Municipal GuideFloridaCity of Hollywood · Broward County

City of Hollywood Building & Trade Permit Guide

How to get a building permit in Hollywood, FL — Accela portal, Express same-day review, ePermitsOneStop county integration, inspections. 2026 guide.

Jurisdiction: City of Hollywood Building DivisionCode: Florida Building Code, 8th Ed. (2023)Portal: Accela Citizen Access + ePermitsOneStop
Authority
Hollywood Building Division
Development Services Hub, City Hall
Apply
Accela + ePermitsOneStop
City + Broward permits in one flow
Express lane
Same-day review Wednesdays
Submit Tue 6 p.m.–Wed 9 a.m.
Consults
QLess virtual check-in
Mon–Thu, 7:30–9:30 a.m.

The City of Hollywood — Broward's beachfront-to-441 city between Fort Lauderdale and the Miami-Dade line — issues building permits through the Building Division at the Development Services Hub in City Hall, 2600 Hollywood Boulevard. Applications run through the Accela portal, and Hollywood carries an integration few Florida cities offer: through ePermitsOneStop, applicants can apply for and receive approval on both Hollywood building permits and associated Broward County permits in one seamless process — eliminating the trip to Broward's Government Center West in Plantation.

Hollywood also runs a genuine speed lane. The Express Permitting Service offers guaranteed same-day plan review for select residential permit types: submit through the Accela portal in the window from 6 p.m. Tuesday to 9 a.m. Wednesday (up to 10 submittals per applicant), and if approved, pay by 3 p.m. Wednesday for electronic issuance the same day. Counter consultations run through the QLess virtual check-in system, with Permit Representative and Plan Examiner consultation days Monday through Thursday, 7:30 to 9:30 a.m.

Applies inside City of Hollywood limits. Neighboring Hallandale Beach, Dania Beach, Pembroke Pines, and West Park run their own permitting, and unincorporated Broward parcels route to the county - confirm the jurisdiction before filing.

📍 Registration gates everything — including the Express lane. Contractors must be registered with the city and up to date on verified insurance, workers' comp, and license before submitting, with certificates of insurance showing the City of Hollywood as the certificate holder. Registration takes the notarized Contractor's Record Management Form plus the qualifier's driver's license, business tax receipt, and state certification or registration. Historic District applications may be delayed for additional review — including in the Express program.

What requires a building permit in City of Hollywood?

Under the Florida Building Code (§105.1), a permit is required before you construct, enlarge, alter, repair, move, demolish, or change the occupancy of most structures and systems. New for 2026: Florida HB 803 (effective July 1, 2026) created additional building-permit exemptions for certain single-family residential work - notably F.S. 553.79(1)(g), which can exempt qualifying work valued under $7,500 when it involves no electrical, plumbing, mechanical, gas, or structural work, the home is not in a Special Flood Hazard Area, and the owner submits a written exemption request to the Building Official. Ask the permit counter whether your scope qualifies before assuming a permit is needed.

Permit required

  • New homes, additions, and tenant build-outs
  • Structural / load-bearing alterations and demolition
  • Reroofing, window and door replacement, and exterior work
  • Electrical service changes and most wiring alterations
  • Mechanical / HVAC changeouts and boilers
  • Plumbing alterations, repipes, gas, and water heaters
  • Pools and spas (barrier required), signs, and fences
  • Manufactured homes and solar PV systems

Usually exempt

  • Painting, flooring, cabinetry, and cosmetic work
  • Like-for-like minor repairs not altering systems
  • Certain low non-structural fences (confirm limits)
  • Routine maintenance not extending or rerouting systems
Exemptions are narrow and local. Always verify with the permit counter before starting work - unpermitted work risks stop-work orders, doubled fees, and closing/insurance problems.

Who handles permitting in City of Hollywood?

