Municipal GuideFloridaCity of Homestead · Miami-Dade County

City of Homestead Building & Trade Permit Guide

How to get a building permit in Homestead, FL — the new EPL-B.U.I.L.D portal, county DERM and impact-fee steps, HVHZ rules, inspections. 2026 guide.

Jurisdiction: City of Homestead Development Services DepartmentCode: Florida Building Code, 8th Ed. (2023)Portal: EPL-B.U.I.L.D portal (since October 1, 2025)
Authority
Homestead Development Services
City Hall, 100 Civic Court
Apply
EPL-B.U.I.L.D (since 10/1/2025)
Legacy projects stay in Community Plus
County layer
DERM / WASD / impact fees
Paid separately once the M# issues
Wind zone
High-Velocity Hurricane Zone
Miami-Dade NOAs required

The City of Homestead — southern Miami-Dade's fast-growing city between the national parks, one of Florida's busiest home-building markets — issues building permits through the Development Services Department at City Hall, 100 Civic Court. The system is brand new: on October 1, 2025, the city launched EPL-B.U.I.L.D — Electronic Permitting & Licensing for Building, Utilities, Inspections, Land, & Development — an integrated platform for submitting applications, uploading drawings, and tracking progress across every reviewing department, rolled out in two phases with electronic plan review enabling simultaneous multi-department reviews. Projects started before October 1, 2025 continue as legacy projects in the Community Plus system.

Homestead's county layer is the step that catches newcomers: projects requiring approval from Miami-Dade County's DERM (environmental), WASD (water and sewer), or county impact fees must also submit to Miami-Dade through the county's portal — and the city is explicit that its own upfront fees do not include the county agencies' charges, which are paid separately once a Miami-Dade Project Number (M#) has been issued. Fee amounts themselves were freshly reset: on September 9, 2025, the City Council adopted Ordinance No. 2025-09-25 establishing updated building permit and related fees.

Applies inside City of Homestead limits. Neighboring Florida City runs its own permitting, and unincorporated parcels route to Miami-Dade County - confirm the jurisdiction before filing.

📍 This is HVHZ — and upfront fees land before review starts. Homestead sits in the High-Velocity Hurricane Zone, so windows, doors, roofing, and shutters need Miami-Dade Notices of Acceptance or HVHZ-rated Florida Product Approvals, with plan review checking them closely. On the money side, projects like new construction and interior remodels require an upfront review fee paid at submittal — with the balance due at issuance — and the county's DERM, WASD, and impact-fee charges stack separately on top once the M# issues, so budget both governments from day one.

What requires a building permit in City of Homestead?

Under the Florida Building Code (§105.1), a permit is required before you construct, enlarge, alter, repair, move, demolish, or change the occupancy of most structures and systems. New for 2026: Florida HB 803 (effective July 1, 2026) created additional building-permit exemptions for certain single-family residential work - notably F.S. 553.79(1)(g), which can exempt qualifying work valued under $7,500 when it involves no electrical, plumbing, mechanical, gas, or structural work, the home is not in a Special Flood Hazard Area, and the owner submits a written exemption request to the Building Official. Ask the permit counter whether your scope qualifies before assuming a permit is needed.

Permit required

  • New homes, additions, and tenant build-outs
  • Structural / load-bearing alterations and demolition
  • Reroofing, window and door replacement, and exterior work
  • Electrical service changes and most wiring alterations
  • Mechanical / HVAC changeouts and boilers
  • Plumbing alterations, repipes, gas, and water heaters
  • Pools and spas (barrier required), signs, and fences
  • Manufactured homes and solar PV systems

Usually exempt

  • Painting, flooring, cabinetry, and cosmetic work
  • Like-for-like minor repairs not altering systems
  • Certain low non-structural fences (confirm limits)
  • Routine maintenance not extending or rerouting systems
Exemptions are narrow and local. Always verify with the permit counter before starting work - unpermitted work risks stop-work orders, doubled fees, and closing/insurance problems.

Who handles permitting in City of Homestead?

