Building permits in the City of Pembroke Pines — Broward County's second-largest city — are issued by the Building Department, with digital submittals through the city's Development Hub. The city follows the 2023 Florida Building Code with the Broward County Administrative Provisions and sits in the High-Velocity Hurricane Zone (HVHZ).
This Pembroke Pines building permit guide covers what requires a permit, how fees work, the Development Hub process, the HVHZ rules, trade permits, and inspections — so your Pembroke Pines project starts clean.
This guide covers the City of Pembroke Pines (Broward County, HVHZ). The city permits work inside its limits; other Broward municipalities and unincorporated Broward run their own. Structures are designed to Exposure Category C (unless D applies) under ASCE 7-22, the Broward County Uniform Building Permit Application is required, and HVHZ rules require Miami-Dade NOA products and signed/sealed engineering.
What requires a building permit in Pembroke Pines?
Under the 2023 Florida Building Code (with the High-Velocity Hurricane Zone provisions and Broward County Administrative Provisions), a permit is required before most construction, alteration, or demolition. Common triggers include:
Permit required
- New construction, additions, and tenant build-outs
- Structural / load-bearing alterations and demolition
- Reroofing, windows, doors, and shutters (HVHZ product approval)
- Electrical service changes and most wiring alterations
- Mechanical / HVAC installations and changeouts
- Plumbing alterations, repipes, and water heaters
- Patio/screen enclosures (engineered drawings) and pools
- Sheds, fences, and accessory structures
Typically exempt
- Painting, flooring, cabinetry, and cosmetic work
- Like-for-like minor repairs not altering structure or systems
- Routine maintenance not extending or rerouting systems
- Small projects expressly exempt (confirm with the Building Department)
Exemptions are narrow and scope-specific. When unsure, confirm with the building department before starting — see the penalty note below.
Get the permit issued before starting work. Building without one exposes the owner to penalties and stop-work orders. A recorded Notice of Commencement is required for most improvements over $2,500, and the permit card must be displayed and accessible during all inspections.
Who handles permitting in Pembroke Pines?
Permitting, plan review, and inspections run through the Building Department (Building Code Services). The Broward County Board of Rules and Appeals governs the building code countywide, and the department commits to a written approval or denial within 15 working days (excluding Planning & Zoning, Engineering, and Fire review).
| Detail | Information |
|---|---|
| Office | 601 City Center Way, 2nd Floor, Pembroke Pines, FL 33025 |
| Phone | (954) 435-6502 |
| Online portal | Development Hub (register as a Contact to apply) |
| Contractor docs | Email license/insurance to pinespermits@cgasolutions.com |
| Review window | 15 working days for building approval/denial (excludes P&Z/Eng/Fire) |
| Enforced code | 2023 Florida Building Code + HVHZ + Broward Administrative Provisions |
Apply through the Development Hub. Register as a Contact, then upload your application and documents; contractors register (and update state/Broward license, liability, and workers' comp) by email to pinespermits@cgasolutions.com. The Broward County Uniform Building Permit Application is required, and HVHZ openings need Miami-Dade NOA products with signed/sealed plans.
Pembroke Pines permit types
A building permit is one record among many. Building Department issues work under separate record types, and filing under the wrong one is a rejection, not a correction — the application is closed and refiled, and the review clock restarts.