The Building Division operates from the Development Services Hub at City Hall, 2600 Hollywood Boulevard — (954) 921-3335, on the city's Monday–Thursday schedule — with email intake at ePermits@hollywoodfl.org for permit types processed in the BCLA permitting system. Under the Florida Building Code, the division processes permits within a maximum of 30 working days of submission, reviewed in date order — a clock that excludes Planning and Zoning, Engineering, and Fire review time. For Express Permitting questions, the city publishes a direct line: call or text (954) 802-1590, answered Wednesdays 7 a.m.–6 p.m. All permitting runs through the Accela Citizen Access + ePermitsOneStop.

  • Address: Development Services Hub, 2600 Hollywood Blvd., Hollywood, FL 33020
  • Phone: (954) 921-3335
  • Email: ePermits@hollywoodfl.org
  • Hours: Monday–Thursday, 7:00 a.m.–6:00 p.m.

City of Hollywood permit types

A building permit is one record among many. the Hollywood Building Division issues work under separate record types, and filing under the wrong one is a rejection, not a correction — the application is closed and refiled, and the review clock restarts.

Residential permit types

Residential permit types in City of Hollywood
Permit typeWhat triggers itReview pathFee basis
New constructionNew dwellings, additions, and accessory structures over the exempt thresholdFull plan review (structural, energy, zoning)Valuation-based
Renovation / alterationStructural or load-bearing changes, layout changes, substantial repairPlan review scaled to scopeValuation-based
ReroofRoof covering replacement and most major roof repairProduct approval review; dry-in and nail-off inspectionsValuation or squares
Solar photovoltaicRooftop or ground-mount PV installation or replacementStructural plus electrical reviewFlat or system-size based
Solar thermalPassive water heating or pool heating systemsPlumbing and structural reviewFlat or per-permit minimum
ElectricalService changes, panel upgrades, new circuits, most wiring alterationsTrade review; filed against the building permitPer-permit minimum or per-device
PlumbingNew piping, repipes, water heaters, fixtures, gas pipingTrade review; filed against the building permitPer-permit minimum or per-fixture
Mechanical / HVACChangeouts that are not like-for-like, ductwork, refrigerationTrade review; filed against the building permitPer-permit minimum or per-unit
Windows and doorsReplacement units and opening protectionProduct approval review for wind-borne debrisValuation or per-opening
Pool and spaIn-ground and above-ground pools, spas, barrier and enclosure workPlan review plus barrier and electrical bondingValuation-based
Fence and accessoryFences, sheds, decks, and carports over the exempt thresholdZoning plus structural where applicableFlat or valuation-based
DemolitionFull or partial demolition of a structureUtility disconnect verification requiredFlat

Commercial permit types

Commercial permit types in City of Hollywood
Permit typeWhat triggers itReview pathFee basis
New constructionGround-up commercial, industrial, and multifamilyFull multi-discipline plan reviewValuation-based
Tenant improvementInterior build-outs and suite fit-upsPlan review across affected disciplinesValuation-based
Renovation / alterationStructural, envelope, or system changes to an existing buildingPlan review scaled to scopeValuation-based
Change of useConverting a building from one occupancy classification to anotherZoning, life-safety, and accessibility reviewValuation or flat
ReroofCommercial roof covering replacementProduct approval review plus fire review where applicableValuation or squares
Solar photovoltaicCommercial rooftop, carport, and ground-mount PVStructural, electrical, and often fire reviewValuation or system-size based
ElectricalService, distribution, and branch circuit workTrade reviewValuation or per-device
PlumbingSupply, waste, vent, and gas systemsTrade reviewValuation or per-fixture
Mechanical / HVACRooftop units, ductwork, exhaust, and refrigerationTrade reviewValuation or per-unit
Fire protectionSprinkler, standpipe, alarm, and suppression systemsFire prevention plan reviewValuation or per-device
SignWall, monument, and illuminated signageZoning plus electrical where illuminatedFlat or per-sign
DemolitionFull or partial commercial demolitionUtility disconnect and environmental clearanceFlat or valuation-based

Residential

  • Single-discipline review in most cases
  • Master permit with trades filed against it
  • Owner-builder route exists but carries statutory affidavits
  • Product approval drives roofing and opening protection

Commercial — multi-discipline

  • Concurrent review across building, fire, and zoning
  • Signed and sealed plans across every affected discipline
  • Accessibility and life-safety review attach to change of use
  • Impact and concurrency fees can apply on top of permit fees

Solar permits in City of Hollywood

Solar is permitted as its own record type in most Florida jurisdictions rather than rolled into a general building permit, and residential and commercial photovoltaic are usually separate records with different document sets. Solar thermal — passive water and pool heating — is a third, distinct record.

