Siskiyou County, California Building Permit Guide

To get a building permit in Siskiyou County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Siskiyou County’s Building Division in Yreka permits construction in the unincorporated county and in its partner cities of Fort Jones, Etna and Montague, with an average 4 to 6 weeks of review for complete plans.

Authority: Siskiyou County Building DivisionInspections: 530-842-8270Phone: 530-841-2100
Authority
County Building Division806 South Main Street, Yreka
Review time
4–6 weeksAfter 2–3 weeks of agency routing
Snow load
40 or 60 psf flat roofMinimum; Hazard Tool if higher
Inspections
530-842-8270Or the online request form

In unincorporated Siskiyou County, building permits come from the Building Division of the Community Development Department, 806 South Main Street, Yreka (530-841-2100), led by Deputy Director Glenn Shockency. The division also handles permits for its partner cities of Fort Jones, Etna and Montague, which do their own planning and related reviews. Applications are routed to other agencies for two to three weeks, and complete plan submittals then take about 4 to 6 weeks to review.

What requires a building permit in Siskiyou County?

The county requires a permit for new construction, additions, remodeling and repairs to electrical, mechanical and plumbing systems, and lists common examples. It also publishes the work that is exempt, but notes that the exemptions do not apply in a design review or preservation district or to a historic landmark.

Permit required

  • New homes and buildings, room additions and garage conversions
  • Demolition, enclosures and carports
  • Decks and patio covers
  • Structures over 120 square feet of footprint
  • Retaining walls over 4 feet and fences over 6 feet
  • Re-roofing, skylights, fireplaces and inserts
  • Water heaters, ceiling fans, landscape irrigation and shower or tub enclosure replacements
  • Swimming pools and spas

Exempt

  • One-story detached accessory structures up to 120 square feet of footprint, with no electrical, plumbing or mechanical work
  • Fences up to 6 feet, subject to Planning approval
  • Retaining walls up to 4 feet from the bottom of the footing, unless holding a surcharge
  • Water tanks on grade up to 5,000 gallons
  • Sidewalks and driveways (other county approvals may apply)
  • Painting, flooring, cabinets and countertops
  • Prefabricated pools under 24 inches deep
  • Unattached decks up to 200 square feet and 30 inches above grade that do not serve the required exit door

Agricultural buildings can qualify for an agricultural exemption, applied for on the county’s agricultural exempt building permit application. Siskiyou County does not issue grading permits, but site grading must be shown on the building plot plan, and the county does not allow a building site to be pre-graded before the construction plans are approved.

What Siskiyou County decides and what the state holds

The county sets its own design criteria for an area that runs from 1,000 to 14,152 feet in elevation. Flat roofs must carry at least 60 pounds per square foot of snow in McCloud, Mount Shasta, Dunsmuir, Weed and Happy Camp and 40 elsewhere, based on the county’s 1993 snow load case study; where the ASCE 7 Hazard Tool gives a higher value for the site, the engineer must use it. Because the code’s snow loads exceed the limit for conventional light-frame construction, that method cannot be used in the county, and every project needs plans sealed and signed by a California-licensed design professional. The basic wind design is 95 mph, Exposure C, for most structures below 5,000 feet; roof loads above 5,000 feet come from the Building Division. Contractor licensing is a state matter.

Short on time to read all of this?

Get a free quote →

Siskiyou County building department: who handles permitting

The Building Division serves the unincorporated county. It routes each application to county departments and to the partner cities of Fort Jones, Etna and Montague for their approval signatures; in those three cities, the city carries out the reviews the county departments do elsewhere. The county’s building pages name no arrangement for the other six cities, so property owners there should contact their city. To check whether a parcel is inside a city, use the Assessor’s online parcel maps or the county GIS.

Building permits by area in Siskiyou County
AreaBuilding permits
Unincorporated Siskiyou CountySiskiyou County Building Division, Yreka
Fort Jones, Etna, MontagueCounty Building Division; as a partner city, the city does the reviews county departments do elsewhere and signs off
Yreka, Mount Shasta, Weed, Dunsmuir, Dorris, TulelakeNot listed as partner cities on the county’s building pages; contact the city
County offices for building projects
OfficeContact
Building Division806 South Main Street, Yreka, CA 96097; 530-841-2100; fax 530-841-4076; BuildingPermitTech@co.siskiyou.ca.us; Monday to Thursday 8 a.m. to 5 p.m. (closed noon to 1), Friday by appointment
Inspection requests530-842-8270 or the online request form
Planning and Environmental Health (septic, wells)806 South Main Street, Yreka; 530-841-2100
Floodplain Administrator530-842-8265
Public Works Road Division (county road encroachments)1312 Fairlane Road, Yreka
CAL FIRE Siskiyou Unit (fire-safe review)1809 Fairlane Road, Yreka; 530-842-3516
Assessor (ownership check)Courthouse, 311 4th Street, Yreka

Siskiyou County permit types

Applications are made on paper for now: the county posts a fillable permit application (the form is marked Rev. 2025) to download, print and sign, and says permits will be available online in the future. The application names the permit holder of record, the water source and sewage disposal, whether the parcel was created before 1991, and the sign-offs needed from the Assessor, Planning, Environmental Health, Road, Fire, Flood and any service district. The description of work must match the construction documents, or the application will not be reviewed.