Residential permit types
| Permit type | What triggers it | Review path | Fee basis |
|---|---|---|---|
| New construction | New dwellings, additions, and accessory structures over the exempt threshold | Full plan review (structural, energy, zoning) | Valuation-based |
| Renovation / alteration | Structural or load-bearing changes, layout changes, substantial repair | Plan review scaled to scope | Valuation-based |
| Reroof | Roof covering replacement and most major roof repair | Product approval review; dry-in and nail-off inspections | Valuation or squares |
| Solar photovoltaic | Rooftop or ground-mount PV installation or replacement | Structural plus electrical review | Flat or system-size based |
| Solar thermal | Passive water heating or pool heating systems | Plumbing and structural review | Flat or per-permit minimum |
| Electrical | Service changes, panel upgrades, new circuits, most wiring alterations | Trade review; filed against the building permit | Per-permit minimum or per-device |
| Plumbing | New piping, repipes, water heaters, fixtures, gas piping | Trade review; filed against the building permit | Per-permit minimum or per-fixture |
| Mechanical / HVAC | Changeouts that are not like-for-like, ductwork, refrigeration | Trade review; filed against the building permit | Per-permit minimum or per-unit |
| Windows and doors | Replacement units and opening protection | Product approval review for wind-borne debris | Valuation or per-opening |
| Pool and spa | In-ground and above-ground pools, spas, barrier and enclosure work | Plan review plus barrier and electrical bonding | Valuation-based |
| Fence and accessory | Fences, sheds, decks, and carports over the exempt threshold | Zoning plus structural where applicable | Flat or valuation-based |
| Demolition | Full or partial demolition of a structure | Utility disconnect verification required | Flat |
Commercial permit types
| Permit type | What triggers it | Review path | Fee basis |
|---|---|---|---|
| New construction | Ground-up commercial, industrial, and multifamily | Full multi-discipline plan review | Valuation-based |
| Tenant improvement | Interior build-outs and suite fit-ups | Plan review across affected disciplines | Valuation-based |
| Renovation / alteration | Structural, envelope, or system changes to an existing building | Plan review scaled to scope | Valuation-based |
| Change of use | Converting a building from one occupancy classification to another | Zoning, life-safety, and accessibility review | Valuation or flat |
| Reroof | Commercial roof covering replacement | Product approval review plus fire review where applicable | Valuation or squares |
| Solar photovoltaic | Commercial rooftop, carport, and ground-mount PV | Structural, electrical, and often fire review | Valuation or system-size based |
| Electrical | Service, distribution, and branch circuit work | Trade review | Valuation or per-device |
| Plumbing | Supply, waste, vent, and gas systems | Trade review | Valuation or per-fixture |
| Mechanical / HVAC | Rooftop units, ductwork, exhaust, and refrigeration | Trade review | Valuation or per-unit |
| Fire protection | Sprinkler, standpipe, alarm, and suppression systems | Fire prevention plan review | Valuation or per-device |
| Sign | Wall, monument, and illuminated signage | Zoning plus electrical where illuminated | Flat or per-sign |
| Demolition | Full or partial commercial demolition | Utility disconnect and environmental clearance | Flat or valuation-based |
Residential
- Single-discipline review in most cases
- Master permit with trades filed against it
- Owner-builder route exists but carries statutory affidavits
- Product approval drives roofing and opening protection
Commercial — multi-discipline
- Concurrent review across building, fire, and zoning
- Signed and sealed plans across every affected discipline
- Accessibility and life-safety review attach to change of use
- Impact and concurrency fees can apply on top of permit fees
Solar permits in Pembroke Pines
Solar is permitted as its own record type in most Florida jurisdictions rather than rolled into a general building permit, and residential and commercial photovoltaic are usually separate records with different document sets. Solar thermal — passive water and pool heating — is a third, distinct record.
A photovoltaic submittal is reviewed on two tracks at once: structural (roof load path, attachment spacing, uplift) and electrical (conductor sizing, rapid shutdown, point of interconnection). A single-line diagram and a signed and sealed structural attachment detail are the two attachments most often missing on a first submittal.
Under Fla. Stat. §163.04, a homeowners' association cannot prohibit a solar collector on a dwelling — HOA architectural approval is not a prerequisite to permit issuance, though it may still be a contractual matter between owner and association.
Utility interconnection runs parallel to the building permit, not inside it. Permission to Operate is issued by the utility after the final electrical inspection clears.
High-Velocity Hurricane Zone. Pembroke Pines sits in Broward County, inside the High-Velocity Hurricane Zone. HVHZ work requires products carrying a Miami-Dade Notice of Acceptance or a Florida Product Approval valid for the HVHZ, uses stricter attachment and uplift criteria, and carries review requirements above the statewide baseline — on both solar and roofing.
Roofing permits in Pembroke Pines
A roof covering replacement requires a permit in every Florida jurisdiction. Repairs below the local threshold may not, but the threshold is scope-specific and confirming it with the building department before tear-off is cheaper than an after-the-fact permit.
Every roof product must carry a current Florida Product Approval or Miami-Dade Notice of Acceptance rated for the wind speed at the project address. A product approval number that has lapsed or is rated below the site wind speed is the single most common reroof rejection.
Reroof inspections are sequenced: dry-in after the underlayment, nail-off on the sheathing fastening, and final. Covering the deck before the dry-in inspection means tearing it back open.
Hurricane mitigation retrofit requirements can attach when an existing roof is replaced, including secondary water barrier and roof-to-wall connection work. These add scope and documents, and they are triggered by the replacement itself.
