South El Monte, California Building Permit Guide

To get a building permit in South El Monte, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

South El Monte’s Building & Safety Division at 1415 Santa Anita Avenue issues building permits for the whole city; every residential and commercial application goes through the city’s Accela online permit portal.

Authority: South El Monte Building & Safety DivisionPhone: (626) 579-6540Hours: Mon–Thu
Authority
City Building & Safety1415 Santa Anita Avenue
Apply
Accela online portalNo hard-copy submittals
Issuance fee
$62 per permitFee schedule effective Sept. 1, 2023
Inspections
Mon, Wed and Thu24 hours’ notice by phone

Building permits in South El Monte come from the city’s Building & Safety Division in the Community Development Department, 1415 Santa Anita Avenue ((626) 579-6540). All residential and commercial applications are filed through the city’s Accela online permit portal, and the city has adopted the Los Angeles County Building Code as its building code. Under the general fee schedule effective September 1, 2023, each permit carries a $62 issuance fee plus valuation-based permit and plan check fees.

What requires a building permit in South El Monte?

South El Monte’s Building & Safety Division enforces the latest adopted building code for all buildings and structures in the city, and its permits page links the Los Angeles County Building Code (Title 26) as the code the city has adopted, so the permit and exemption rules are that code’s. The city’s own handouts and fee schedule show the work it permits most often.

City handouts show a permit for

  • Residential re-roofing, with any HOA approval filed at application
  • Patio covers (the forms page lists patio cover permit standards)
  • Additions, new buildings and tenant improvements, priced on valuation with plan check
  • Electrical, mechanical and plumbing work, including water heaters
  • Demolition, with a construction and demolition recycling plan and South Coast AQMD Form 1403 notice
  • Grading, sewer and septic work (Engineering forms)
  • Garage-to-ADU conversions and new ADUs

Planning steps that come first

  • Fences and walls carry a $187 Planning fee
  • ADUs need an approved Pre-Application Consultation
  • Business license zoning review for new businesses
  • Conditional use, variance and site development permits where zoning requires them

For a project not covered here, the permit counter answers at (626) 579-6540 or bldg@soelmonte.org.

What South El Monte decides and what the state holds

South El Monte’s adopted building code is the Los Angeles County Building Code, which carries the county’s amendments to the state code. Locally it sets its own fees (the September 1, 2023 schedule built on a December 2022 user fee study), its zoning code, its ADU ordinance and rules such as Ordinance 1216 of October 24, 2017, which bans commercial cannabis activity in every zone. Fire plan review is done by the Los Angeles County Fire Department.

South El Monte building department: who handles permitting

The Building & Safety Division reviews construction plans against the adopted building code, city ordinances and state and federal law, issues permits, inspects the work and keeps the history of permit records for every property in the city. It sits in the Community Development Department, which is led by the Director of Community Development and Public Works, Gerardo Marquez, and shares its building with Planning and Engineering. Fire plans go separately to the Los Angeles County Fire Department, and food businesses to Los Angeles County Environmental Health.

Short on time to read all of this?

Get a free quote →
South El Monte permit contacts
DetailInformation
OfficeBuilding & Safety Division, Community Development, 1415 Santa Anita Avenue, South El Monte, CA 91733
Phone / email(626) 579-6540 (permit counter ext. 3246); bldg@soelmonte.org; a city notice for portal users gives 626-242-1666
HoursMonday to Thursday (Planning lists 7:00 a.m. to 5:30 p.m.); closed on major holidays
PortalAccela online permit portal for all building permit applications
PlanningPlanning@soelmonte.org; (626) 579-6540
Fire plan checkLos Angeles County Fire Department: houses through EPIC-LA; commercial plans at 5200 Irwindale Ave., Suite 210, Irwindale, (626) 430-3050
Health plan checkLos Angeles County Environmental Health, 5050 Commerce Dr., Baldwin Park, (626) 430-5560

South El Monte permit types

Building permits are priced on the job’s valuation, with a separate building plan check fee. Electrical, mechanical and plumbing work is permitted per item under its own code tables, and separate electrical, mechanical or plumbing plan check applies when a project meets the triggers on the city’s questionnaire.

