Municipal GuideFloridaCity of Pompano Beach · Broward County

City of Pompano Beach Building & Trade Permit Guide

How to get a building permit in Pompano Beach, FL — one-permit concept, Click2Gov + ePlan review, scanning fees on paper, inspections. 2026 guide.

Jurisdiction: City of Pompano Beach Building DepartmentCode: Florida Building Code, 8th Ed. (2023)Portal: Click2Gov + ePlan (electronic plan review)
Authority
Pompano Beach Building Dept.
City Hall 3rd Floor, 100 W. Atlantic
Apply
Click2Gov → ePlan
One-permit concept for all trades
Paper filing
Scanned at the counter
Scanning fees apply
New leadership
Jay Olsen, Acting Building Official
Announced June 18, 2026

The City of Pompano Beach — coastal Broward's fast-redeveloping city between Fort Lauderdale and Deerfield Beach — issues building permits through the Building Department on the 3rd floor of City Hall at 100 W. Atlantic Boulevard. The city's signature is its "one permit" concept: a single permit encompasses the trade applications — plumbing, electrical, roofing, site drainage, and more — under one master permit, with each trade contractor submitting required information and appearing on the master application, and the integrated electronic system carrying projects through Temporary, Partial, or Final Certificates of Occupancy.

Intake starts in Click2Gov, where creating an application number requires no account registration — and once the number is generated, an ePlan account is established automatically for document upload, with all review conducted electronically. Paper is still accepted at the 3rd-floor counter, but documents are scanned into the electronic system and scanning fees apply. The department is also in a leadership transition: on June 18, 2026 the city honored longtime Building Official Mike Rada's service and announced Jay Olsen as Acting Building Official.

Applies inside City of Pompano Beach limits. Neighboring Deerfield Beach, Lighthouse Point, and Fort Lauderdale run their own permitting, and unincorporated Broward parcels route to the county - confirm the jurisdiction before filing.

📍 The application form and rules have been moving — use current everything. Pompano adopted the new Broward County Uniform Building Permit Application in November 2025 and updated it again in February 2026 to add a Private Provider section; contractor licensing changes took effect in August 2025, and private providers now use a one-time registration adopted in September 2025. Projects triggering Broward County review coordinate through ePermitsOneStop — submitting county-required plan sets from the city ePlan project into the county's system — and county approvals must land before city issuance where applicable.

What requires a building permit in City of Pompano Beach?

Under the Florida Building Code (§105.1), a permit is required before you construct, enlarge, alter, repair, move, demolish, or change the occupancy of most structures and systems. New for 2026: Florida HB 803 (effective July 1, 2026) created additional building-permit exemptions for certain single-family residential work - notably F.S. 553.79(1)(g), which can exempt qualifying work valued under $7,500 when it involves no electrical, plumbing, mechanical, gas, or structural work, the home is not in a Special Flood Hazard Area, and the owner submits a written exemption request to the Building Official. Ask the permit counter whether your scope qualifies before assuming a permit is needed.

Permit required

  • New homes, additions, and tenant build-outs
  • Structural / load-bearing alterations and demolition
  • Reroofing, window and door replacement, and exterior work
  • Electrical service changes and most wiring alterations
  • Mechanical / HVAC changeouts and boilers
  • Plumbing alterations, repipes, gas, and water heaters
  • Pools and spas (barrier required), signs, and fences
  • Manufactured homes and solar PV systems

Usually exempt

  • Painting, flooring, cabinetry, and cosmetic work
  • Like-for-like minor repairs not altering systems
  • Certain low non-structural fences (confirm limits)
  • Routine maintenance not extending or rerouting systems
Exemptions are narrow and local. Always verify with the permit counter before starting work - unpermitted work risks stop-work orders, doubled fees, and closing/insurance problems.

Who handles permitting in City of Pompano Beach?