Under Fla. Stat. §553.7922, jurisdictions run expedited procedures for permits that need no technical review — reroofs, roof repairs, and similar — during a declared state of emergency.
Pembroke Pines building permit cost
Pembroke Pines building permit fees are set by the city's annual Building Permit Fee Schedule and based on the type and valuation of work, with separate trade fees and a state-mandated surcharge.
Revisions after issuance require a Building Division Revision Cover Sheet and a plan-review fee; a recorded Notice of Commencement is required for most improvements over $2,500. Confirm current amounts in the city fee schedule before budgeting.
| Fee component | How it works |
|---|---|
| Building permit fee | Based on type and valuation of work (annual fee schedule) |
| Trade permits (E / P / M) | Charged separately per trade |
| Revisions | Building Division Revision Cover Sheet + plan-review fee |
| HVHZ product approval | Miami-Dade NOA / signed-and-sealed engineering |
| Notice of Commencement | Recorded for most improvements over $2,500 |
| Work-without-permit | Penalties and possible stop-work orders |
Want a precise number for a specific Pembroke Pines project? Send us the scope and valuation and we'll return a fee estimate alongside a filing timeline.
Pembroke Pines trade permits
Electrical, plumbing, and mechanical work needs its own permit and a Florida-licensed contractor registered with the city, each filed in the Development Hub.
Electrical permits
Required for service installations, panel upgrades, solar PV, and most wiring alterations, performed by a Florida-licensed electrical contractor.
Plumbing permits
Required for new plumbing, repipes, water heater changeouts, fixtures, and gas piping, performed by a Florida-licensed plumbing contractor.
Mechanical (HVAC) permits
Required for HVAC changeouts, ductwork, and refrigeration, performed by a Florida-licensed mechanical contractor. Specialized systems are permitted and inspected separately.
Miscellaneous & specialty
Reroofs, pools, and shutters are permitted separately. Enclosing a patio is treated as an addition and requires drawings prepared by a Florida-registered architect or engineer, and HVHZ openings require Miami-Dade NOA products.
Verify your contractor's license. Confirm the contractor is licensed by the Florida Department of Business & Professional Regulation (DBPR) at (850) 487-1395 — or holds a valid county registration — and is registered to work in the city before signing. Only a licensed contractor (or a qualifying owner-builder) may pull a permit; owner-builders must apply in person and meet the requirements of Florida Statute 489.103. The property owner is responsible for ensuring a permit is obtained.
How to get a building permit in Pembroke Pines
Confirm scope, zoning & HVHZ items
Verify the work needs a permit, confirm the parcel is inside Pembroke Pines, and identify HVHZ product approvals (NOA) and Exposure Category for design.
Register & prepare documents
Register as a Contact in the Development Hub (contractors email license/insurance to pinespermits@cgasolutions.com), and assemble signed/sealed plans, NOA approvals, the Broward Uniform Application, and the Notice of Commencement for work over $2,500.
Apply in the Development Hub
Upload the application and documents; ensure all information is typed or clearly printed to avoid process holds.
Plan review & corrections
The Building Department reviews (target 15 working days, excluding P&Z/Engineering/Fire); resolve comments and resubmit with a Revision Cover Sheet if needed.
Pay fees & pull the permit
Pay the calculated fees, then post the permit card so it's accessible outside the property for inspections.
Schedule inspections through close-out
Schedule inspections and keep the permit card available. Clear all required inspections to obtain your Certificate of Occupancy.
Inspections in Pembroke Pines
Schedule inspections through the Building Department; the permit card and attached documents must be available and accessible (outside the property) to the inspector during all inspections. Typical checkpoints include foundation, tie-beam, rough-in MEP, framing, insulation, and final.
A re-inspection fee applies to failed inspections and must be cleared before a final inspection or Certificate of Occupancy can be requested.
Official Pembroke Pines permitting resources
- 🏛️ Pembroke Pines — Apply for a Building Permit
- 📋 Applications & forms (Broward Uniform App)
- ❓ Building Department FAQs
- 🪪 Florida DBPR contractor licensing
- 📘 Florida Building Code (HVHZ)
- 🗺️ Broward County Board of Rules & Appeals
Frequently asked questions
Who issues building permits in the City of Pembroke Pines?
The City of Pembroke Pines Building Department (Building Code Services) issues permits, reviews plans, and inspects inside city limits. Other Broward municipalities and unincorporated Broward run their own departments.
How do I get a building permit in Pembroke Pines?
