alert staff
ValuationFloor area times a pre-determined cost per square foot
💻

Pictures are not accepted in lieu of inspections in the City of Dunwoody. And the insulation cannot be installed for the rough-in inspection — it is considered a visual obstruction, so the insulation inspection is conducted after the rough-in. Insulating early to keep a schedule moving means pulling it back out.

Dunwoody sits inside DeKalb County but is not permitted by it, and it borders Sandy Springs, Brookhaven, Chamblee, and Doraville. Some third-party listings still name eTRAKiT or iWorQ as Dunwoody's portal; the city's own notice says operations moved to CentralSquare on August 4, 2025.

Dunwoody permits: record types and what each covers

Dunwoody's records include several that only appear once you look at the residential checklists — the agent form, the deck detail, the alarm requirements. These are the records you will file:

Residential permit types

Residential permit types in Dunwoody
Permit typeWhat triggers itReview pathFee basis
New constructionNew dwellings, additions, and accessory structures above the local size thresholdFull plan review against the 2024 IRC with Georgia Amendments, plus zoningValuation-based
Renovation / alterationStructural changes, layout changes, or added plumbing, mechanical, or electricalPlan review scaled to scope; existing-building provisions apply only where locally adoptedValuation-based
ReroofRoof covering replacement, recover, and structural deck repairDry-in and deck inspection; plan review rarely requiredValuation or squares
Solar photovoltaicRooftop or ground-mount arrays, with or without battery storageElectrical review led, with structural review of the attachmentFlat or system-size based
Battery energy storageWall or floor-mounted storage added to a dwellingElectrical review plus fire separation and location checkFlat or per-permit minimum
ElectricalService changes, panel upgrades, new circuits, EV chargers, and rewiringTrade review; filed as its own record under a Class I or Class II licencePer-permit minimum or per-device
PlumbingNew piping, repipes, fixtures, gas piping, and water heater replacementTrade review under a Journeyman or Master licencePer-permit minimum or per-fixture
Mechanical / HVACChangeouts, new ductwork, and refrigerationTrade review; conditioned air licence class keyed to system capacityPer-permit minimum or per-unit
Deck and porchNew decks, screened porches, and structural rebuildsFooting and framing review against the residential codeFlat or valuation-based
Pool and spaIn-ground and above-ground pools, spas, barriers, and bondingStructural, barrier, and electrical bonding review under the 2024 ISPSCValuation-based
Accessory structureSheds, detached garages, and carports above the local size thresholdZoning first, then structural review where applicableFlat or valuation-based
DemolitionFull or partial demolition of a structureUtility disconnect verification and asbestos notificationFlat
Land disturbanceClearing, grading, and any disturbance above the local thresholdErosion and sedimentation review on its own statutory clockPer-acre or valuation-based
Authorized Permit Agent formSubmitting licences on behalf of another individualFiled alongside the contractor's licence, business licence, and photo IDNo separate fee
Prescriptive deck detailA single-span, single-level residential deckA copy must be on the job site for each required inspectionNo separate fee

Commercial permit types

Commercial permit types in Dunwoody
Permit typeWhat triggers itReview pathFee basis
New constructionGround-up commercial, industrial, and multifamily buildingsFull multi-discipline review; sealed plans requiredValuation-based
Tenant build-outInterior fit-ups and suite build-outs in an existing shellConcurrent building, trade, and fire reviewValuation-based
Renovation / alterationStructural, envelope, or system changes to an existing buildingPlan review scaled to scope; accessibility triggers attachValuation-based
Change of occupancyConverting a building from one occupancy classification to anotherLife-safety, accessibility, and zoning reviewValuation or flat
Shell buildingA building permitted without a known tenant or useShell review only; no certificate of occupancy until a build-out closesValuation-based
ReroofCommercial roof covering replacement or recoverStructural check on added dead load; fire review where applicableValuation or squares
Solar photovoltaicCommercial rooftop, carport, and ground-mount arraysStructural, electrical, and fire access reviewValuation or system-size based
ElectricalService, distribution, and branch circuit workTrade review; separate record from the building permitValuation or per-device
PlumbingSupply, waste, vent, grease, and gas systemsTrade review; backflow and grease interceptor sign-offs attachValuation or per-fixture
Mechanical / HVACRooftop units, ductwork, exhaust, and refrigerationTrade review; energy compliance documented against the 2015 IECCValuation or per-unit
Fire protectionSprinkler, standpipe, alarm, hood, and suppression systemsFire review under the state Safety Fire Commissioner's adopted codesValuation or per-device
SignWall, monument, and illuminated signageZoning review plus electrical where illuminatedFlat or per-sign
Land disturbanceSite clearing, grading, and stormwater installationErosion and sedimentation review as a Local Issuing AuthorityPer-acre or valuation-based
Development permitA project that went before a board, commission, or councilMay be required even where administrative approval was obtainedSet by the city
Outside agency reviewProjects touching county, state, or environmental jurisdictionDeKalb County, Georgia DOT, the conservation commission, or EPDSet by that agency

