City of Orlando Building & Trade Permit Guide

How to get a building permit in the City of Orlando, FL — requirements, the published fee formulas, the Orlando Digital Permits and ProjectDox process, private provider options, trade permits, and inspections inside city limits. 2026 guide.

Jurisdiction: Orlando Permitting ServicesCode: Florida Building Code, 8th Ed. (2023)Portal: Digital Permits + ProjectDox
Authority
Orlando Permitting Services
Inside city limits only
Apply Online
Digital Permits + ProjectDox
Electronic plan review
Inspections
Online scheduling
Portal request + on-site
Code
FBC, 8th Ed. (2023)
+ local amendments

Building permits inside Orlando city limits are issued by the Permitting Services Division (Economic Development Department). Orlando runs a fully digital process — applications through the Orlando Digital Permits portal, plan review through ProjectDox, and a Permit Lookup tool for fees, inspections, and status — with one of the busiest permit counters in Florida.

Applies inside City of Orlando limits only. Surrounding unincorporated areas permit through Orange County's Fast Track system — check the parcel's jurisdiction first.

📍 Private providers thrive here. Under F.S. 553.791 you can hire a licensed private provider for plan review and inspections instead of the city — a popular route on Orlando commercial work, with a formal city process for electing it.

What requires a building permit in the City of Orlando?

Under the Florida Building Code (§105.1), a permit is required before you construct, enlarge, alter, repair, move, demolish, or change the occupancy of most structures and systems. New for 2026: Florida HB 803 (effective July 1, 2026) created additional building-permit exemptions for certain single-family residential work. Ask the permit counter whether your scope qualifies before assuming a permit is needed.

Permit required

  • New residential, multifamily, and commercial construction
  • Additions, garages, sheds, and porches
  • Structural alterations, interior build-outs, and demolition
  • Roof replacements and window / door replacements
  • Electrical service changes and most wiring work
  • Mechanical / HVAC installations and changeouts
  • Plumbing, gas, and irrigation work
  • Signs, pools, and screen enclosures

Usually exempt

  • Painting, flooring, cabinets, and cosmetic finishes
  • Like-for-like minor repairs that don't alter systems
  • Routine maintenance that doesn't extend or reroute systems
  • Certain minor single-family work newly exempted by HB 803 (verify)
Exemptions are narrow and local. Always verify with the permit counter before starting work - unpermitted work risks stop-work orders, doubled fees, and closing/insurance problems.

Who handles permitting in the City of Orlando?

All permitting is administered by the City of Orlando Permitting Services Division through the Orlando Digital Permits (ProjectDox plan review system).

  • Address: Orlando City Hall, 400 S. Orange Avenue, Orlando, FL 32801
  • Phone: (407) 246-2271

City of Orlando permit types

A building permit is one record among many. the Orlando Permitting Services Division issues work under separate record types, and filing under the wrong one is a rejection, not a correction — the application is closed and refiled, and the review clock restarts.

Residential permit types

Residential permit types in City of Orlando
Permit typeWhat triggers itReview pathFee basis
New constructionNew dwellings, additions, and accessory structures over the exempt thresholdFull plan review (structural, energy, zoning)Valuation-based
Renovation / alterationStructural or load-bearing changes, layout changes, substantial repairPlan review scaled to scopeValuation-based
ReroofRoof covering replacement and most major roof repairProduct approval review; dry-in and nail-off inspectionsValuation or squares
Solar photovoltaicRooftop or ground-mount PV installation or replacementStructural plus electrical reviewFlat or system-size based
Solar thermalPassive water heating or pool heating systemsPlumbing and structural reviewFlat or per-permit minimum
ElectricalService changes, panel upgrades, new circuits, most wiring alterationsTrade review; filed against the building permitPer-permit minimum or per-device
PlumbingNew piping, repipes, water heaters, fixtures, gas pipingTrade review; filed against the building permitPer-permit minimum or per-fixture
Mechanical / HVACChangeouts that are not like-for-like, ductwork, refrigerationTrade review; filed against the building permitPer-permit minimum or per-unit
Windows and doorsReplacement units and opening protectionProduct approval review for wind-borne debrisValuation or per-opening
Pool and spaIn-ground and above-ground pools, spas, barrier and enclosure workPlan review plus barrier and electrical bondingValuation-based
Fence and accessoryFences, sheds, decks, and carports over the exempt thresholdZoning plus structural where applicableFlat or valuation-based
DemolitionFull or partial demolition of a structureUtility disconnect verification requiredFlat