Residential permits

  • New homes need plans prepared, signed and stamped by a licensed architect or engineer, in two identical sets for homes of up to four units or two stories; accessory and agricultural structures also take two sets.
  • Pre-approved plans: the county offers seven free home designs, from an efficiency studio to a three-bedroom, 2.5-bath house, in Craftsman, Farmhouse and Modern styles. Since the 2025 codes took effect, they can be used only where the ASCE 7 ground snow load is 100 pounds per square foot or less for risk category II. They save design and plan check costs, but inspection permit fees still apply.
  • Fire sprinklers: new dwellings need NFPA 13D sprinkler drawings by a licensed C-16 contractor; an ADU needs them if the existing home has sprinklers.
  • Manufactured homes use the county’s foundation requirements, tie-down certification, data sheet and state forms 433A and 433B.
  • Unpermitted ADUs built before January 1, 2020 can be legalized through the county’s ADU amnesty program, ending with a certificate of compliance.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

Multifamily buildings of five or more units and commercial or assembly buildings for fewer than 50 people need three plan sets; commercial buildings with hazardous materials and assembly buildings for 50 or more need four. All must be prepared and stamped by a licensed person.

What comes before the building permit

  • CAL FIRE: before a new home, standalone ADU, manufactured home, commercial or industrial project, check with the CAL FIRE Siskiyou Unit that the site meets fire response rules; projects in state responsibility areas are routed to CAL FIRE for the 4290 and 4291 fire-safe rules.
  • Floodplain: a flood zone determination is required before a building permit application is accepted, and any development in a special flood hazard area needs a separate floodplain development permit first ($525).
  • Planning: the plot plan is checked for setbacks and zoning, and use permits or variances come first where needed.
  • Septic and wells: Environmental Health reviews the plot plan for wells and sewage disposal; pre-approved plan users book a septic site review with its land use inspector.
  • Roads: private roads connecting to county roads need a Road Division encroachment permit; state highway connections need a Caltrans permit.

Siskiyou County building permit fees

The county does not publish a flat building fee table. It computes building permit fees from the fee tables in the 1997 Uniform Administrative Code, under Section 9-1.07 of the county code, applied to a valuation worked out from the International Code Council’s Building Valuation Data or from actual construction cost. Since March 1, 2025 the county uses the most current ICC valuation table each year, and it posts the February 2026 and August 2026 tables. From January 1, 2026 the basic permit portion of the fee was set to rise by an amount the county says stays within the limits set by code.

School districts charge development fees on new construction: the Building Division completes the district forms at plan check, and the fees are paid directly to the school district before the permit is issued. Pre-approved plans avoid design and plan check costs, though inspection fees still apply.

Rather talk it over?

Call 1-855-478-4290 →
Selected planning fees (2025 adopted schedule)
ItemFee
Flood damage development permit$525
Use permit: administrative / Planning Commission$525 / $950
Use permit: ministerial second unit / non-exempt home occupation$100 / $250
Variance: administrative / Planning Commission$525 / $725
Boundary line adjustment or certificate of compliance$550, plus $50 per lot over 2
Erosion control or grading plan review$100
Sign$150
Zone change: minor / major$1,175 / $1,800
Tentative parcel map, minor$975
Plan sets required by project (county guidelines)
ProjectPlan sets
Residential up to 4 units or 2 stories; accessory or agricultural structures2
Multifamily, 5 or more units; commercial or assembly under 50 people3
Commercial with hazardous materials; assembly of 50 or more4

Environmental Health charges its own fees for septic site inspections and well permits under its posted fee schedule, and Public Works and Caltrans set their own encroachment fees. Ask the Building Division at 530-841-2100 for a valuation-based estimate before you apply.

Trade permits and who may pull them in Siskiyou County

Electrical, mechanical and plumbing work is permitted by the Building Division, either as part of a building permit or on its own; water heaters, ceiling fans and landscape irrigation all need permits. Plans must include an electrical plan and specifications for all electrical equipment, though calculations and diagrams are not needed for residential services of 200 amps or less, and a plumbing plan for sewer, drains, water, gas and fixtures. Solar systems need engineered design drawings when they go with the pre-approved plans, and fire sprinkler systems need a licensed C-16 contractor.

