Inside the City of Soledad, building permits are issued by the Building & Safety Division of the Community & Economic Development Department at City Hall, 248 Main Street ((831) 223-5041, building.permits@cityofsoledad.gov). The city contracts with 4Leaf for its Building Official. All building and planning applications are filed in the SmartGov portal, but permit fees can only be paid in person. Under the city’s adopted FY 2026-27 Master Fee Schedule the building permit fee comes from a valuation table (Table 3A), plan check is 65% of the permit fee, and a certificate of occupancy costs $307.
What requires a building permit in Soledad?
The city puts the duty on the property owner: before a building is built or altered, the owner must get a building permit, and the plans are reviewed against city and state construction codes before the permit is issued. Soledad’s building permit application lists the kinds of work the division permits, and its pre-application checklists add several common jobs.
Residential work
- New single-family houses, additions and remodels
- ADUs and junior ADUs
- Re-roofs and solar systems
- Electric heat pumps and heat pump water heaters
- Residential window replacement
- Electric vehicle chargers
- Swimming pools
- Demolition
Commercial work
- New commercial structures
- Tenant improvements
- Fire sprinklers and alarms
- Signs
- Grading, priced by the city’s contract consultant
- A certificate of occupancy for every business, and for changes of use, tenant or owner
The city does not post a list of work that is exempt from permits, so ask Building & Safety before starting a small job. Work started without a permit triggers an investigation billed at the consultant’s actual cost plus a 10% city administration fee.
What Soledad decides and what the state holds
The city sets its own fees, zoning, architectural review and density bonus rules (Soledad Municipal Code chapter 17.39), and the Building & Safety pages cover its electric vehicle charging ordinance and the Model Water Efficient Landscape Ordinance. Its Architectural Review Committee approves the design of larger projects. Contractor licensing is a state matter, and the application carries the state’s licensed-contractor, owner-builder and workers’ compensation declarations.
Soledad building department: who handles permitting
The Building & Safety Division of the Community & Economic Development Department issues building permits and inspects work inside the city limits; the city contracts with the firm 4Leaf for its Building Official, and its inspectors are certified. The same department’s Planning Division handles zoning and architectural review, and Public Works handles encroachment permits and other right-of-way matters. Areas outside the city limits are unincorporated Monterey County, where the county’s Housing and Community Development department issues permits (see the Monterey County guide).
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Building & Safety | City Hall, 248 Main Street, Soledad, CA 93960; (831) 223-5041; building.permits@cityofsoledad.gov |
| Office hours | Monday to Friday, 8 a.m. to 5 p.m. |
| City Hall main line | (831) 223-5000; business licenses option 5 |
| Planning Division | (831) 223-5020 |
| Public Works (encroachment permits) | (831) 223-5176 |
| Mobile home park inspections | State Department of Housing and Community Development, (916) 255-2501 |
| Online | SmartGov portal: applications, documents, inspection requests and results |
Inspections in the city’s five mobile home parks (Santa Elena, Nielsen’s Trailer Park, Soledad Motor Lodge and Trailer Park, Greenleaf Estates and Almond Acres) are done by the State of California, not the city.
Soledad permit types
All building and planning applications go through SmartGov. A main applicant signs up and creates an account; when more than one applicant or professional works on a project, the others request an access code by email with the building permit number. After an application is processed, SmartGov emails the applicant either the changes needed or the total fees due. Rooftop solar can instead go through the SolarAPP+ portal, which the city now accepts.
Residential permits
- Who signs. The applicant certifies being a California-licensed contractor, the property owner (with a separate verification form) or someone authorized by the owner (with a separate authorization form).
- Owner-builders choose between doing the work themselves or with their own employees, or contracting only with licensed contractors, and acknowledge that, apart from a personal residence lived in for at least a year before completion, an owner-built structure cannot legally be sold unless licensed contractors built all of it.
- Checklists. The division posts pre-application checklists for electric heat pumps, heat pump water heaters, EV chargers, residential window replacement and demolition, plus a smoke alarm affidavit.
- ADUs and junior ADUs are marked as their own project type on the application, and the division has an ADU page.
Building or remodeling a home here? Alliance handles home building permits, so the crew isn't waiting on the counter.
Commercial permits
New commercial buildings, tenant improvements, signs and fire sprinkler or alarm work use the same application. A business needs both a certificate of occupancy ($307) and a city business license to operate. The certificate of occupancy application must be completed within 180 days or it expires; it needs Planning, Building and Fire sign-off for a change of use, tenant or owner, and Health Department sign-off when a change of use involves food. A temporary certificate of occupancy has its own 2026 application.