Commercial permit types

Commercial permit types in City of Orlando
Permit typeWhat triggers itReview pathFee basis
New constructionGround-up commercial, industrial, and multifamilyFull multi-discipline plan reviewValuation-based
Tenant improvementInterior build-outs and suite fit-upsPlan review across affected disciplinesValuation-based
Renovation / alterationStructural, envelope, or system changes to an existing buildingPlan review scaled to scopeValuation-based
Change of useConverting a building from one occupancy classification to anotherZoning, life-safety, and accessibility reviewValuation or flat
ReroofCommercial roof covering replacementProduct approval review plus fire review where applicableValuation or squares
Solar photovoltaicCommercial rooftop, carport, and ground-mount PVStructural, electrical, and often fire reviewValuation or system-size based
ElectricalService, distribution, and branch circuit workTrade reviewValuation or per-device
PlumbingSupply, waste, vent, and gas systemsTrade reviewValuation or per-fixture
Mechanical / HVACRooftop units, ductwork, exhaust, and refrigerationTrade reviewValuation or per-unit
Fire protectionSprinkler, standpipe, alarm, and suppression systemsFire prevention plan reviewValuation or per-device
SignWall, monument, and illuminated signageZoning plus electrical where illuminatedFlat or per-sign
DemolitionFull or partial commercial demolitionUtility disconnect and environmental clearanceFlat or valuation-based

Residential

  • Single-discipline review in most cases
  • Master permit with trades filed against it
  • Owner-builder route exists but carries statutory affidavits
  • Product approval drives roofing and opening protection

Commercial — multi-discipline

  • Concurrent review across building, fire, and zoning
  • Signed and sealed plans across every affected discipline
  • Accessibility and life-safety review attach to change of use
  • Impact and concurrency fees can apply on top of permit fees

Solar permits in City of Orlando

Solar is permitted as its own record type in most Florida jurisdictions rather than rolled into a general building permit, and residential and commercial photovoltaic are usually separate records with different document sets. Solar thermal — passive water and pool heating — is a third, distinct record.

A photovoltaic submittal is reviewed on two tracks at once: structural (roof load path, attachment spacing, uplift) and electrical (conductor sizing, rapid shutdown, point of interconnection). A single-line diagram and a signed and sealed structural attachment detail are the two attachments most often missing on a first submittal.

Under Fla. Stat. §163.04, a homeowners' association cannot prohibit a solar collector on a dwelling — HOA architectural approval is not a prerequisite to permit issuance, though it may still be a contractual matter between owner and association.

Utility interconnection runs parallel to the building permit, not inside it. Permission to Operate is issued by the utility after the final electrical inspection clears.

Roofing permits in City of Orlando

A roof covering replacement requires a permit in every Florida jurisdiction. Repairs below the local threshold may not, but the threshold is scope-specific and confirming it with the building department before tear-off is cheaper than an after-the-fact permit.

Every roof product must carry a current Florida Product Approval or Miami-Dade Notice of Acceptance rated for the wind speed at the project address. A product approval number that has lapsed or is rated below the site wind speed is the single most common reroof rejection.

Reroof inspections are sequenced: dry-in after the underlayment, nail-off on the sheathing fastening, and final. Covering the deck before the dry-in inspection means tearing it back open.

Hurricane mitigation retrofit requirements can attach when an existing roof is replaced, including secondary water barrier and roof-to-wall connection work. These add scope and documents, and they are triggered by the replacement itself.

