The City of Decatur issues building permits for property inside city limits through its Design, Environment and Construction division. Applications are filed online through CommunityCore.
What requires a permit in Decatur?
Decatur requires a building permit for constructing, enlarging, altering, repairing, moving, demolishing or changing the occupancy of a structure. The City also specifically requires a permit for repairs and maintenance valued at $1,000 or more.
Any roofing or structural work triggers a permit regardless of that $1,000 repair/maintenance threshold. Separate trade permits are required for drainage, sewer, gas, mechanical, electrical and plumbing work regardless of value.
Projects that affect zoning, disturb land, occur in a Local Historic District, or affect a sidewalk, street or other right-of-way require the related City review in addition to the construction permit path.
Who issues building permits in Decatur?
Depending on the project, review can involve permit technicians, plan reviewers, the City Planner, the City Arborist, Building, Engineering and the Fire Marshal.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Authority | City of Decatur Design, Environment & Construction |
| Phone | 404-377-6198 |
| Office | Leveritt Public Works Building, first floor, 2635 Talley Street, Decatur, GA 30030 |
| Hours | Monday–Friday, 9 a.m.–4 p.m. (closed 12–1 p.m.) |
| Portal access | Email permits@decaturga.com for CommunityCore access |
| Primary filing | CommunityCore |
Permit fees in Decatur
Decatur’s FY 2025-26 consolidated fee schedule lists a $25 e-permitting/digital plan review fee per item and a $60 minimum building permit. For permits exceeding $1,000 of value or involving roofing or structural work, the published formula is $60 for the first $1,000 of value plus $7 for each additional thousand or fraction thereof, whichever is greater.
The same schedule lists minimum trade permit amounts of $90 for electrical and $60 each for HVAC and plumbing, plus separate certificate, plan-review, reinspection and other development charges.
Not sure this scope needs a permit?
Get a free quote →Electrical, plumbing, mechanical and gas work
A building permit does not cover regulated trade work in Decatur. Electrical, plumbing, mechanical/HVAC and gas work each need their own permit record.
How to apply: 6-step Decatur process
Property inside city limits is permitted by the City, not DeKalb County.
List the building, trade, site, planning, fire, utility or specialty approvals the scope needs.
Assemble plans, contractor documents and required affidavits for the City application.
File through CommunityCore and pay the fees generated for the permit record.
Upload corrected documents through CommunityCore.
Request the required inspections, pass finals and obtain the applicable certificate or completion record.
Rather talk it over?
Call 1-855-478-4290 →Decatur inspections
Certificates of occupancy/completion require paid fees, passed inspections, as-built approval where applicable, HPBS compliance and no unresolved holds, stop-work orders or citations.
Do not cover regulated work before the required inspection is complete.
Local Decatur details that matter
1. CommunityCore is mandatory; the City says it no longer accepts paper or emailed permit applications.
2. Tree impacts can trigger a mandatory arborist pre-application meeting before permit filing.
Georgia building code
Georgia's State Minimum Standard Codes apply statewide: the 2024 International Building, Residential, Plumbing, Mechanical, Fuel Gas, and Swimming Pool and Spa Codes and the 2023 National Electrical Code, with Georgia Amendments, in force since 1 January 2026; the energy code is still the 2015 IECC with Georgia supplements. The Georgia State Minimum Standard Codes
Rather not deal with the building department?
Get a free quote →Official Decatur permitting resources
These are the primary sources behind this guide. Codes, fee schedules and procedures change — confirm the position for your filing date.
- Georgia DCA current codes
- FY 25-26 fee schedule
- Applications, forms & fees
- Permit requirements
- How to obtain a permit
- Georgia DCA enforcement
Decatur permit FAQs
Can I email a permit application to Decatur?
No. Decatur states that applications must be submitted through CommunityCore.
Want this handled start to finish?
Get a free quote →What is Decatur’s repair-value trigger?
The City requires a permit for repairs and maintenance valued at $1,000 or more, while roofing and structural work require permits regardless of that threshold.
Are trade permits separate?
Yes. Decatur requires separate trade permits for regulated drainage, sewer, gas, mechanical, electrical and plumbing work regardless of value.
What happens when protected trees are affected?
For specified permit types that remove trees or disturb protected root zones, the City requires a pre-application meeting with the City Arborist before filing.
How is a CO or completion certificate requested?
Request it from the permitting office once fees are paid, inspections are passed and no holds, stop-work orders or citations remain.
Simplify Decatur permitting with Alliance Permitting
Inspections are where schedules slip.
Get a free quote →Alliance Permitting is a permit documentation and submission company in Georgia. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Decatur sooner?
Let Alliance prepare, file, and track your Decatur permits while your crew stays on the job.
More Georgia permitting guides
This guide is provided by Alliance Permitting for general information about Decatur permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.