Holmes County permitting runs through the county Building Department, located inside the Board of County Commissioners office at 107 E. Virginia Ave. in Bonifay — open 8 a.m. to 4 p.m. weekdays. Building Official Keith Bennett heads the office, planning services are provided through Alday-Howell Engineering (planner John Feeney), and there is no city building department in Bonifay — the county handles it.
Holmes County publishes unusually specific technical rules that trip up out-of-county contractors: all trusses must be engineered with truss plans and layout submitted at application, new single-family dwellings require Florida energy forms at application, and temp power poles have their own grounding spec. This guide covers all of it — requirements, fees, trade permits, and inspections.
Applies to Holmes County parcels under the county Building Department, including the towns. For work inside the limits of Bonifay, Esto, Noma, Ponce de Leon or Westville, the county’s checklists require a letter from that town for city compliance (Bonifay 850-547-4238, Esto 850-263-6521, Noma 850-263-3449, Ponce de Leon 850-836-4361, Westville 850-548-5858).
What requires a building permit in Holmes County?
Permit required
- New homes, additions, and tenant build-outs
- Structural / load-bearing alterations and demolition
- Reroofing, window and door replacement, and exterior work
- Electrical service changes and most wiring alterations
- Mechanical / HVAC changeouts and boilers
- Plumbing alterations, repipes, gas, and water heaters
- Pools and spas (barrier required), signs, and fences
- Manufactured homes and solar PV systems
Usually exempt
- Painting, flooring, cabinetry, and cosmetic work
- Like-for-like minor repairs not altering systems
- Certain low non-structural fences (confirm limits)
- Routine maintenance not extending or rerouting systems
Florida requires a permit under the Florida Building Code (section 105.1) for most construction, alteration, repair, demolition and change of occupancy; since 1 July 2026 a narrow exemption covers some single-family work under $7,500, and single-family permits stay valid for at least a year. When a permit is required in Florida
Who handles permitting in Holmes County?
The Building Department sits inside the Holmes County BOCC office in Bonifay: Building Official Keith Bennett (hcbd@holmescountyfl.org, office 850-547-1119, cell 850-703-3900), permit technicians Shawna Lumpkin and Gracie Slay at the same email, and planning through Alday-Howell (John Feeney, 850-634-6084). Related steps route to other agencies: land development approval happens in the Building Department, 911 address verification through the 911 office (850-547-1112), septic tank permits through the Florida Department of Environmental Protection (850-245-8383), as the county packets list it, driveways on county roads through the Holmes County Road Department (850-547-1408), and driveways on State Roads 79, 90, 81, and 2 through FDOT (850-836-5790). All permitting runs through the In person (BOCC office, Bonifay).
Short on time to read all of this?
Get a free quote →- Address: 107 E. Virginia Ave., Bonifay, FL 32425
- Phone: (850) 547-1119 ext. 3
- Email: hcbd@holmescountyfl.org
- Hours: Monday–Friday, 8:00 a.m. – 4:00 p.m.
Holmes County permit types
A building permit is one record among many. the Holmes County Building Department issues work under separate record types, and filing under the wrong one is a rejection, not a correction — the application is closed and refiled, and the review clock restarts.