Under Fla. Stat. §553.7922, jurisdictions run expedited procedures for permits that need no technical review — reroofs, roof repairs, and similar — during a declared state of emergency.

Record types, document sets, and fee structures are set by the Orlando Permitting Services Division and change without notice. Confirm the current record type against the building department before filing.

the City of Orlando building permit cost

Orlando calculates permit fees from project valuation using published formulas, with percentage surcharges. Representative rows from the city's published commercial fee schedule:

Published fee formulas and surcharges (city schedule)

ItemHow it's calculated
Commercial plumbing / gas permit$64.94 first $1,000 of cost + $10.81 per add'l $1,000 to $25,000; $8.12 per $1,000 above $25,001
Commercial application fee25% of the initial estimated permit fee — non-refundable, credited to the final fee
Technology surcharge3% of the permit fee
Administrative inspection fund1.5% of the permit fee ($2 minimum)
DCA operational trust fund surcharge1% of the permit fee ($2 minimum)
Inspection cancellation (≤24 hrs notice)$50
Refund policyCity retains 25% of the permit fee or the minimum fee, whichever is greater
Residential and other trade formulas follow the same valuation-based structure — pull the current schedules from the Permitting Services fee pages before budgeting, as rates are updated periodically.

the City of Orlando trade permits

Electrical permits

Required for service installations, panel upgrades, solar PV, and most wiring alterations in the City of Orlando, filed by a licensed electrical contractor against the master building permit in Orlando Digital Permits.

Plumbing permits

Required for new plumbing, repipes, water heater changeouts, fixture relocations, and gas piping; fees follow the local schedule with per-permit minimums.

Mechanical (HVAC) permits

Required for HVAC installations and changeouts, ductwork, and refrigeration; specialized systems are permitted and inspected separately.

Miscellaneous & specialty

Roofs, pools and spas, screen enclosures, and demolition are permitted separately. Exterior components need current Florida Product Approval rated for the local wind speed.

How to get a building permit in the City of Orlando

Confirm scope & jurisdiction

Verify the work needs a permit and that the parcel is inside Orlando city limits rather than unincorporated Orange County.

Prepare your documents

Assemble the application, valuation details, signed and sealed plans, energy calcs, and product approvals; commercial applicants pay the 25% non-refundable application fee before digital plan submission.

Apply through Orlando Digital Permits

Submit online; the city emails a ProjectDox link for uploading digital plans once the application is processed.

Plan review & corrections

Reviews route through ProjectDox; upload corrections promptly — or elect a licensed private provider under F.S. 553.791 for plan review and inspections.

Pay fees & pull the permit

Pay the valuation-based fees and surcharges, print the permit, and for work over $5,000 file the Notice of Commencement with the Orange County Comptroller first, then with the city, and post it on site.

Inspections through close-out

Schedule inspections through the Permit Lookup tool as phases complete; request the CO (new construction / change of use) or Certificate of Completion by email at the end.

Inspections in the City of Orlando

Schedule and track inspections through the city's Permit Lookup tool; cancel with more than 24 hours' notice to avoid the $50 fee. Typical checkpoints include foundation, rough MEP trades, framing, insulation, and final, with the CO or Certificate of Completion issued on request after passage.

Official the City of Orlando permitting resources

Frequently asked questions

How much is a building permit in Orlando?

Fees are valuation-based under published city formulas — for example, commercial plumbing/gas runs $64.94 for the first $1,000 of cost plus $10.81 per additional $1,000 up to $25,000 — plus a 3% technology surcharge, 1.5% administrative inspection fund, and 1% DCA surcharge. Commercial applicants also pay a 25% application fee credited to the final permit.

What is ProjectDox?

Orlando's digital plan review system. After your application is processed, the city emails a ProjectDox link where you upload plans, track review comments, and submit corrections — no paper sets.

Can I use a private provider in Orlando?

Yes. Under F.S. 553.791 you can hire a licensed private provider for plan review and inspections instead of the city, using Orlando's formal election process — a common way to compress commercial timelines.