Residential permits

  • Re-roofs follow the city’s re-roofing handout, which applies the state code’s re-roofing section and asks for a copy of any HOA approval with the application.
  • Patio covers have their own entry in the city’s permit standards list, and the city posts sample floor and site plans for homeowners.
  • ADUs start with a Pre-Application Consultation package filed in the portal, a ministerial review by Planning that runs alongside building plan check; the building permit application is filed separately once Planning approves it. The city takes part in the San Gabriel Valley Council of Governments’ pre-approved ADU plans program, though a pre-approved plan still needs site-specific work and city review.
  • Garage conversions. The city’s garage-to-ADU handout lists the usual problems: a built-up floor over an unprotected slab can push the ceiling below the 7-foot minimum, the unit needs a compliant egress door and window, new openings within 5 feet of a property line raise fire-resistance issues, a non-gable roof or a wall too cut up for prescriptive bracing needs an engineer’s design, a permanent heating system is required, the electrical panel may need a sub-panel or upgrade, a lot sloping to the rear may need a sewage ejector, and the existing insulation often fails the energy calculation.
  • Smoke and carbon monoxide alarm verification forms are part of residential permit work.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

Projects other than single-family homes that are submitted without trade plans fill in the city’s mechanical, electrical and plumbing plan check questionnaire. Separate mechanical plan review is needed for systems over 500,000 BTU, commercial kitchen hoods, garage exhaust, spray booths, smoke dampers or air systems over 2,000 cfm; separate electrical review for equipment of 400 amperes or more, motors over 10 horsepower, generators, transformers or batteries, equipment above 600 volts, assembly rooms over 500 people, and gas stations or repair garages. Under state law AB 3002, commercial permit and business license applicants receive a disability-access notice, and food businesses need county Environmental Health plan check. Industrial waste discharge permits and Low Impact Development (LID) plans have their own city forms.

What comes before the building permit

  • Planning. Zoning review comes first for ADUs, fences and walls ($187) and discretionary approvals such as a conditional use permit ($3,500), minor CUP ($2,250), R1 variance ($1,000) or site development permit ($6,250). A pre-application consultation costs $105 for R1 lots and $375 for R2 and above.
  • Fire. One- and two-family dwelling plans go to the Los Angeles County Fire Department through EPIC-LA (the city’s routing sheet says about 20 days); commercial fire plans go to the county’s Irwindale office.
  • Grading and stormwater. LID review must be completed before grading plan review, and grading jobs need a registered civil engineer acknowledgement and supervised grading inspection form.
  • Demolition. A recycling plan for construction and demolition debris and the South Coast AQMD Form 1403 notice are filed with the demolition permit.

South El Monte permit fees

The city’s General Fee Schedule took effect on September 1, 2023, and its building fees come from the NBS user fee study dated December 1, 2022. Permit and plan check fees each have a base for a valuation band plus an amount for each additional $1,000.

Rather talk it over?

Call 1-855-478-4290 →
Selected South El Monte building fees (effective September 1, 2023)
ItemFee
Building permit, from $2,001$124 base, plus $35.047 per additional $1,000
Building permit, from $25,001$930 base, plus $21.080 per additional $1,000
Building permit, from $50,001$1,457 base, plus $19.840 per additional $1,000
Building permit, from $100,001$2,449 base, plus $12.400 per additional $1,000
Building plan check, from $2,001$248 base, plus $40.441 per additional $1,000
Building plan check, from $25,001$1,178 base, plus $27.234 per additional $1,000
Building plan check, from $50,001$1,859 base, plus $24.785 per additional $1,000
Permit issuance$62
Water heater and/or vent$62
Plan review beyond the second check, or extra inspections$124 per hour in business hours
Preliminary review$258 for the first 2 hours, then $129 per hour
Technology fee2% per application
Work without a permitDouble the permit fee

Worked example: a job valued at $20,000 is 18 thousands above the $2,001 band start, so the permit fee is $124 + 18 × $35.047 = $754.85 and plan check is $248 + 18 × $40.441 = $975.94. With the $62 issuance fee that totals $1,792.79, before the 2% technology fee and the state seismic (0.013% of valuation for one- to three-story homes, $2.60 here) and building standards ($1) fees. Trade permits for the same job are priced separately from the electrical, mechanical and plumbing tables.

Planning and Engineering fees are separate, including an $84 Engineering permit issuance fee on encroachment and other Public Works permits. School district and sanitation district charges are not in the city schedule.

Trade permits and who may pull them in South El Monte

Electrical, mechanical and plumbing permits use the per-item tables in the general fee schedule, for example $62 for each water heater or vent. On commercial jobs the Building Official may still ask for trade plans after the first review even if the questionnaire answers are all "no".