Development Services operates from Homestead City Hall at 100 Civic Court, running the EPL-B.U.I.L.D platform with electronic plan review across Development Services, Public Works, Code Compliance, the city's own Energy Department (Homestead runs its own electric utility), and the City Clerk's Office — plus a citywide online payment solution. Project questions route to epermits@homesteadfl.gov, legacy submissions historically flowed through permits@homesteadfl.gov, and planning payment accounts come from planning@cityofhomestead.com — with drawings and documents uploading at the Attachment screen of the online application. All permitting runs through the EPL-B.U.I.L.D portal (since October 1, 2025).

  • Address: Homestead City Hall, 100 Civic Court, Homestead, FL 33030
  • Email: epermits@homesteadfl.gov
  • Hours: Monday–Friday (city business hours)

City of Homestead permit types

A building permit is one record among many. Homestead Development Services issues work under separate record types, and filing under the wrong one is a rejection, not a correction — the application is closed and refiled, and the review clock restarts.

Residential permit types

Residential permit types in City of Homestead
Permit typeWhat triggers itReview pathFee basis
New constructionNew dwellings, additions, and accessory structures over the exempt thresholdFull plan review (structural, energy, zoning)Valuation-based
Renovation / alterationStructural or load-bearing changes, layout changes, substantial repairPlan review scaled to scopeValuation-based
ReroofRoof covering replacement and most major roof repairProduct approval review; dry-in and nail-off inspectionsValuation or squares
Solar photovoltaicRooftop or ground-mount PV installation or replacementStructural plus electrical reviewFlat or system-size based
Solar thermalPassive water heating or pool heating systemsPlumbing and structural reviewFlat or per-permit minimum
ElectricalService changes, panel upgrades, new circuits, most wiring alterationsTrade review; filed against the building permitPer-permit minimum or per-device
PlumbingNew piping, repipes, water heaters, fixtures, gas pipingTrade review; filed against the building permitPer-permit minimum or per-fixture
Mechanical / HVACChangeouts that are not like-for-like, ductwork, refrigerationTrade review; filed against the building permitPer-permit minimum or per-unit
Windows and doorsReplacement units and opening protectionProduct approval review for wind-borne debrisValuation or per-opening
Pool and spaIn-ground and above-ground pools, spas, barrier and enclosure workPlan review plus barrier and electrical bondingValuation-based
Fence and accessoryFences, sheds, decks, and carports over the exempt thresholdZoning plus structural where applicableFlat or valuation-based
DemolitionFull or partial demolition of a structureUtility disconnect verification requiredFlat

Commercial permit types

Commercial permit types in City of Homestead
Permit typeWhat triggers itReview pathFee basis
New constructionGround-up commercial, industrial, and multifamilyFull multi-discipline plan reviewValuation-based
Tenant improvementInterior build-outs and suite fit-upsPlan review across affected disciplinesValuation-based
Renovation / alterationStructural, envelope, or system changes to an existing buildingPlan review scaled to scopeValuation-based
Change of useConverting a building from one occupancy classification to anotherZoning, life-safety, and accessibility reviewValuation or flat
ReroofCommercial roof covering replacementProduct approval review plus fire review where applicableValuation or squares
Solar photovoltaicCommercial rooftop, carport, and ground-mount PVStructural, electrical, and often fire reviewValuation or system-size based
ElectricalService, distribution, and branch circuit workTrade reviewValuation or per-device
PlumbingSupply, waste, vent, and gas systemsTrade reviewValuation or per-fixture
Mechanical / HVACRooftop units, ductwork, exhaust, and refrigerationTrade reviewValuation or per-unit
Fire protectionSprinkler, standpipe, alarm, and suppression systemsFire prevention plan reviewValuation or per-device
SignWall, monument, and illuminated signageZoning plus electrical where illuminatedFlat or per-sign
DemolitionFull or partial commercial demolitionUtility disconnect and environmental clearanceFlat or valuation-based

Residential

  • Single-discipline review in most cases
  • Master permit with trades filed against it
  • Owner-builder route exists but carries statutory affidavits
  • Product approval drives roofing and opening protection

Commercial — multi-discipline

  • Concurrent review across building, fire, and zoning
  • Signed and sealed plans across every affected discipline
  • Accessibility and life-safety review attach to change of use
  • Impact and concurrency fees can apply on top of permit fees

Solar permits in City of Homestead

Solar is permitted as its own record type in most Florida jurisdictions rather than rolled into a general building permit, and residential and commercial photovoltaic are usually separate records with different document sets. Solar thermal — passive water and pool heating — is a third, distinct record.