The Building Department operates from the 3rd floor of Pompano Beach City Hall at 100 W. Atlantic Boulevard — (954) 786-4600 — with a posted support hotline, contractor registration lane, lien search request process, and a permit fee estimator among its published tools. All plan review runs electronically through ePlan across the reviewing disciplines — Building, Zoning, Fire, and Engineering (954-786-4060) — and the city publishes submittal checklists by permit type, from A/C changeouts and additions through building shells, cell towers, chickee huts, and changes of contractor or use. All permitting runs through the Click2Gov + ePlan (electronic plan review).

  • Address: City Hall, 3rd Floor, 100 W. Atlantic Blvd., Pompano Beach, FL 33060
  • Phone: (954) 786-4600
  • Email: building@copbfl.com
  • Hours: Monday–Friday (city business hours)

City of Pompano Beach permit types

A building permit is one record among many. the Pompano Beach Building Department issues work under separate record types, and filing under the wrong one is a rejection, not a correction — the application is closed and refiled, and the review clock restarts.

Residential permit types

Residential permit types in City of Pompano Beach
Permit typeWhat triggers itReview pathFee basis
New constructionNew dwellings, additions, and accessory structures over the exempt thresholdFull plan review (structural, energy, zoning)Valuation-based
Renovation / alterationStructural or load-bearing changes, layout changes, substantial repairPlan review scaled to scopeValuation-based
ReroofRoof covering replacement and most major roof repairProduct approval review; dry-in and nail-off inspectionsValuation or squares
Solar photovoltaicRooftop or ground-mount PV installation or replacementStructural plus electrical reviewFlat or system-size based
Solar thermalPassive water heating or pool heating systemsPlumbing and structural reviewFlat or per-permit minimum
ElectricalService changes, panel upgrades, new circuits, most wiring alterationsTrade review; filed against the building permitPer-permit minimum or per-device
PlumbingNew piping, repipes, water heaters, fixtures, gas pipingTrade review; filed against the building permitPer-permit minimum or per-fixture
Mechanical / HVACChangeouts that are not like-for-like, ductwork, refrigerationTrade review; filed against the building permitPer-permit minimum or per-unit
Windows and doorsReplacement units and opening protectionProduct approval review for wind-borne debrisValuation or per-opening
Pool and spaIn-ground and above-ground pools, spas, barrier and enclosure workPlan review plus barrier and electrical bondingValuation-based
Fence and accessoryFences, sheds, decks, and carports over the exempt thresholdZoning plus structural where applicableFlat or valuation-based
DemolitionFull or partial demolition of a structureUtility disconnect verification requiredFlat

Commercial permit types

Commercial permit types in City of Pompano Beach
Permit typeWhat triggers itReview pathFee basis
New constructionGround-up commercial, industrial, and multifamilyFull multi-discipline plan reviewValuation-based
Tenant improvementInterior build-outs and suite fit-upsPlan review across affected disciplinesValuation-based
Renovation / alterationStructural, envelope, or system changes to an existing buildingPlan review scaled to scopeValuation-based
Change of useConverting a building from one occupancy classification to anotherZoning, life-safety, and accessibility reviewValuation or flat
ReroofCommercial roof covering replacementProduct approval review plus fire review where applicableValuation or squares
Solar photovoltaicCommercial rooftop, carport, and ground-mount PVStructural, electrical, and often fire reviewValuation or system-size based
ElectricalService, distribution, and branch circuit workTrade reviewValuation or per-device
PlumbingSupply, waste, vent, and gas systemsTrade reviewValuation or per-fixture
Mechanical / HVACRooftop units, ductwork, exhaust, and refrigerationTrade reviewValuation or per-unit
Fire protectionSprinkler, standpipe, alarm, and suppression systemsFire prevention plan reviewValuation or per-device
SignWall, monument, and illuminated signageZoning plus electrical where illuminatedFlat or per-sign
DemolitionFull or partial commercial demolitionUtility disconnect and environmental clearanceFlat or valuation-based

Residential

  • Single-discipline review in most cases
  • Master permit with trades filed against it
  • Owner-builder route exists but carries statutory affidavits
  • Product approval drives roofing and opening protection

Commercial — multi-discipline

  • Concurrent review across building, fire, and zoning
  • Signed and sealed plans across every affected discipline
  • Accessibility and life-safety review attach to change of use
  • Impact and concurrency fees can apply on top of permit fees

Solar permits in City of Pompano Beach

Solar is permitted as its own record type in most Florida jurisdictions rather than rolled into a general building permit, and residential and commercial photovoltaic are usually separate records with different document sets. Solar thermal — passive water and pool heating — is a third, distinct record.