Register as a Contact in the Development Hub, upload the Broward County Uniform Building Permit Application plus signed/sealed plans and NOA product approvals, complete review (target 15 working days), pay fees, and schedule inspections.
What building code does Pembroke Pines use?
The City of Pembroke Pines follows the 2023 Florida Building Code with the Broward County Administrative Provisions and is in the High-Velocity Hurricane Zone, with structures designed to Exposure Category C (unless D applies) under ASCE 7-22.
How long does Pembroke Pines take to review a permit?
The code allows 15 working days to provide a written approval or denial of a building application; that period does not include review time for Planning & Zoning, Engineering, and Fire.
Do I need engineered drawings to enclose a patio in Pembroke Pines?
Yes. Enclosing a patio is considered an addition and requires drawings prepared by a Florida-registered architect or engineer, plus HVHZ-compliant products.
Do I need a permit to install solar panels in Pembroke Pines?
Yes. Photovoltaic installations in Pembroke Pines are permitted under a dedicated solar record type reviewed on both a structural and an electrical track. Solar thermal — passive water and pool heating — is a separate record. Under Fla. Stat. §163.04 a homeowners' association cannot prohibit a solar collector, so HOA approval is not a prerequisite to permit issuance. Utility interconnection and Permission to Operate run in parallel with the permit, not inside it.
Does a roof replacement require a permit in Pembroke Pines?
Yes, and Pembroke Pines is in the High-Velocity Hurricane Zone, so the bar is higher than the rest of Florida. Roof products must carry a Miami-Dade Notice of Acceptance or a Florida Product Approval valid for the HVHZ, attachment and uplift criteria are stricter, and hurricane mitigation retrofit requirements commonly attach when an existing roof is replaced. Inspections remain sequenced — dry-in, nail-off, then final.
What is the difference between a residential and a commercial permit in Pembroke Pines?
Residential work is generally a single-discipline review filed as a master permit with trades filed against it. Commercial work in Pembroke Pines runs concurrent review across building, fire, and zoning, requires signed and sealed plans for every affected discipline, and can carry impact and concurrency fees on top of permit fees. Change of use adds accessibility and life-safety review.
Do trade permits need to be pulled separately in Pembroke Pines?
Yes in most cases. Electrical, plumbing, and mechanical work is permitted separately by the licensed contractor for each trade and filed against the master building permit. Each trade permit carries its own fee and its own inspection sequence.
What happens if I file under the wrong permit type in Pembroke Pines?
The application is rejected rather than corrected. Building Department closes the record, the filing is resubmitted under the correct record type, and the review clock restarts from zero. Confirming the record type before filing is the cheapest step in the entire process.
Can I apply for all Pembroke Pines permit types online?
Most record types are filed through Development Hub, but availability varies by permit type and by applicant. Some records still require in-person submittal, and owner-builder filings are frequently restricted to counter submittal regardless of record type.
Simplify Pembroke Pines permitting with Alliance Permitting
Pembroke Pines' Development Hub intake, Broward Administrative Provisions, and HVHZ Exposure-C design rules reward applicants who prepare complete, NOA-backed packages. Alliance Permitting is a permit expediter for Pembroke Pines — our permit expediting services pair AI-driven document review with experts who know the Building Department and Development Hub process, so your Pembroke Pines submissions move faster.
Trusted by leading builders and brands — including Dream Finders Homes, Tesla, Verizon, Hyatt, and Sunnova.
Contractors and builders choose Alliance for Pembroke Pines because we deliver:
- Local expertise — we know the Pembroke Pines Building Department, the Development Hub, the Broward Uniform Application, and HVHZ requirements.
- Complete oversight — track every permit and inspection across all your jobs in one place.
- Error-free submissions — AI pre-checks plus expert review catch issues before they become correction cycles.
Alliance Permitting is a permit documentation and submission company: we prepare your paperwork, file it correctly, and coordinate with the building department through issuance — including preparing private-provider documentation where that option is available. We are not a contractor and do not perform licensed plan review or inspections; that work stays with your team and the jurisdiction.
Ready to break ground in Pembroke Pines sooner?
Let Alliance prepare, file, and track your City of Pembroke Pines permits while you stay focused on building. Get a free, no-obligation quote today.
More Florida permitting guides
This guide is provided by Alliance Permitting for general informational purposes and reflects publicly available information believed accurate as of June 2026. Permit requirements, fees, and processes change; always confirm current details with the City of Pembroke Pines Building Department before filing. This is not legal advice.