Temple City, California Building Permit Guide

To get a building permit in Temple City, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Temple City’s Building & Safety division at City Hall, 9701 Las Tunas Drive, reviews plans, issues permits and inspects all construction in the city, and charges 120% of Los Angeles County’s plan check and permit fees.

Authority: Temple City Building & SafetyPhone: (626) 285-0488Inspections: (626) 656-7327
Authority
City Building & Safety9701 Las Tunas Drive
Fees
120% of county feesExcept encroachment permits
Plan review
About two weeksPlanning approval comes first
Permit life
Six monthsPlan check approval good one year

Building permits in Temple City come from the city’s Building & Safety division of the Community Development Department at City Hall, 9701 Las Tunas Drive (building@templecity.us, (626) 285-0488), which also issues encroachment permits for work in the street. Planning must approve a project before plans go to Building, plan review averages two weeks, and plan check and permit fees are set at 120% of the Los Angeles County fees.

What requires a building permit in Temple City?

Temple City’s Building & Safety division covers all types of construction, and its review process lists structural, mechanical, plumbing, electrical and grading plans as the plans it checks. The Building & Safety pages give no list of exempt work, and the starting point is the Planning Division, which reviews plans for all new construction and new businesses before Building takes them.

Permits the city handles

  • New buildings, additions and alterations, with structural plan check
  • Electrical, plumbing and mechanical work
  • Grading
  • Window replacements (the city’s B-001 form lists each window’s size and egress dimensions)
  • Garage conversions and new ADUs
  • Solar energy systems and EV chargers, which have their own online applications
  • Encroachment permits for work in the public right-of-way, driveway approaches and sewer laterals

Approvals that come first

  • Planning approval of the plans before any building plan check
  • A zoning clearance and address assignment for an ADU on a pre-approved plan
  • A paid plan check application before plans are uploaded
  • Fire Department referral for an ADU when the water supply does not meet the fire-flow figures

What Temple City decides and what the state holds

Locally, Temple City sets its own fee rule (120% of the county’s building fees), its zoning code, the time limits on plan check approvals and permits, and its own encroachment fee schedule. The Building Inspector makes the final call on whether replacement windows meet code at inspection. Its ADU handout applies the code’s change-of-use rules to garage conversions in detail, as set out below.

Temple City building department: who handles permitting

The Building & Safety division of the Community Development Department, led by Community Development Director Scott Reimers, reviews plans, issues permits and inspects every kind of construction in the city, and it also issues encroachment permits for the public right-of-way. Planning, in the same department, reviews plans for new construction and new businesses first.

Short on time to read all of this?

Get a free quote →
Temple City permit contacts
DetailInformation
OfficeBuilding & Safety, Community Development, City Hall, 9701 Las Tunas Drive, Temple City, CA 91780
Phone / email(626) 285-0488; building@templecity.us
Permit techniciansMonday to Thursday, 8:00 to 11:30 a.m. and 1:30 to 4:30 p.m.; appointments recommended
Plan checkerMonday and Wednesday, 8:00 to 11:30 a.m.
Inspection requests(626) 656-7327, Monday to Thursday
Planning(626) 656-7316; planning@templecity.us; Monday to Friday, 8:00 to 11:30 a.m. and 1:30 to 4:30 p.m.

Temple City permit types

Most work goes through plan check: you file a plan check application with Building, pay the fee, then submit plans either at City Hall or, optionally, through the city’s electronic plan check (e-PlanSoft) at no extra charge. Solar energy systems and EV chargers can be applied for directly in the city’s Permit & Project Portal.