Residential permit types
| Permit type | What triggers it | Review path | Fee basis |
|---|---|---|---|
| New construction | New dwellings, additions, and accessory structures over the exempt threshold | Full plan review (structural, energy, zoning) | Valuation-based |
| Renovation / alteration | Structural or load-bearing changes, layout changes, substantial repair | Plan review scaled to scope | Valuation-based |
| Reroof | Roof covering replacement and most major roof repair | Product approval review; dry-in and nail-off inspections | Valuation or squares |
| Solar photovoltaic | Rooftop or ground-mount PV installation or replacement | Structural plus electrical review | Flat or system-size based |
| Solar thermal | Passive water heating or pool heating systems | Plumbing and structural review | Flat or per-permit minimum |
| Electrical | Service changes, panel upgrades, new circuits, most wiring alterations | Trade review; filed against the building permit | Per-permit minimum or per-device |
| Plumbing | New piping, repipes, water heaters, fixtures, gas piping | Trade review; filed against the building permit | Per-permit minimum or per-fixture |
| Mechanical / HVAC | Changeouts that are not like-for-like, ductwork, refrigeration | Trade review; filed against the building permit | Per-permit minimum or per-unit |
| Windows and doors | Replacement units and opening protection | Product approval review for wind-borne debris | Valuation or per-opening |
| Pool and spa | In-ground and above-ground pools, spas, barrier and enclosure work | Plan review plus barrier and electrical bonding | Valuation-based |
| Fence and accessory | Fences, sheds, decks, and carports over the exempt threshold | Zoning plus structural where applicable | Flat or valuation-based |
| Demolition | Full or partial demolition of a structure | Utility disconnect verification required | Flat |
Not sure this scope needs a permit?
Get a free quote →Commercial permit types
| Permit type | What triggers it | Review path | Fee basis |
|---|---|---|---|
| New construction | Ground-up commercial, industrial, and multifamily | Full multi-discipline plan review | Valuation-based |
| Tenant improvement | Interior build-outs and suite fit-ups | Plan review across affected disciplines | Valuation-based |
| Renovation / alteration | Structural, envelope, or system changes to an existing building | Plan review scaled to scope | Valuation-based |
| Change of use | Converting a building from one occupancy classification to another | Zoning, life-safety, and accessibility review | Valuation or flat |
| Reroof | Commercial roof covering replacement | Product approval review plus fire review where applicable | Valuation or squares |
| Solar photovoltaic | Commercial rooftop, carport, and ground-mount PV | Structural, electrical, and often fire review | Valuation or system-size based |
| Electrical | Service, distribution, and branch circuit work | Trade review | Valuation or per-device |
| Plumbing | Supply, waste, vent, and gas systems | Trade review | Valuation or per-fixture |
| Mechanical / HVAC | Rooftop units, ductwork, exhaust, and refrigeration | Trade review | Valuation or per-unit |
| Fire protection | Sprinkler, standpipe, alarm, and suppression systems | Fire prevention plan review | Valuation or per-device |
| Sign | Wall, monument, and illuminated signage | Zoning plus electrical where illuminated | Flat or per-sign |
| Demolition | Full or partial commercial demolition | Utility disconnect and environmental clearance | Flat or valuation-based |
Rather talk it over?
Call 1-855-478-4290 →Residential
- Single-discipline review in most cases
- Master permit with trades filed against it
- Owner-builder route exists but carries statutory affidavits
- Product approval drives roofing and opening protection
Commercial — multi-discipline
- Concurrent review across building, fire, and zoning
- Signed and sealed plans across every affected discipline
- Accessibility and life-safety review attach to change of use
- Impact and concurrency fees can apply on top of permit fees
Roofing permits in Holmes County
Solar and roofing work follow statewide rules on HOA limits, product approval, reroof inspections and hurricane mitigation. Solar and roofing rules in Florida
Holmes County building permit cost
Holmes County bases the building permit fee on the total cost of the project, labour and materials (if labour is unknown, the county doubles the materials cost); reroof permit cost depends on the size of the roof, and trade sub-permits are charged separately. From 1 October 2026 a plan review fee of $300 (residential) or $500 (commercial) is due at submittal. The county’s residential and commercial construction packets (posted on the Building/Planning/Zoning page) spell out the documentation requirements per project type. Budget for the septic, E-911, and driveway steps where they apply, and remember the double-fee penalty for unpermitted starts.
How Holmes County permitting works
| Component | How it works |
|---|---|
| Building permit fees | By project type and scope per county packets (reroofs priced by roof size) |
| Work started before permit | Double fees (posted county policy) |
| Septic permit | Florida Department of Environmental Protection, (850) 245-8383 (per county packets) |
| State-road driveways (SR 79, 90, 81, 2) | FDOT permitting, (850) 836-5790 |
Holmes County trade permits
Rather not deal with the Holmes County building department?