A photovoltaic submittal is reviewed on two tracks at once: structural (roof load path, attachment spacing, uplift) and electrical (conductor sizing, rapid shutdown, point of interconnection). A single-line diagram and a signed and sealed structural attachment detail are the two attachments most often missing on a first submittal.

Under Fla. Stat. §163.04, a homeowners' association cannot prohibit a solar collector on a dwelling — HOA architectural approval is not a prerequisite to permit issuance, though it may still be a contractual matter between owner and association.

Utility interconnection runs parallel to the building permit, not inside it. Permission to Operate is issued by the utility after the final electrical inspection clears.

🌪

High-Velocity Hurricane Zone. City of Hollywood sits in Broward County, inside the High-Velocity Hurricane Zone. HVHZ work requires products carrying a Miami-Dade Notice of Acceptance or a Florida Product Approval valid for the HVHZ, uses stricter attachment and uplift criteria, and carries review requirements above the statewide baseline — on both solar and roofing.

Roofing permits in City of Hollywood

A roof covering replacement requires a permit in every Florida jurisdiction. Repairs below the local threshold may not, but the threshold is scope-specific and confirming it with the building department before tear-off is cheaper than an after-the-fact permit.

Every roof product must carry a current Florida Product Approval or Miami-Dade Notice of Acceptance rated for the wind speed at the project address. A product approval number that has lapsed or is rated below the site wind speed is the single most common reroof rejection.

Reroof inspections are sequenced: dry-in after the underlayment, nail-off on the sheathing fastening, and final. Covering the deck before the dry-in inspection means tearing it back open.

Hurricane mitigation retrofit requirements can attach when an existing roof is replaced, including secondary water barrier and roof-to-wall connection work. These add scope and documents, and they are triggered by the replacement itself.

Under Fla. Stat. §553.7922, jurisdictions run expedited procedures for permits that need no technical review — reroofs, roof repairs, and similar — during a declared state of emergency.

Record types, document sets, and fee structures are set by the Hollywood Building Division and change without notice. Confirm the current record type against the building department before filing.

City of Hollywood building permit cost

Permit fees are assessed per the city's schedule at issuance — confirm current amounts with the Building Division when you file. The structural costs are procedural: contractor registration current before submittal, certificates naming the City of Hollywood as certificate holder, and — for the Express lane — payment received by 3 p.m. Wednesday for same-day electronic issuance. Statutorily expedited projects should flag their entitlement at submission; the city gives such applications first priority.

How City of Hollywood permitting works

ComponentHow it works
Permit feesPer the city schedule at issuance — confirm with the Building Division
Standard review clockMaximum 30 working days per FBC, reviewed in date order (excludes P&Z / Engineering / Fire)
Express PermittingSelect residential types; submit Tue 6 p.m.–Wed 9 a.m.; same-day review; pay by 3 p.m. Wed
Express volume capUp to 10 submittals per applicant per window
Contractor registrationNotarized Record Management Form + license, BTR, driver's license; COI names City of Hollywood
ePermitsOneStopHollywood + associated Broward County permits approved in one process
Program windows and registration requirements per the City of Hollywood Building Division's posted Express Permitting and registration instructions — confirm current fee amounts before budgeting

City of Hollywood trade permits

Trade permits run through the same Accela intake against the master permit, with Broward's High-Velocity Hurricane Zone driving product-approval review on windows, doors, roofing, and shutters. The Express Permitting lane covers select residential permit types — the city posts the eligible list with required checklists, and submissions must include the completed checklist to qualify. Owner-builders may permit work on their own one- or two-family residence, with the standard Florida restriction: no sale within one year of final inspection.