For tenant improvements and new commercial builds, Alliance handles commercial permit filing through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Planning approvals first. Staff may refer you to Planning, and required planning approvals must be granted before a building permit application is accepted. Approval can come from staff, the Architectural Review Committee, the Planning Commission or the City Council, and planning fees are separate from building fees.
- Site plan and architectural review. Conditionally allowed uses, multifamily projects over the city’s threshold, new or expanded non-residential buildings and planned development projects need a site plan and architectural review permit; ARC review of a new building up to 15,000 sq ft is $1,229.45.
- Other agencies. Staff may also send you to Public Works, the Fire Department or the Monterey County Health Department to find any special requirements.
- Density bonus. Housing developments of five or more units can request a density bonus under Municipal Code chapter 17.39.
- Street work. Encroachment permits come from Public Works.
Soledad permit costs and fees
Soledad’s fees are in the Adopted Master Fee Schedule for FY 2026-27, posted on the Finance Department page. Building permit and trade permit fees come from Table 3A, which works from the project’s valuation; plan check is charged by the city’s contract consultant at 65% of the permit fee. The document is titled “Adopted Master Fee Schedule FY 2026-27”, but its Table 3A page is headed “All New Construction - PROPOSED, FY 26/27”, so ask Building & Safety which rates apply before you budget. Permit fees can only be paid in person, by cash, check or credit card.
| Valuation | Base fee | Plus |
|---|---|---|
| $1 to $500 | $96.89 | – |
| $501 to $2,000 | $96.89 | $4.55 per $100 |
| $2,001 to $25,000 | $103.22 | $20.87 per $1,000 |
| $25,001 to $50,000 | $583.92 | $15.05 per $1,000 |
| $50,001 to $100,000 | $959.54 | $10.43 per $1,000 |
| $100,001 to $500,000 | $1,481.23 | $8.35 per $1,000 |
| $500,001 to $1,000,000 | $4,820.05 | $7.08 per $1,000 |
| Over $1,000,000 | $8,360.10 | $5.44 per $1,000 |
The first two bands do not join up (the $501 to $2,000 band reaches about $165 at $2,000, while the next band starts at $103.22), so ask Building & Safety for the exact figure on a small job. For new construction, valuation comes from the International Code Council’s square-foot cost table: the schedule prints the February 2026 table (for example $175.92 per sq ft for a type VB one- or two-family house, and $31.50 per sq ft for an unfurnished basement) and says the city would follow the new ICC table released in August 2026; ask which table now applies.
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee |
|---|---|
| Plan check, original | 65% of the permit fee |
| Plan check revisions, grading, reinstatement, work-without-permit investigation | Actual cost plus 10% city administration fee |
| Office automation / document storage / training fees | 1.5% (min. $2) / 1.125% (min. $1) / 0.3% (min. $2) of the permit amount |
| Certificate of occupancy | $307 |
| State green building fee | $1 per $25,000 of valuation |
| Encroachment permit (driveway approach, curb and gutter, sidewalk, street cut, utilities) | $399 minimum (actual cost) plus $1,192 deposit |
| Water or sewer hook-up | Actual cost plus $418 administration fee |
| Planning site plan review, new house, addition, ADU or accessory structure | $181.66 per unit minimum (hourly, actual cost), plus 10% admin fee |
| Zoning compliance check for a new or relocating business | $206.40 |
| Appeal on a single-family house | $492 |
Reinspections, inspections outside business hours and extra plan review for changes are billed at the city’s actual hourly cost plus 10%, and the inspection page warns that fees apply for no-shows, same-day cancellations and failed inspections. Planning plan check fees are non-refundable, and the fee for a site plan and architectural review permit is set at the intake meeting with a planner. The schedule also carries development impact fees for general government, public safety, parks, water, wastewater, storm drains and traffic; ask the division for the amounts on a new unit or building.
Trade permits and who may pull them
Electrical, mechanical and plumbing permits are issued by Building & Safety and priced from the same Table 3A valuation table as building permits; they are filed in SmartGov like any other application. The application’s declarations follow state law: a contractor affirms a current state license by class and number, an owner-builder states the exemption claimed, and every applicant identifies workers’ compensation coverage. The general contractor or owner-builder is responsible for checking that work is complete before asking for an inspection and for coordinating subcontractors on corrections.
- Business license. Building, engineering, plumbing, electrical, roofing and specialty contractors pay Soledad’s business license tax on annual gross receipts from work in the city, from $40 under $100,000 to $500 at $1,000,000 and over; a contractor with no place of business in the city still needs a license for work performed there.
- Timing. Licenses expire each June 30, take 7 to 10 business days to process and are never issued over the counter the same day; send applications to businesslicense@cityofsoledad.gov or bring them to City Hall.
Rather not deal with the building department?
Get a free quote →How to apply for a Soledad building permit
Staff will say whether Planning, Public Works, Fire or County Health must review the project.