Get a free quote →Electrical permits
Required for service installations, panel upgrades, solar PV, and most wiring alterations in Holmes County, filed by a licensed electrical contractor against the master building permit through the Holmes County Building Department.
Plumbing permits
Required for new plumbing, repipes, water heater changeouts, fixture relocations, and gas piping; fees follow the local schedule with per-permit minimums.
Mechanical (HVAC) permits
Required for HVAC installations and changeouts, ductwork, and refrigeration; specialized systems are permitted and inspected separately.
Miscellaneous & specialty
Roofs, pools and spas, screen enclosures, mobile home set-ups, and demolition are permitted separately. Exterior components need current Florida Product Approval rated for the local wind speed.
How to get a building permit in Holmes County
Clear the prerequisite agencies
Get land development approval (in the Building Department), verify your 911 address (850-547-1112), obtain a septic tank permit from the Florida Department of Environmental Protection (850-245-8383), as the county packets list it, with a copy of your plans, get a letter from the town if the site is inside town limits, and secure a driveway permit from the county Road Department (850-547-1408) or, on SR 79, 90, 81, or 2, from FDOT.
Assemble the technical package
Include engineered truss plans and layout, Florida energy forms (new single-family), Florida Product Approval numbers for materials, and an elevation certificate from a licensed professional for any flood-zone construction.
Apply at the BOCC office
Submit at 107 E. Virginia Ave. in Bonifay, Monday–Friday 8 a.m.–4 p.m., or call (850) 547-1119 ext. 3 with questions first.
Record the Notice of Commencement
Submit the NOC (or a recorded copy with affidavit) with the application; a certified copy must reach the Building Department before the second inspection can be performed.
Pull the permit before touching the site
No inspections occur before issuance, and work started early is subject to double fees. The department does not enforce deed restrictions — check your own covenants.
Inspect on 24-hour notice through final
Call each inspection at least 24 hours ahead, keep activity moving — the permit voids if no inspection is called within six months — and close out through final.
Inspections in Holmes County
Inspections require 24-hour advance notice, no inspection happens before the permit is issued, and a certified copy of the recorded Notice of Commencement must be on file before the second or any subsequent inspection. The six-month rule matters on slow-moving projects: a permit becomes void if no inspection is called for within six months, so schedule at least one qualifying inspection to keep the permit alive.
Want this handled start to finish?
Get a free quote →Official Holmes County permitting resources
- Holmes County Building Department
- Fee information
- Permitting information
- Permit lookup
- Florida Building Code (8th Ed.)
- Florida Product Approval search
- DBPR license verification
Frequently asked questions
How long does it take to get a building permit in Holmes County?
The county says a complete residential submittal may take up to seven days for plan review and permitting, and commercial projects fourteen days or longer depending on complexity. The prerequisite steps — septic, 911 address verification, and driveway permits — usually set the critical path, so start them first. Call (850) 547-1119 ext. 3 for current review times.
How do I look up a permit in Holmes County?
Holmes County runs an online permit search on its iWorQ portal (holmessearch.portal.iworq.net), linked from the Building/Planning/Zoning page. For anything the portal does not show, contact the Building Department at (850) 547-1119 or hcbd@holmescountyfl.org with the parcel or permit number.
What are Holmes County's truss and energy form rules?
All trusses must be engineered, and truss plans and layout must be submitted at the time of building permit application — not later. All new single-family dwellings also require Florida energy forms at application. Missing either is the most common reason first-time submissions bounce.
What happens if I start work without a permit in Holmes County?
Any construction commenced prior to being permitted is subject to double fees under the county's posted policy, and no inspections will be made prior to permit issuance. The county also voids permits when no inspection is called for within six months.
What are the temp power pole requirements in Holmes County?