A photovoltaic submittal is reviewed on two tracks at once: structural (roof load path, attachment spacing, uplift) and electrical (conductor sizing, rapid shutdown, point of interconnection). A single-line diagram and a signed and sealed structural attachment detail are the two attachments most often missing on a first submittal.

Under Fla. Stat. §163.04, a homeowners' association cannot prohibit a solar collector on a dwelling — HOA architectural approval is not a prerequisite to permit issuance, though it may still be a contractual matter between owner and association.

Utility interconnection runs parallel to the building permit, not inside it. Permission to Operate is issued by the utility after the final electrical inspection clears.

🌪

High-Velocity Hurricane Zone. City of Homestead sits in Miami-Dade County, inside the High-Velocity Hurricane Zone. HVHZ work requires products carrying a Miami-Dade Notice of Acceptance or a Florida Product Approval valid for the HVHZ, uses stricter attachment and uplift criteria, and carries review requirements above the statewide baseline — on both solar and roofing.

Roofing permits in City of Homestead

A roof covering replacement requires a permit in every Florida jurisdiction. Repairs below the local threshold may not, but the threshold is scope-specific and confirming it with the building department before tear-off is cheaper than an after-the-fact permit.

Every roof product must carry a current Florida Product Approval or Miami-Dade Notice of Acceptance rated for the wind speed at the project address. A product approval number that has lapsed or is rated below the site wind speed is the single most common reroof rejection.

Reroof inspections are sequenced: dry-in after the underlayment, nail-off on the sheathing fastening, and final. Covering the deck before the dry-in inspection means tearing it back open.

Hurricane mitigation retrofit requirements can attach when an existing roof is replaced, including secondary water barrier and roof-to-wall connection work. These add scope and documents, and they are triggered by the replacement itself.

Under Fla. Stat. §553.7922, jurisdictions run expedited procedures for permits that need no technical review — reroofs, roof repairs, and similar — during a declared state of emergency.

Record types, document sets, and fee structures are set by Homestead Development Services and change without notice. Confirm the current record type against the building department before filing.

City of Homestead building permit cost

Permit fees follow the schedule adopted September 9, 2025 under Ordinance No. 2025-09-25 — with upfront review fees at submittal on new construction and interior remodels, the balance at issuance, and online payments keyed to the 8-digit process/permit number on the invoice. The county layer is a separate budget line: DERM, WASD, and impact-fee charges are paid to Miami-Dade once the M# issues, never bundled into the city's upfront fees — and HVHZ product documentation carries its usual cost premium on every exterior component.

How City of Homestead permitting works

ComponentHow it works
Permit feesPer Ordinance No. 2025-09-25 (adopted 9/9/2025) through EPL-B.U.I.L.D
Upfront feesPaid at submittal on new construction and interior remodels; balance at issuance
Online paymentBy account number — the 8-digit process/permit number on the invoice
County agenciesDERM / WASD / impact fees paid separately to Miami-Dade once the M# issues
Legacy projectsApplications started before 10/1/2025 continue in Community Plus
HVHZ productsMiami-Dade NOAs or HVHZ-rated approvals on all exterior components
Platform dates, ordinance citation, and county-fee separation per the City of Homestead's posted permitting guide and fee pages — confirm current fee amounts through EPL-B.U.I.L.D before budgeting

City of Homestead trade permits

Trade permits file through EPL-B.U.I.L.D against the master permit — with Homestead's city-owned electric utility making the Energy Department a reviewing party on electrical-service scopes, a wrinkle unique among Florida cities of its size. HVHZ governs everything exterior: impact windows and doors, roofing systems with Miami-Dade's uniform roofing documentation, and shutters all carry NOA-level product approvals, while plans for new structures include the full technical set — structural cross-sections with materials and fasteners, roof framing, electrical service, and energy calculations on conditioned space.