File the planning application and pay its separate fees; approval must come before the building application.
Sign up on the portal; extra applicants request an access code by email.
Upload the application, plans and supporting structural, energy or soils documents.
SmartGov emails the changes needed or the total fees due.
Pay at City Hall by cash, check or credit card; the permit then issues.
Begin work within six months and keep it moving to avoid expiration.
Review, corrections and what causes delay
The city’s General Building Permit Information handout (dated October 2010 and still posted) sets plan check goals of 4 weeks for minor projects such as a house or a remodel, 6 weeks for standard commercial, industrial or multifamily projects and 8 weeks for major ones, with rechecks within two weeks. Building & Safety checks the building, plumbing, mechanical, electrical, energy and access codes; Fire checks fire safety; Public Works checks flood control, drainage, driveways and public improvements; and Planning checks use, parking, lot coverage, height, setbacks and density. For site plan and architectural review, an incomplete application gets a notice within 30 days, and the city asks for one folded full-size plan set (never rolled) with reductions, a digital copy, a grading plan where more than 50 cubic yards will be moved and a tree protection plan for work within 20 feet of a tree’s dripline. Permit extensions and reinstatements have their own request form.
Inspections in Soledad
Request inspections at least two days ahead, preferably in SmartGov, or by phone at (831) 223-5041 or by email to building.permits@cityofsoledad.gov, with the permit job card, the inspection code and an on-site contact ready. Cancellations and reschedules need 24 hours’ notice. Inspections run Monday and Friday mornings until 11 a.m. (the page gives a start of 8 or 8:15 a.m.) and Wednesday from 11 a.m. to 2 p.m., never on weekends or holidays. Someone over 18 must be on site, with safe access, the city-stamped approved plans, the permit card and any earlier correction notices.
The usual sequence runs foundation, slab or under-floor, roof sheathing, exterior shear, masonry fireplace, framing, insulation, drywall and lath, building sewer and water service, stucco, gas line air test and final; all work must stay exposed until it passes. Every inspection must be cleared in writing, with final sign-off from Building, Planning, Public Works and Fire, before utilities are released and a certificate of occupancy is issued.
Want this handled start to finish?
Get a free quote →California building code in Soledad
Soledad enforces the state building code through its own Building & Safety Division; its zoning and density bonus rules are in the Soledad Municipal Code. FEMA’s Community Status Book lists Soledad (community 060204) as participating in the National Flood Insurance Program, with a current flood map dated November 30, 2023.
California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
Soledad building permit FAQs
Who issues building permits in Soledad?
The city’s Building & Safety Division at City Hall, 248 Main Street ((831) 223-5041), with 4Leaf as the contract Building Official.
How do I apply?
Through the SmartGov portal; create an account, and additional applicants request an access code by email. Fees are then paid in person.
How much is plan check?
65% of the building permit fee from Table 3A, charged by the city’s contract consultant; revisions are billed at actual cost.
When are inspections available?
Monday and Friday mornings until 11 a.m. and Wednesday from 11 a.m. to 2 p.m., booked at least two days ahead.
Who inspects mobile home parks?
The State Department of Housing and Community Development, (916) 255-2501, for the five parks in the city.
Do I need planning approval first?
If the project needs it, yes: required planning approvals must be granted before you can apply for the building permit.
Do I need a certificate of occupancy to open a business?
Yes. A certificate of occupancy ($307) and a city business license are both required to operate a commercial business.
Who handles encroachment permits?
Public Works, at (831) 223-5176; the FY 2026-27 fee is a $399 minimum plus a $1,192 deposit.
Soledad permit search and official resources
Applicants follow their own applications and inspection results in the SmartGov portal, which also lists public notices. For past permits on a property, Building & Safety posts a Building Research Record request form; call (831) 223-5041 with questions.
Inspections are where schedules slip.
Get a free quote →- Soledad Building & Safety Division
- Building permit services and forms
- Building inspection services
- Adopted Master Fee Schedule FY 2026-27 (PDF)
- General building permit information (PDF)
- Business licenses
- City of Soledad SmartGov permit portal
- Portal documents: building and planning forms
- Building permit application
- Certificate of occupancy application
- Site plan and architectural review checklist
- Planning permit application
- Density bonus application guidelines
- California Building Standards Code (Title 24)
- FEMA Community Status Book, California
Simplify Soledad permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Soledad sooner?
Let Alliance prepare, file, and track your Soledad permits while your crew stays on the job.
More California permitting guides
Monterey County
Read guide →Greenfield
Read guide →King City
Read guide →Sonoma Building Permit Guide
Read guide →Sonoma County Building Permit Guide
Read guide →South El Monte Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Soledad permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.