Electrical permits

Required for service installations, panel upgrades, solar PV, and most wiring alterations in City of Hollywood, filed by a licensed electrical contractor against the master building permit through the City of Hollywood Building Division.

Plumbing permits

Required for new plumbing, repipes, water heater changeouts, fixture relocations, and gas piping; fees follow the local schedule with per-permit minimums.

Mechanical (HVAC) permits

Required for HVAC installations and changeouts, ductwork, and refrigeration; specialized systems are permitted and inspected separately.

Miscellaneous & specialty

Roofs, pools and spas, screen enclosures, mobile home set-ups, and demolition are permitted separately. Exterior components need current Florida Product Approval rated for the local wind speed.

How to get a building permit in City of Hollywood

Register with the city first

File the notarized Contractor's Record Management Form with the qualifier's driver's license, business tax receipt, and state certification — with insurance certificates naming the City of Hollywood as certificate holder. Keep it current; Express submittals require verified up-to-date registration.

Pick your lane

Standard applications go through the Accela portal (or ePermits@hollywoodfl.org for BCLA-system permit types). Eligible residential scopes can target the Express window: Tuesday 6 p.m. to Wednesday 9 a.m., up to 10 submittals.

Assemble the package with the checklist

Include the completed permit checklist the city publishes for your permit type, plans, and HVHZ product approvals for exterior components. Historic District parcels may need additional review.

Submit and track in Accela

Upload through the portal; ePermitsOneStop routes associated Broward County approvals in the same process. Standard review runs in date order within the FBC's 30-working-day maximum.

Pay and pull the permit

Standard permits pay at issuance; Express approvals must pay by 3 p.m. Wednesday for same-day electronic issuance. Record the Notice of Commencement where required.

Inspect through close-out

Schedule inspections through the portal, keep the permit and approved plans posted, and clear the final for your Certificate of Occupancy or Completion.

Inspections in City of Hollywood

Inspections are scheduled and tracked through the city's online system against the issued permit. For in-person questions, the QLess virtual check-in covers Mechanical, Electrical, Plumbing, Structural, Zoning, Fire, Engineering, and more — with consultation days Monday through Thursday, 7:30 to 9:30 a.m., and the call-back feature eliminating counter lines. Resubmittals re-enter review in date order, so clean packages protect the schedule.

Official City of Hollywood permitting resources

Frequently asked questions

How long does it take to get a building permit in City of Hollywood?

Two clocks: standard review runs in date order within the FBC's 30-working-day maximum (excluding P&Z, Engineering, and Fire time), while Express-eligible residential permits can go from Tuesday-night submittal to Wednesday issuance. Resubmittals re-enter the date-order queue, so the biggest lever is a complete, checklist-conforming package. Call (954) 921-3335 for current workload.

How do I look up a permit in City of Hollywood?

Hollywood runs a Building Permit Self-Service portal for permit status lookups, plus the Accela portal for application and inspection tracking. To verify the status of any permit for a legal purpose — such as the sale of a property — the city directs you to call the Building Division at (954) 921-3335.

What is Hollywood's Express Permitting Service?

Guaranteed same-day plan review for select residential permit types: submit through the Accela portal between 6 p.m. Tuesday and 9 a.m. Wednesday (up to 10 submittals per applicant), include the required checklist, and — if approved — pay by 3 p.m. Wednesday for electronic issuance. Contractor registration and insurance must be verified and current before submitting, and Historic District applications may need extra review.

What is ePermitsOneStop in Hollywood?

An integration that lets Hollywood applicants apply for and receive approval on both city building permits and associated Broward County permits in one seamless process — no separate trip to Broward's Government Center West in Plantation. It's a genuine time-saver on projects that trigger county-level review.

How long does Hollywood take to review a permit?