Electrical permits

Required for service installations, panel upgrades, solar PV, and most wiring alterations in City of Homestead, filed by a licensed electrical contractor against the master building permit through the City of Homestead Development Services Department.

Plumbing permits

Required for new plumbing, repipes, water heater changeouts, fixture relocations, and gas piping; fees follow the local schedule with per-permit minimums.

Mechanical (HVAC) permits

Required for HVAC installations and changeouts, ductwork, and refrigeration; specialized systems are permitted and inspected separately.

Miscellaneous & specialty

Roofs, pools and spas, screen enclosures, mobile home set-ups, and demolition are permitted separately. Exterior components need current Florida Product Approval rated for the local wind speed.

How to get a building permit in City of Homestead

Confirm jurisdiction and the county triggers

Verify the parcel is inside Homestead city limits (unincorporated parcels permit through Miami-Dade County), and identify early whether the scope triggers DERM, WASD, or county impact fees — those run through Miami-Dade's portal alongside the city file.

Register in EPL-B.U.I.L.D

Create the portal account — the intake channel for everything filed since October 1, 2025 — noting that pre-existing applications continue as legacy projects in Community Plus.

Assemble the HVHZ package

Plans with the full technical set — site plan, survey, structural cross-sections, roof framing, electrical service, energy calculations on conditioned space — and Miami-Dade NOAs or HVHZ-rated approvals on every exterior product.

Submit, upload, and pay the upfront fee

File through the portal, uploading drawings and documents at the Attachment screen; new construction and interior remodels pay the upfront review fee at submittal.

Run the county lane in parallel

Where triggered, submit to Miami-Dade for DERM, WASD, and impact-fee processing — paying those agencies separately once the M# project number issues — so county approvals land alongside city review.

Pay the balance, pull, and inspect

Pay remaining fees at issuance by the invoice's 8-digit account number, record the Notice of Commencement, post the permit, and schedule inspections through the portal through final and CO.

Inspections in City of Homestead

Inspections run through the EPL-B.U.I.L.D platform's integrated workflow, with electronic plan review's multi-department routing — Development Services, Public Works, Code Compliance, Energy — carried into the field phase. HVHZ inspections verify NOA-documented products on every exterior component, county-triggered scopes keep the M#-linked approvals in the file, and the city's own electric utility coordinates on service releases through the Energy Department's role in the system.

Official City of Homestead permitting resources

Frequently asked questions

How long does it take to get a building permit in City of Homestead?

EPL-B.U.I.L.D's simultaneous multi-department electronic review was built to compress issuance times, and the schedule levers are the parallel tracks: the county lane (DERM/WASD/impact fees via the M#) started early so it never trails city review, upfront fees paid at submittal so review starts immediately, and NOA documentation complete so HVHZ checks pass the first time. Email epermits@homesteadfl.gov for current turnaround by permit type.

How do I look up a permit in City of Homestead?

Homestead applications filed since October 1, 2025 live in the EPL-B.U.I.L.D portal — submit, upload, and track in one place — while projects started before that date continue as legacy projects in the Community Plus system. Online payments run by account number: the 8-digit process/permit number from the permit invoice, with planning items using a 6-digit account from planning@cityofhomestead.com.

What is EPL-B.U.I.L.D in Homestead?

The city's Electronic Permitting & Licensing platform — Building, Utilities, Inspections, Land, & Development — launched October 1, 2025 in a two-phase rollout: an integrated portal for submitting applications, uploading documents, and tracking progress, with electronic plan review running simultaneous multi-department reviews and a citywide online payment solution. Applications started before October 1, 2025 continue as legacy projects in the Community Plus system.

How do Miami-Dade County fees work on a Homestead permit?

Separately — and after the M#. If the project requires DERM (environmental), WASD (water/sewer), or county impact fees, you submit to Miami-Dade through the county's portal, and those agencies' upfront fees are paid directly to the county once a Miami-Dade Project Number (M#) has been issued. The city's own upfront fees never include the county charges.

Does Homestead require Miami-Dade NOAs?

Yes — Homestead sits in the High-Velocity Hurricane Zone, so windows, doors, roofing systems, and shutters need Miami-Dade Notices of Acceptance or HVHZ-rated Florida Product Approvals, verified in plan review and at inspection. It's the toughest wind-product standard in the country, and it applies to every exterior component.