All temp power poles require one ground rod and two separate GFIs; all other power poles require two ground rods. Florida Product Approval numbers are also required for materials such as shingles, underlayment, and metal roofing.
Does Bonifay have its own building department?
No — the City of Bonifay does not have a local building department. The Holmes County Building Department at 107 E. Virginia Ave. handles permitting, and planning services are provided through Alday-Howell Engineering.
Do I need a permit to install solar panels in Holmes County?
Yes. Photovoltaic installations in Holmes County are permitted under a dedicated solar record type reviewed on both a structural and an electrical track. Solar thermal — passive water and pool heating — is a separate record. Under Fla. Stat. §163.04 a homeowners' association cannot ban solar panels, though it can decide where on the roof they go if that does not reduce their performance; HOA review is separate from the building permit. Utility interconnection and Permission to Operate run in parallel with the permit, not inside it.
Inspections are where schedules slip.
Get a free quote →Does a roof replacement require a permit in Holmes County?
Yes. A roof covering replacement almost always requires a permit in Florida, including Holmes County. Products must carry a current Florida Product Approval or Miami-Dade Notice of Acceptance rated for the wind speed at the project address, and inspections usually run deck nailing, then dry-in, then final. Some minor repairs fall below the permit threshold, and a small single-family job under $7,500 can qualify for the written-request exemption under F.S. 553.79(1)(g), so ask the department first.
What is the difference between a residential and a commercial permit in Holmes County?
Residential work is generally a single-discipline review filed as a master permit with trades filed against it. Commercial work in Holmes County runs concurrent review across building, fire, and zoning, requires signed and sealed plans for every affected discipline, and can carry impact and concurrency fees on top of permit fees. Change of use adds accessibility and life-safety review.
Do trade permits need to be pulled separately in Holmes County?
Yes in most cases. Electrical, plumbing, and mechanical work is permitted separately by the licensed contractor for each trade and filed against the master building permit. Each trade permit carries its own fee and its own inspection sequence.
What happens if I file under the wrong permit type in Holmes County?
The application is rejected rather than corrected. the Holmes County Building Department closes the record, the filing is resubmitted under the correct record type, and the review clock restarts from zero. Confirming the record type before filing is the cheapest step in the entire process.
Can I apply for all Holmes permit types online?
Most record types are filed through counter intake at the BOCC office in Bonifay, but availability varies by permit type and by applicant. Florida law requires building departments to accept completed applications electronically, but owner-builders must still appear in person to sign (F.S. 489.103(7)).
Simplify Holmes County permitting with Alliance Permitting
Holmes County's truss-at-application rule, multi-agency prerequisites, and double-fee penalty punish incomplete first submissions. Alliance Permitting is a permit expediter for Holmes County and sequences the septic, E-911, FDOT, and county steps and files a package that passes the first time.
Trusted by leading builders and brands - including Dream Finders Homes, Tesla, Verizon, Hyatt, and Sunnova.
Contractors and builders choose Alliance for Holmes County because we deliver:
- Local expertise - we know the Holmes County Building Department and the In person (BOCC office, Bonifay) process.
- Complete oversight - track every permit and inspection across all your jobs in one place.
- Complete submissions - AI pre-checks plus expert review catch issues before they become correction cycles.
Alliance Permitting is a permit documentation and submission company: we prepare your paperwork, file it correctly, and coordinate with the building department through issuance - including preparing private-provider documentation where that option is available. We are not a contractor and do not perform licensed plan review or inspections; that work stays with your team and the jurisdiction.
Ready to break ground in Holmes County sooner?
Let Alliance prepare, file, and track your Holmes County permits while you stay focused on building. Get a free, no-obligation quote today.
More Florida permitting guides
This guide is provided by Alliance Permitting for general informational purposes and reflects publicly available information believed accurate as of July 2026. Permit requirements, fees, and processes change; always confirm current details with the Holmes County Building Department before filing. This is not legal advice.