Residential

  • Single-discipline review in most cases
  • Trade records filed separately under Chapter 14 licences regardless of job value
  • State licence required once the work exceeds the statutory threshold, per project
  • A private professional provider may be engaged to shorten the review path

Commercial — multi-discipline

  • Concurrent review across building, trades, fire, and zoning
  • Signed and sealed plans across every affected discipline
  • Land-disturbance review runs on its own statutory clock under Title 12
  • Accessibility and life-safety review attach to any change of occupancy

Records you will actually see in Dunwoody

Dunwoody record catalog
RecordWhat it covers
Building permitAll construction activities within the city
Development permitOften required where the project went before a board, commission, or council
Trade permitsPlumbing, electrical, low voltage, heating and air conditioning, and utility work
Land disturbance permitSite work, subject to buffer and stormwater regulations
Contractor AccountRequired before you can apply through the portal
Authorized Permit Agent formWhere you are submitting licences on behalf of another individual
Prescriptive deck detailState deck details, a copy of which must be on the job site
Certificate of Completion or OccupancyAlways issued at final, depending on the scope of work

Solar permits in Dunwoody

Solar is filed as its own record across Georgia rather than as a line item on a building permit, and it is reviewed on two tracks at once: the electrical side (conductors, overcurrent protection, rapid shutdown, labelling, and the service or supply-side connection, all against the 2023 National Electrical Code with the 2026 Georgia Amendments) and the structural side (attachment detail, rail spacing, and whether the existing framing carries the added dead load).

Solar in Dunwoody is filed in CentralSquare under a Contractor Account, and the same inspection rules apply: no photographs in place of a visit, and an inspector whose arrival time cannot be fixed because staff work as combination inspectors across trades.

The covenant question comes up on nearly every residential array, and Georgia answers it less generously than several neighbouring states. Georgia's Solar Power Free-Market Financing Act (O.C.G.A. § 44-3-113 and Title 46, Chapter 3, Article 8) makes third-party solar financing lawful and limits a property owners' association's ability to prohibit solar outright, but Georgia gives homeowners materially less protection than North Carolina or Florida do: an association retains real authority over placement and appearance, and a covenant restricting where panels may sit on the roof will usually stand. Read the covenants before designing the array, not after.

Utility interconnection runs on its own clock alongside the permit. Georgia Power and the state's electric membership corporations each set their own application, meter, and witness-test sequence, and permission to operate is not something the building department controls — plan for the two tracks to finish at different times.

Roofing permits in Dunwoody

A roof covering replacement needs a permit across most of Georgia. The permit is usually quick, but it is not optional, and the inspection that matters happens before the covering goes on rather than after.

Because Georgia enforces a statewide minimum code, there is no state product-approval database to search and no approval number to cite on the application. The assembly has to comply with the adopted code and the manufacturer's listed installation instructions, and that pairing is what the inspector checks — which makes the manufacturer's instructions a document worth having on site.

Reroofs inside Dunwoody are city permits, valued by the city rather than from your contract — the valuation comes from floor area and a pre-determined cost per square foot for the construction type, so quoting a client from the contract price can mislead them.

Sequencing is where reroofs go wrong. The deck and dry-in condition has to be visible when the inspector arrives, so covering it first means opening it back up. Where a previous layer has been torn off, expect attention to deck fastening and to any sheathing replaced along the eaves.

Record types, document sets, and fee structures are set by local ordinance and change without notice. Confirm the current catalog against the official portal before you file.

Dunwoody permit cost

Dunwoody bases permit fees on construction valuation, and the city calculates that valuation from the floor area of the project and a pre-determined cost per square foot based on the type of construction. Fee estimation examples and the fee schedule are published, and the department will discuss fees for a specific project by phone.

Payment methods are limited in a way worth checking before you rely on them. The city accepts card payments online, and accepts cheque, cash, or card in person — but has historically not accepted payment by phone or by credit card authorisation form. Confirm the current position before assuming a remote payment route.

Outside agencies are the schedule cost. Many projects require review and approval by DeKalb County among others, which the city notes may add to the overall process time. That is time the building department does not control and cannot compress.

How Dunwoody fees are structured
Fee componentHow it works
Building permitBased on construction valuation calculated by the city
Valuation basisFloor area times a pre-determined cost per square foot by construction type
PaymentCard online, or cheque, cash, or card in person
Plan reviewRequired for most major projects, including decks and retaining walls
Outside agenciesDeKalb County, DOT, and state agencies charge and schedule separately
Fee estimationPublished examples and a fee schedule, plus advice by phone
🧮

Want a precise number for a specific Dunwoody project? Send us the scope and we will price the permit path before you file.