Under the Florida Building Code, the Building Division processes permits within a maximum of 30 working days of submission, reviewed in date order — excluding review time for Planning and Zoning, Engineering, and Fire. Express-eligible residential permits can clear in a single Wednesday.

What does a contractor need to register with the City of Hollywood?

The notarized Contractor's Record Management Form plus copies of the qualifier's driver's license, occupational license or business tax receipt, and state certification or registration — with certificates of insurance (or exemption) showing the City of Hollywood as the certificate holder.

Do I need a permit to install solar panels in City of Hollywood?

Yes. Photovoltaic installations in City of Hollywood are permitted under a dedicated solar record type reviewed on both a structural and an electrical track. Solar thermal — passive water and pool heating — is a separate record. Under Fla. Stat. §163.04 a homeowners' association cannot prohibit a solar collector, so HOA approval is not a prerequisite to permit issuance. Utility interconnection and Permission to Operate run in parallel with the permit, not inside it.

Does a roof replacement require a permit in City of Hollywood?

Yes, and City of Hollywood is in the High-Velocity Hurricane Zone, so the bar is higher than the rest of Florida. Roof products must carry a Miami-Dade Notice of Acceptance or a Florida Product Approval valid for the HVHZ, attachment and uplift criteria are stricter, and hurricane mitigation retrofit requirements commonly attach when an existing roof is replaced. Inspections remain sequenced — dry-in, nail-off, then final.

What is the difference between a residential and a commercial permit in City of Hollywood?

Residential work is generally a single-discipline review filed as a master permit with trades filed against it. Commercial work in City of Hollywood runs concurrent review across building, fire, and zoning, requires signed and sealed plans for every affected discipline, and can carry impact and concurrency fees on top of permit fees. Change of use adds accessibility and life-safety review.

Do trade permits need to be pulled separately in City of Hollywood?

Yes in most cases. Electrical, plumbing, and mechanical work is permitted separately by the licensed contractor for each trade and filed against the master building permit. Each trade permit carries its own fee and its own inspection sequence.

What happens if I file under the wrong permit type in City of Hollywood?

The application is rejected rather than corrected. the Hollywood Building Division closes the record, the filing is resubmitted under the correct record type, and the review clock restarts from zero. Confirming the record type before filing is the cheapest step in the entire process.

Can I apply for all Hollywood permit types online?

Most record types are filed through the BCLA permitting system, but availability varies by permit type and by applicant. Some records still require in-person submittal, and owner-builder filings are frequently restricted to counter submittal regardless of record type.

Simplify City of Hollywood permitting with Alliance Permitting

A same-day Express lane, one-stop county integration, QLess consultations, and a hard 30-working-day review clock — Hollywood gives prepared applicants real speed. Alliance Permitting is a permit expediter for City of Hollywood and keeps registrations verified and packages checklist-perfect so your submissions catch every fast lane the city offers.

250K+Permits approved
All 50States covered
AI + HumanExpert filing
Done-for-youWe file, you build

Trusted by leading builders and brands - including Dream Finders Homes, Tesla, Verizon, Hyatt, and Sunnova.

Contractors and builders choose Alliance for City of Hollywood because we deliver:

  • Local expertise - we know the City of Hollywood Building Division and the Accela Citizen Access + ePermitsOneStop process.
  • Complete oversight - track every permit and inspection across all your jobs in one place.
  • Error-free submissions - AI pre-checks plus expert review catch issues before they become correction cycles.

Alliance Permitting is a permit documentation and submission company: we prepare your paperwork, file it correctly, and coordinate with the building department through issuance - including preparing private-provider documentation where that option is available. We are not a contractor and do not perform licensed plan review or inspections; that work stays with your team and the jurisdiction.

Ready to break ground in City of Hollywood sooner?

Let Alliance prepare, file, and track your City of Hollywood permits while you stay focused on building. Get a free, no-obligation quote today.

This guide is provided by Alliance Permitting for general informational purposes and reflects publicly available information believed accurate as of July 2026. Permit requirements, fees, and processes change; always confirm current details with the City of Hollywood Building Division before filing. This is not legal advice.