A photovoltaic submittal is reviewed on two tracks at once: structural (roof load path, attachment spacing, uplift) and electrical (conductor sizing, rapid shutdown, point of interconnection). A single-line diagram and a signed and sealed structural attachment detail are the two attachments most often missing on a first submittal.

Under Fla. Stat. §163.04, a homeowners' association cannot prohibit a solar collector on a dwelling — HOA architectural approval is not a prerequisite to permit issuance, though it may still be a contractual matter between owner and association.

Utility interconnection runs parallel to the building permit, not inside it. Permission to Operate is issued by the utility after the final electrical inspection clears.

🌪

High-Velocity Hurricane Zone. City of Pompano Beach sits in Broward County, inside the High-Velocity Hurricane Zone. HVHZ work requires products carrying a Miami-Dade Notice of Acceptance or a Florida Product Approval valid for the HVHZ, uses stricter attachment and uplift criteria, and carries review requirements above the statewide baseline — on both solar and roofing.

Roofing permits in City of Pompano Beach

A roof covering replacement requires a permit in every Florida jurisdiction. Repairs below the local threshold may not, but the threshold is scope-specific and confirming it with the building department before tear-off is cheaper than an after-the-fact permit.

Every roof product must carry a current Florida Product Approval or Miami-Dade Notice of Acceptance rated for the wind speed at the project address. A product approval number that has lapsed or is rated below the site wind speed is the single most common reroof rejection.

Reroof inspections are sequenced: dry-in after the underlayment, nail-off on the sheathing fastening, and final. Covering the deck before the dry-in inspection means tearing it back open.

Hurricane mitigation retrofit requirements can attach when an existing roof is replaced, including secondary water barrier and roof-to-wall connection work. These add scope and documents, and they are triggered by the replacement itself.

Under Fla. Stat. §553.7922, jurisdictions run expedited procedures for permits that need no technical review — reroofs, roof repairs, and similar — during a declared state of emergency.

Record types, document sets, and fee structures are set by the Pompano Beach Building Department and change without notice. Confirm the current record type against the building department before filing.

City of Pompano Beach building permit cost

Permit fees are assessed per the Building Department's posted fee schedule, with the online permit fee estimator pricing scopes before you file — and paper submittals carrying scanning fees on top, since every document enters the electronic system. The one-permit concept concentrates the paperwork: every trade contractor and sub-contractor signs onto the master application, so assembling signatures before submission is part of the real cost of a clean filing.

How City of Pompano Beach permitting works

ComponentHow it works
Permit feesPer the Building Department fee schedule — online fee estimator available
Paper submittalsScanned into the electronic system — scanning fees apply
One-permit conceptTrades ride a single master permit; all contractors sign the master application
Application formBroward Uniform application (Nov 2025), updated Feb 17, 2026 with Private Provider section
Private providersOne-time registration process (since Sept 9, 2025)
County coordinationePermitsOneStop — county plan sets submitted from the city ePlan project
System structure, form dates, and program changes per the City of Pompano Beach Building Department's posted announcements — confirm current fee amounts with the fee estimator or fee schedule before budgeting

City of Pompano Beach trade permits

Under the one-permit concept, plumbing, electrical, mechanical, roofing, and site-drainage applications ride the master building permit — each trade contractor submitting required information and signing on — with the city's submittal checklists mapping documentation by scope. Broward's High-Velocity Hurricane Zone governs exterior components, the Building Safety Inspection Program covers aging structures per county policy, and asbestos certificates and Broward environmental approvals route through the posted county-coordination lanes where scopes trigger them.