Dunwoody trade permits

Dunwoody cites the trade licensing statute directly on its own FAQ, and its first-time submission requirements are more specific than most cities in the metro.

First-time submissions carry three documents

Upload the general contractor's licence, the business licence, and a government-issued photo ID of the contractor when submitting to Dunwoody for the first time.

Agent form for third-party submissions

If you are submitting licences on behalf of another individual, you also need a completed Authorized Permit Agent Form.

Trade licensing is quoted directly

The city cites Georgia law requiring all persons contracting or performing for hire any plumbing, electrical, low voltage, heating and air conditioning, or utility work to be duly and currently licensed by the state licensing board for that work.

Inspectors work as combination inspectors

Inspection staff are limited and work across trades, and the time an inspector spends on a job site is unpredictable — which is why set inspection times cannot be scheduled.

🧢 Georgia's contractor licensing threshold is $2,500, which is far lower than most states and catches work people assume is too small to regulate. Under O.C.G.A. § 43-41-2 a state licence is required once the value of the work — or the contractor's compensation, whichever is higher — exceeds that figure, and the test is per project, not per invoice. The State Licensing Board for Residential and General Contractors sits under the Secretary of State and issues four tiers: Residential-Basic (detached one- and two-family homes and townhouses up to three stories); Residential-Light Commercial (adding multifamily and light commercial under four stories and under 25,000 square feet); General Contractor (all building types, no dollar cap); and General Contractor Limited Tier (the same scope capped at $1,000,000 per contract). The consequence of getting this wrong is not just a fine. Under O.C.G.A. § 43-41-17 a contract for work requiring a licence, entered into with a contractor who does not hold one, is unenforceable in law or in equity by that contractor — who also cannot file a mechanic's lien and cannot make a bond claim. An unlicensed contractor on a Georgia job has no collection mechanism at all. The trades are licensed separately under O.C.G.A. Title 43, Chapter 14 through the divisions of the Construction Industry Licensing Board, and those licences are required regardless of project value — the $2,500 floor does not apply to them. Electrical runs Class I (restricted to low-voltage and single-phase installations not exceeding 200 amperes) and Class II (unrestricted). Conditioned air runs Class I (not exceeding 175,000 BTU heating and 60,000 BTU cooling) and Class II (unrestricted). Plumbing runs Journeyman, Master Class I (one- and two-family dwellings and commercial structures not exceeding 10,000 square feet), and Master Class II (unrestricted). One Georgia rule ties the permit directly to the lien statute: under O.C.G.A. § 44-14-361.3 a lien claimant may rely on the building permit issued on the property for the name of the contractor. The permit is not merely a construction approval in Georgia — it is a public record that the lien system reads. Whoever is named on it is who downstream claimants will name, which makes an inaccurate contractor field on a permit application a legal problem rather than a clerical one.

Dunwoody permit application: how to apply step by step

Here is how to get a building permit in Dunwoody, from confirming the requirement through to close-out. Each step below corresponds to a real decision point where projects commonly stall.

1. Confirm you are inside Dunwoody

Dunwoody incorporated in 2008 and permits its own work. Sandy Springs, Brookhaven, Chamblee, Doraville, and unincorporated DeKalb all border it and permit separately.

2. Set up a Contractor Account in CentralSquare

You must have a Contractor Account to apply through the portal. Note that the city moved to CentralSquare on August 4, 2025 — if you hold an application or complaint from before then, check with staff that it transferred.

3. Assemble the first-time documents

On a first submission to Dunwoody, upload the general contractor's licence, business licence, and a government-issued photo ID of the contractor. If you are submitting licences on someone else's behalf, add the Authorized Permit Agent Form.

4. Get the checklists from the Permit Desk

The Permit Desk supplies construction specifications, the plan review checklist, details, buffer regulations, and stormwater regulations. Most major projects need plan review — new construction, additions, deck replacement, land disturbance, retaining walls, swimming pools, permanent signs, and fire sprinklers.

5. Submit, then email to say you have

Upload a digital copy of the plans with the application, then email the permits address to alert Community Development staff. Check whether DeKalb County, Georgia DOT, or state agencies also need to review, as that adds to the overall time.

6. Sequence the inspections properly

Photographs are never accepted in place of an inspection, and insulation cannot be installed before the rough-in because it obstructs the view. Once the job passes final, the city always issues either a Certificate of Completion or a Certificate of Occupancy depending on scope.

Inspections in Dunwoody

Dunwoody's inspection staff work as combination inspectors, covering several trades rather than one each. Because the length of time an inspector spends on a job site is unpredictable, the city does not schedule set times — a constraint worth explaining to a client expecting an appointment.