Where do I file the Notice of Commencement?

For work over $5,000, file with the Orange County Comptroller's Office first, then provide it to the City of Orlando, and post it at the jobsite before the first inspection.

How long is an Orlando permit valid?

Under the Florida Building Code, a permit generally expires if work does not start within 180 days of issuance (or stalls for 180 days); each passed inspection typically extends it. Extensions are requested through the department.

Do I need a permit to install solar panels in City of Orlando?

Yes. Photovoltaic installations in City of Orlando are permitted under a dedicated solar record type reviewed on both a structural and an electrical track. Solar thermal — passive water and pool heating — is a separate record. Under Fla. Stat. §163.04 a homeowners' association cannot prohibit a solar collector, so HOA approval is not a prerequisite to permit issuance. Utility interconnection and Permission to Operate run in parallel with the permit, not inside it.

Does a roof replacement require a permit in City of Orlando?

Yes. A roof covering replacement requires a permit in every Florida jurisdiction, including City of Orlando. Products must carry a current Florida Product Approval or Miami-Dade Notice of Acceptance rated for the wind speed at the project address, and inspections are sequenced — dry-in, nail-off, then final. Some minor repairs fall below the permit threshold, but the threshold is scope-specific.

What is the difference between a residential and a commercial permit in City of Orlando?

Residential work is generally a single-discipline review filed as a master permit with trades filed against it. Commercial work in City of Orlando runs concurrent review across building, fire, and zoning, requires signed and sealed plans for every affected discipline, and can carry impact and concurrency fees on top of permit fees. Change of use adds accessibility and life-safety review.

Do trade permits need to be pulled separately in City of Orlando?

Yes in most cases. Electrical, plumbing, and mechanical work is permitted separately by the licensed contractor for each trade and filed against the master building permit. Each trade permit carries its own fee and its own inspection sequence.

What happens if I file under the wrong permit type in City of Orlando?

The application is rejected rather than corrected. the Orlando Permitting Services Division closes the record, the filing is resubmitted under the correct record type, and the review clock restarts from zero. Confirming the record type before filing is the cheapest step in the entire process.

Can I apply for all Orlando permit types online?

Most record types are filed through Orlando Digital Permits, but availability varies by permit type and by applicant. Some records still require in-person submittal, and owner-builder filings are frequently restricted to counter submittal regardless of record type.

Simplify the City of Orlando permitting with Alliance Permitting

Valuation formulas, ProjectDox routing, and the two-step NOC filing make Orlando a city where clean packages move and messy ones stall. Alliance Permitting is a permit expediter for the City of Orlando — we prepare your submission, file it through Orlando Digital Permits, and manage review through issuance, with private-provider documentation prepared where that route fits.

250K+Permits approved
All 50States covered
AI + HumanExpert filing
Done-for-youWe file, you build

Trusted by leading builders and brands - including Dream Finders Homes, Tesla, Verizon, Hyatt, and Sunnova.

Contractors and builders choose Alliance for the City of Orlando because we deliver:

  • Local expertise - we know City of Orlando Permitting Services Division and the Orlando Digital Permits process.
  • Complete oversight - track every permit and inspection across all your jobs in one place.
  • Error-free submissions - AI pre-checks plus expert review catch issues before they become correction cycles.

Alliance Permitting is a permit documentation and submission company: we prepare your paperwork, file it correctly, and coordinate with the building department through issuance - including preparing private-provider documentation where that option is available. We are not a contractor and do not perform licensed plan review or inspections; that work stays with your team and the jurisdiction.

Ready to break ground in the City of Orlando sooner?

Let Alliance prepare, file, and track your Orlando permits while you stay focused on building. Get a free, no-obligation quote today.

This guide is provided by Alliance Permitting for general informational purposes and reflects publicly available information believed accurate as of July 2026. Permit requirements, fees, codes, portals, and review timelines change; always confirm current details with the local permit authority before filing.