When did Homestead's permit fees last change?

September 9, 2025 — the City Council adopted Ordinance No. 2025-09-25 establishing updated building permit and related fees, weeks before the EPL-B.U.I.L.D launch. Upfront review fees apply at submittal on new construction and interior remodels, with the balance due at issuance and online payment keyed to the invoice's 8-digit account number.

Do I need a permit to install solar panels in City of Homestead?

Yes. Photovoltaic installations in City of Homestead are permitted under a dedicated solar record type reviewed on both a structural and an electrical track. Solar thermal — passive water and pool heating — is a separate record. Under Fla. Stat. §163.04 a homeowners' association cannot prohibit a solar collector, so HOA approval is not a prerequisite to permit issuance. Utility interconnection and Permission to Operate run in parallel with the permit, not inside it.

Does a roof replacement require a permit in City of Homestead?

Yes, and City of Homestead is in the High-Velocity Hurricane Zone, so the bar is higher than the rest of Florida. Roof products must carry a Miami-Dade Notice of Acceptance or a Florida Product Approval valid for the HVHZ, attachment and uplift criteria are stricter, and hurricane mitigation retrofit requirements commonly attach when an existing roof is replaced. Inspections remain sequenced — dry-in, nail-off, then final.

What is the difference between a residential and a commercial permit in City of Homestead?

Residential work is generally a single-discipline review filed as a master permit with trades filed against it. Commercial work in City of Homestead runs concurrent review across building, fire, and zoning, requires signed and sealed plans for every affected discipline, and can carry impact and concurrency fees on top of permit fees. Change of use adds accessibility and life-safety review.

Do trade permits need to be pulled separately in City of Homestead?

Yes in most cases. Electrical, plumbing, and mechanical work is permitted separately by the licensed contractor for each trade and filed against the master building permit. Each trade permit carries its own fee and its own inspection sequence.

What happens if I file under the wrong permit type in City of Homestead?

The application is rejected rather than corrected. Homestead Development Services closes the record, the filing is resubmitted under the correct record type, and the review clock restarts from zero. Confirming the record type before filing is the cheapest step in the entire process.

Can I apply for all Homestead permit types online?

Most record types are filed through EPL-B.U.I.L.D, but availability varies by permit type and by applicant. Some records still require in-person submittal, and owner-builder filings are frequently restricted to counter submittal regardless of record type.

Simplify City of Homestead permitting with Alliance Permitting

A weeks-old permitting platform, a two-government fee structure keyed to the M#, a city-owned electric utility in the review chain, and HVHZ product standards on every opening — Homestead layers Miami-Dade's toughest rules onto Florida's newest system. Alliance Permitting is a permit expediter for City of Homestead and runs both portals in parallel so your south-Dade project clears city and county in one coordinated pass.

250K+Permits approved
All 50States covered
AI + HumanExpert filing
Done-for-youWe file, you build

Trusted by leading builders and brands - including Dream Finders Homes, Tesla, Verizon, Hyatt, and Sunnova.

Contractors and builders choose Alliance for City of Homestead because we deliver:

  • Local expertise - we know the City of Homestead Development Services Department and the EPL-B.U.I.L.D portal (since October 1, 2025) process.
  • Complete oversight - track every permit and inspection across all your jobs in one place.
  • Error-free submissions - AI pre-checks plus expert review catch issues before they become correction cycles.

Alliance Permitting is a permit documentation and submission company: we prepare your paperwork, file it correctly, and coordinate with the building department through issuance - including preparing private-provider documentation where that option is available. We are not a contractor and do not perform licensed plan review or inspections; that work stays with your team and the jurisdiction.

Ready to break ground in City of Homestead sooner?

Let Alliance prepare, file, and track your City of Homestead permits while you stay focused on building. Get a free, no-obligation quote today.

This guide is provided by Alliance Permitting for general informational purposes and reflects publicly available information believed accurate as of July 2026. Permit requirements, fees, and processes change; always confirm current details with the City of Homestead Development Services Department before filing. This is not legal advice.