Two rules are absolute. Pictures are not accepted in lieu of inspections, so a photographed rough-in is not an inspected rough-in. And insulation cannot be installed for the rough-in inspection because it is a visual obstruction; the insulation inspection follows the rough-in rather than accompanying it.

At the end, the city always issues either a Certificate of Completion or a Certificate of Occupancy, depending on the scope of work, when the job has passed final inspection. The city's own guidance to homeowners is that it may be in their interest to require the contractor to produce the appropriate document before final payment — worth knowing on both sides of that conversation.

Where a prescriptive deck detail is used, a copy must be on the job site and available to the inspector during each required inspection. a Georgia building permit generally becomes invalid if work does not begin within 180 days of issuance, or if work is suspended or abandoned for 180 days after commencing, under the administrative provisions of the adopted International Building and Residential Codes — local ordinance may set a different period, and extensions are usually available in writing on request.

Dunwoody permit search and official resources

Dunwoody publishes its permitting guidance, FAQs, and portal instructions through Community Development, alongside its fee schedule and estimation examples.

Frequently asked questions

Who issues building permits in Dunwoody, GA?

The City of Dunwoody Community Development Department. All construction activities in the city require a permit through that department, which administers and enforces the Georgia State Minimum Standard Codes locally.

What portal does Dunwoody use?

CentralSquare. On August 4, 2025 Dunwoody's Community Development operations moved to CentralSquare, replacing the old system, iWorQ. If you had an existing application or complaint, contact staff to make sure the information transferred correctly.

Do I need an account to apply?

Yes. To apply for a permit through the online portal you must have a Contractor Account, and the city publishes instructions for setting one up.

Do I need to do anything after uploading my application?

Yes — email the city's permits address to alert Community Development staff that you have uploaded your application and plans. It is a small step and it prevents a submission sitting unnoticed.

Can I send photos instead of having an inspection?

No. Pictures are not accepted in lieu of inspections in the City of Dunwoody.

Can insulation be in place for the rough-in inspection?

No. Insulation cannot be installed for the rough-in inspection because it is considered a visual obstruction. The insulation inspection is conducted after the rough-in.

Why can I not get a set inspection time?

The inspection staff is limited and works as combination inspectors, and the length of time an inspector might be on a job site is unpredictable — which makes scheduling set times impractical.

How does Dunwoody calculate permit fees?

Fees are based on construction valuation, and the city calculates that valuation from the floor area of the project and a pre-determined cost per square foot based on the type of construction. Fee schedules and estimation examples are published.

What documents do I need on a first submission?

Upload the general contractor's licence, business licence, and a government-issued photo ID of the contractor if submitting to Dunwoody for the first time. If you are submitting licences on behalf of another individual, add a completed Authorized Permit Agent Form.

Are other agencies involved in a Dunwoody permit?

They can be. Additional permits may be required from DeKalb County, the Georgia Department of Transportation, the Georgia Soil and Water Conservation Commission, the Environmental Protection Division, or the Dunwoody Public Works Department, which can add to the overall process time.

What certificate do I get at the end?

The city always issues either a Certificate of Completion or a Certificate of Occupancy, depending on the scope of work, once the job has passed final inspection.

Is Dunwoody aware of permit payment scams?

Yes — the city has published a warning about fraudulent emails targeting residents and businesses with planning-related applications, in which scammers pose as City staff, send fake invoices, and request payment by electronic wire transfer. The city never uses wire transfers for these matters.

Simplify Dunwoody permitting with Alliance Permitting

Dunwoody changed systems in 2025, calculates your valuation for you, will not accept a photograph in place of an inspection, and has had to warn its own residents about invoice fraud. It is a small department with clear rules and several places to trip: the wrong portal, a missing alert email, insulation in too early, or an invoice that never came from the city. A permit expediter for Dunwoody watches all four.

250K+Permits approved
All 50States covered
21 YearsJurisdictional depth
Done-for-youWe file, you build

Trusted by leading builders, developers, and national contractors — 21 years of filing in the jurisdictions we write about.

Contractors and builders choose Alliance for Dunwoody because the work is done by people who have stood at the counter:

  • Right system, right account — CentralSquare with a proper Contractor Account, and the alert email sent after upload.
  • Inspection sequence protected — rough-in before insulation, and no reliance on photographs to close a stage.
  • Complete oversight — every Dunwoody permit, outside-agency approval, and inspection tracked across your jobs in one place.

Alliance Permitting is a permit documentation and expediting service. We are not a law firm and do not provide legal advice, and we are not the permitting authority.

Ready to break ground in Dunwoody sooner?

Let Alliance prepare, file, and track your Dunwoody permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Dunwoody permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.