Electrical permits

Required for service installations, panel upgrades, solar PV, and most wiring alterations in City of Pompano Beach, filed by a licensed electrical contractor against the master building permit through the City of Pompano Beach Building Department.

Plumbing permits

Required for new plumbing, repipes, water heater changeouts, fixture relocations, and gas piping; fees follow the local schedule with per-permit minimums.

Mechanical (HVAC) permits

Required for HVAC installations and changeouts, ductwork, and refrigeration; specialized systems are permitted and inspected separately.

Miscellaneous & specialty

Roofs, pools and spas, screen enclosures, mobile home set-ups, and demolition are permitted separately. Exterior components need current Florida Product Approval rated for the local wind speed.

How to get a building permit in City of Pompano Beach

Confirm jurisdiction and pull the checklist

Verify the parcel is inside Pompano Beach city limits, then download the submittal checklist for your permit type — the city publishes one for virtually every scope, from A/C changeouts to building shells.

Create the application number in Click2Gov

No account registration needed to start — generate the application number, which becomes your tracking reference, and the system establishes your ePlan account from the information provided.

Assemble signatures and documents

Signed application forms from all contractors and sub-contractors on the master permit, signed and sealed drawings where required, and HVHZ product approvals — all in PDF for electronic upload (paper scans at the counter with scanning fees).

Upload to ePlan and work the review

All disciplines — Building, Zoning, Fire, Engineering — review electronically; respond to correction notices promptly, and push county-required plan sets to ePermitsOneStop where Broward review applies.

Pay and pull the permit

Pay final fees when notified the permit is ready, record the Notice of Commencement, and post the permit on site.

Inspect through certificate

Schedule and track inspections through the online system, clearing phases through Temporary, Partial, or Final Certificate of Occupancy as the project structure requires.

Inspections in City of Pompano Beach

Inspection scheduling and tracking run through the city's online system against the master permit, with the one-permit structure keeping every trade's inspections under a single record through Temporary, Partial, or Final CO. The department's posted contact lanes — support hotline, engineering division, fire department — cover discipline-specific questions, and HVHZ product documentation should be ready at every exterior-component inspection in this beachfront jurisdiction.

Official City of Pompano Beach permitting resources

Frequently asked questions

How long does it take to get a building permit in City of Pompano Beach?

Electronic review across Building, Zoning, Fire, and Engineering moves at the pace of your correction responses — the city's own guidance is that timely, accurate resubmittals are the key to speed — and county-triggering projects add the ePermitsOneStop coordination loop. The fee estimator and submittal checklists front-load the budgeting and documentation. Call (954) 786-4600 for current turnaround by permit type.

How do I look up a permit in City of Pompano Beach?

Pompano Beach permit records run through the Click2Gov system — search by application or permit number (two-digit year in the first box, remaining digits in the second, no 'BP' or dashes) or by parcel — with ePlan tracking carrying review status. The city also posts a permit fee estimator and a lien search request lane for closing-related research.

What is Pompano Beach's one-permit concept?

A single master permit encompasses the trade applications — plumbing, electrical, roofing, site drainage, and more — instead of separate stand-alone permits per trade. Each trade contractor still submits required information and signs onto the master application, and the electronic system carries the whole project through Temporary, Partial, or Final Certificate of Occupancy.

Do I need an account to start a Pompano Beach permit?

No — create the application number in Click2Gov without registering, and once the number is generated, an ePlan account is established automatically from the information you provided. The application number becomes the tracking reference for all correspondence.

Does Pompano Beach still accept paper applications?

Yes, at the Building Department counter on the 3rd floor of City Hall — but paper documents are scanned into the electronic review system and scanning fees apply, and all actual review is electronic through ePlan. Uploading PDFs directly avoids the scanning charge.

Who is the Pompano Beach Building Official?