  • Licensing. The city’s forms page links the Contractors State License Board check for contractor licenses and home improvement salesperson registrations.
  • Business license. Under the city’s business license rates (Resolution No. 95-64 of December 14, 1995), a contractor based in South El Monte pays an annual registration of $100 plus $10 per employee, and a contractor from outside the city pays $50 per quarter. Business licenses are applied for through the city’s online business license portal.

Rather not deal with the building department?

Get a free quote →

How to apply for a South El Monte building permit

1. Check zoning and the parcel

Use the county assessor’s property map and the city zoning code, and ask Planning whether a pre-application consultation or discretionary approval is needed.

2. Create an Accela account

All residential and commercial building applications are submitted through the city’s Accela online permit portal.

3. Prepare electronic plans

One PDF set of plans for Planning and Building, plus any trade plans the questionnaire calls for, grading and LID reports, and the alarm verification form.

4. Send fire and health plans to the county

Submit dwelling fire plans through EPIC-LA or commercial plans to the Irwindale office; food businesses go to Environmental Health.

5. Answer corrections

Resubmit corrected plans electronically; the first and second checks are covered by the plan check fee.

6. Collect the permit

When plans and all agency approvals are in, the permit counter contacts you to issue the permit and collect fees.

Review, corrections and what causes delay

The city does not publish a building plan check turnaround; the county’s fire plan check for one- and two-family dwellings is listed at about 20 days. Reviews beyond the second plan check, revisions to approved plans and extra inspections are billed at $124 an hour. Missing county fire or health approvals, LID review not finished before grading review, and missing trade plans are the gaps the city’s routing sheet and questionnaire point to. The city’s Request for Extension form covers permits and plan checks that need more time.

Inspections in South El Monte

Building inspections run on Mondays, Wednesdays and Thursdays, from 9:00 a.m. to noon and 2:00 to 3:00 p.m.; inspectors are in the office from 8:00 to 9:00 a.m. and noon to 1:00 p.m. Requests need 24 hours’ notice, and a Monday inspection must be booked by the Thursday before. The portal’s inspection scheduler is down, so the city asks for requests by phone at (626) 579-6540.

Grading jobs file the city’s supervised grading inspection verification form. Extra inspections, and inspections for work with no listed fee, are charged at $124 an hour in business hours or $127 after hours.

California building code in South El Monte

South El Monte enforces the state code through the Los Angeles County Building Code, which its permits page lists as the city’s adopted building code. FEMA’s Community Status Book lists South El Monte (community 060162) as participating in the National Flood Insurance Program, with no special flood hazard area mapped in the city.

Want this handled start to finish?

Get a free quote →

California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments

South El Monte building permit FAQ

Can I apply for a building permit in person?

The city says all building permit applications, residential or commercial, must be submitted through its Accela online permit portal, and its routing sheet says no hard-copy submissions are taken.

How much is a building permit in South El Monte?

A $20,000 job pays $754.85 in permit fees and $975.94 in plan check, plus the $62 issuance fee, a 2% technology fee and small state fees, under the schedule effective September 1, 2023.

How do I schedule an inspection?

Call (626) 579-6540 at least 24 hours ahead; Monday inspections must be booked by the Thursday before. Inspections run Monday, Wednesday and Thursday.

How do I get an ADU approved?

File a Pre-Application Consultation package in the portal first. After Planning approves it, file the building permit application separately. Pre-approved ADU plans from the San Gabriel Valley Council of Governments program can be bought from their designers.

Do contractors need a South El Monte business license?

The city’s fee schedule sets contractor business license rates: $100 a year plus $10 per employee for contractors based in the city, and $50 per quarter for those from outside it.

Who reviews fire plans?

The Los Angeles County Fire Department. Dwelling plans are filed through the county’s EPIC-LA portal and take about 20 days; commercial fire plans go to the county office in Irwindale.

South El Monte permit search and official resources

The Building & Safety Division keeps the history of permit records for every property in the city; the Accela portal shows the status of your own applications, and records research is charged at $124 an hour. A zoning compliance letter from Planning costs $105.

Inspections are where schedules slip.

Get a free quote →

Simplify South El Monte permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in South El Monte sooner?

Let Alliance prepare, file, and track your South El Monte permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about South El Monte permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.