The permit is issued in the name of the licensed contractor or the property owner as permit holder of record. Contractors sign the licensed contractor’s declaration; owners sign the owner-builder declaration, and the county posts an owner-builder handout and a notice on Assembly Bill 2335 to read before pulling a permit. A permit cannot be transferred: if the holder no longer has an interest in the property or the work, the permit becomes void, work must stop, and a new permit is needed.

Rather not deal with the Siskiyou County building department?

Get a free quote →

How to apply for a Siskiyou County building permit

1. Confirm the parcel and fire access

Check the parcel on the Assessor’s maps, and for a new home or ADU, check fire response rules with CAL FIRE Siskiyou Unit (530-842-3516).

2. Get the flood zone determination

Use FEMA’s map service or ask Community Development; in a special flood hazard area, get the floodplain development permit first.

3. Prepare stamped plans

Design to the county snow and wind criteria and show site grading, the well and septic area, the driveway and true north on the plot plan.

4. Complete the application

Download the fillable application, print and sign it, and attach the owner-builder or contractor declaration and any agency approvals you already have.

5. Submit to the Building Division

Bring the application and plan sets to 806 South Main Street, Yreka; the division routes them to the Assessor, Planning, Environmental Health, Roads, CAL FIRE and partner cities.

6. Pay school fees and collect the permit

Pay the district school fees directly, then collect the permit once plan review is approved.

Review, corrections and what causes delay

Agency routing takes two to three weeks, and complete plan packages with all agency approvals are then checked in the order they are deemed complete, averaging 4 to 6 weeks. Applicants may instead collect the agency approval signatures themselves before submitting. Applications whose work description does not match the plans are not reviewed, and plans must be on uniform sheets of at least 18 by 24 inches; the county asks applicants to avoid added ink or pencil changes. If you plan to live in an RV or trailer while building, apply for a camping permit with the building permit; the RV must be removed at the final inspection.

Siskiyou County building inspections

Call the inspection request line, 530-842-8270, or use the county’s online building inspection request form. The county’s required inspections, as a guideline, are foundation (trenches, steel in place, forms set and before grouting masonry), concrete slab or underfloor before concrete or floor sheathing, framing (including fire-blocking, bracing, rough electrical, piping, chimneys, vents, roofing, ducts and glazing), insulation, lath or wallboard before plastering or taping, and final after finish grading and completion.

In flood zones, an elevation certificate from a licensed surveyor, engineer or architect may be required for new construction and substantial improvements. ADU amnesty projects end with a final inspection and a certificate of compliance from the Building Division.

California building code in Siskiyou County

Since January 1, 2026 Siskiyou County enforces the 2025 California Building Standards Code, together with the 1997 editions of the Uniform Housing Code, the Uniform Code for the Abatement of Dangerous Buildings, the Uniform Administrative Code and the Uniform Sign Code. Its snow load case study, approved under the building code’s ground snow load section, sets the local minimums. FEMA’s Community Status Book lists Siskiyou County’s unincorporated area (community 060362) as participating in the National Flood Insurance Program, with flood maps effective December 11, 2025; flood rules are in Title 10, Chapter 10 of the county code.

Want this handled start to finish?

Get a free quote →

California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments

Siskiyou County permit search and official resources

For the status of a permit or copies of permit records, contact the Building Division at 530-841-2100 or BuildingPermitTech@co.siskiyou.ca.us. The county also posts an affidavit for release of architectural or engineering plans, used when stamped drawings from an earlier permit are reused.

Inspections are where schedules slip.

Get a free quote →

Siskiyou County building permit FAQs

Who issues building permits in Siskiyou County?

The county Building Division in Yreka for unincorporated land and for the partner cities of Fort Jones, Etna and Montague; owners in the other six cities should contact their city.

How long does plan review take?

Agency routing takes two to three weeks, and accepted complete submittals average 4 to 6 weeks of plan review.

How are building permit fees calculated?

From the 1997 Uniform Administrative Code fee tables applied to a valuation based on current ICC Building Valuation Data or actual cost; school fees are paid separately to the district.

What snow load must I design for?

At least 60 psf flat roof snow load in McCloud, Mount Shasta, Dunsmuir, Weed and Happy Camp and 40 psf elsewhere, or the ASCE 7 Hazard Tool value if higher.

Do I need a grading permit?

No. The county issues no grading permits, but grading must be shown on the plot plan and the site may not be graded before the plans are approved.

Are there free house plans?

Yes. The county’s pre-approved plans are free apart from printing, where the site’s ground snow load is 100 psf or less.

How do I request an inspection?

Call 530-842-8270 or use the online inspection request form.

Simplify Siskiyou County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Siskiyou County sooner?

Let Alliance prepare, file, and track your Siskiyou County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Siskiyou County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.