Jay Olsen is Acting Building Official, announced June 18, 2026, as the city honored longtime Building Official Mike Rada's service. The department has been modernizing steadily — new Broward Uniform application (Nov 2025, updated Feb 2026), private provider one-time registration (Sept 2025), and contractor licensing changes (Aug 2025).

Do I need a permit to install solar panels in City of Pompano Beach?

Yes. Photovoltaic installations in City of Pompano Beach are permitted under a dedicated solar record type reviewed on both a structural and an electrical track. Solar thermal — passive water and pool heating — is a separate record. Under Fla. Stat. §163.04 a homeowners' association cannot prohibit a solar collector, so HOA approval is not a prerequisite to permit issuance. Utility interconnection and Permission to Operate run in parallel with the permit, not inside it.

Does a roof replacement require a permit in City of Pompano Beach?

Yes, and City of Pompano Beach is in the High-Velocity Hurricane Zone, so the bar is higher than the rest of Florida. Roof products must carry a Miami-Dade Notice of Acceptance or a Florida Product Approval valid for the HVHZ, attachment and uplift criteria are stricter, and hurricane mitigation retrofit requirements commonly attach when an existing roof is replaced. Inspections remain sequenced — dry-in, nail-off, then final.

What is the difference between a residential and a commercial permit in City of Pompano Beach?

Residential work is generally a single-discipline review filed as a master permit with trades filed against it. Commercial work in City of Pompano Beach runs concurrent review across building, fire, and zoning, requires signed and sealed plans for every affected discipline, and can carry impact and concurrency fees on top of permit fees. Change of use adds accessibility and life-safety review.

Do trade permits need to be pulled separately in City of Pompano Beach?

Yes in most cases. Electrical, plumbing, and mechanical work is permitted separately by the licensed contractor for each trade and filed against the master building permit. Each trade permit carries its own fee and its own inspection sequence.

What happens if I file under the wrong permit type in City of Pompano Beach?

The application is rejected rather than corrected. the Pompano Beach Building Department closes the record, the filing is resubmitted under the correct record type, and the review clock restarts from zero. Confirming the record type before filing is the cheapest step in the entire process.

Can I apply for all Pompano Beach permit types online?

Most record types are filed through the city permitting system, but availability varies by permit type and by applicant. Some records still require in-person submittal, and owner-builder filings are frequently restricted to counter submittal regardless of record type.

Simplify City of Pompano Beach permitting with Alliance Permitting

A one-permit structure, no-registration intake, scanning fees that punish paper, and a 2025–2026 run of form and program changes — Pompano Beach rewards teams running current documents through clean electronic filings. Alliance Permitting is a permit expediter for City of Pompano Beach and keeps the checklists, signatures, and county coordination sequenced so your beachfront project reaches CO without a stall.

250K+Permits approved
All 50States covered
AI + HumanExpert filing
Done-for-youWe file, you build

Trusted by leading builders and brands - including Dream Finders Homes, Tesla, Verizon, Hyatt, and Sunnova.

Contractors and builders choose Alliance for City of Pompano Beach because we deliver:

  • Local expertise - we know the City of Pompano Beach Building Department and the Click2Gov + ePlan (electronic plan review) process.
  • Complete oversight - track every permit and inspection across all your jobs in one place.
  • Error-free submissions - AI pre-checks plus expert review catch issues before they become correction cycles.

Alliance Permitting is a permit documentation and submission company: we prepare your paperwork, file it correctly, and coordinate with the building department through issuance - including preparing private-provider documentation where that option is available. We are not a contractor and do not perform licensed plan review or inspections; that work stays with your team and the jurisdiction.

Ready to break ground in City of Pompano Beach sooner?

Let Alliance prepare, file, and track your City of Pompano Beach permits while you stay focused on building. Get a free, no-obligation quote today.

This guide is provided by Alliance Permitting for general informational purposes and reflects publicly available information believed accurate as of July 2026. Permit requirements, fees, and processes change; always confirm current details with the City of Pompano Beach Building Department before filing. This is not legal advice.