Residential permits

  • Window replacements use form B-001, listing each room and window with the new size, type and egress dimensions, plus a floor plan labelling every room. Sleeping rooms need an emergency escape opening of 5.7 square feet (5.0 square feet at grade), at least 24 inches high and 20 inches wide with the sill no higher than 44 inches, and the form repeats the smoke and carbon monoxide alarm locations.
  • Garage-to-ADU conversions are a change of use from garage to dwelling, so the city’s ADU handout says the structure must be brought up to current code: fire-rated walls within 5 feet of a property line, a new footing where the garage door opening is framed in, a vapor retarder over the existing slab, and its own heating unit.
  • Attached ADUs need a 1-hour fire separation and sound rating of STC 50 from the main house, and an addition to a garage for an ADU means a structural reanalysis.
  • Older unpermitted ADUs. Under AB 2533 the city offers a streamlined path for an ADU or JADU built or converted before January 1, 2020: a Substandard Housing Inspection Checklist completed by a California-licensed B contractor, architect or engineer, a covenant recorded through Planning, proof of the construction date (assessor, escrow, disclosure or past city records), site and floor plans, photos and the application fee. Any violations found need plans and permits to correct them.
  • Rooftop solar. Small residential systems (photovoltaic up to 10 kW AC or solar thermal up to 30 kW thermal on a house or duplex, within the zoning height limit) can be applied for online with the city’s solar combination permit application and standard plans; the plan check fee is paid by card or eCheck, the Building Official checks completeness, and work may not start until the permit fee is paid and the permit issued.
  • Pre-approved ADU plans. The city lists two designer-owned plans (a 476-square-foot one-bedroom and a 799-square-foot two-bedroom); you buy the plan, add a site plan, file a zoning clearance and address assignment and submit online.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

Commercial projects follow the same Planning-first path, with structural, mechanical, plumbing, electrical and grading plans in the plan check package. The plan check fee covers the first review and up to two resubmittals; more than two resubmittals bring additional review fees. New businesses also go through Planning’s review and the city business license.

What comes before the building permit

  • Planning approval. Electronic plan check will not accept plans until Planning has approved them, a plan check application is on file with Building and the fees are paid in full.
  • Fire. For ADUs, the handout says fire sprinklers are required unless the main house has none, and a fire-flow form (Form 195) must show 1,250 gallons per minute in a fire hazard zone, 1,000 for an unsprinklered building or 500 for a sprinklered one outside a hazard zone, or the project is referred to the Fire Department. An attached structure over 3,600 square feet, or one more than 150 feet from a 20-foot paved access road, needs Fire Department approval.
  • Street work. Building & Safety issues the encroachment permit for work in the public right-of-way; driveway approaches follow the city’s residential driveway approach policy and sewer laterals its sewer lateral plans.

Temple City permit fees

Temple City sets its plan check and permit fees at 120% of the fees established by the County of Los Angeles, for every permit except encroachment permits, which follow the city’s own fee schedule. The county publishes its fees through Los Angeles County Public Works, and the city offers an online fee estimator for plan check, permit and certain development fees.

How Temple City fees are built
ItemRule
Building plan check and permit fees120% of the Los Angeles County fee for the same work
Electrical, plumbing and mechanical permits120% of the county fee
Encroachment permitsCity fee schedule
Plan review roundsTwo included; more than two resubmittals add review fees
Electronic plan checkNo additional charge

Rather talk it over?

Call 1-855-478-4290 →

Worked example: the county’s 2026-27 table for unincorporated areas lists a plan check fee of $540.62 and a permit fee of $638.63 for a $20,000 residential job that needs an energy check. At 120%, Temple City’s fees for the same job would be $648.74 for plan check and $766.36 for the permit; the county’s $41.35 issuance fee would become $49.62 if it is included in the 120% rule, which the city’s page does not spell out. The city’s online fee estimator gives the figure for a specific project.

Trade permits and who may pull them in Temple City

Electrical, plumbing and mechanical plans are part of the plan check package for larger jobs, and trade permits are priced at 120% of the county’s trade fees. The ADU handout notes that electrical plan check is not required to install a panel of 399 amps or less at 120/240 volts, single phase, but residential load calculations must show the service is big enough for the new unit; a separate meter or panel for an ADU is optional.

  • Contractor’s business license. Temple City issues a contractor’s business license, applied for or renewed online through the city’s business license portal or in person with the Contractor License Application, which asks for the state license number and expiry. Questions go to (626) 656-7316.

How to apply for a Temple City building permit

1. Book an appointment and see Planning

Planning reviews the plans for zoning first; appointments cut waiting at the counter.

2. File the plan check application

File it with Building and pay the plan check fee in full.

3. Submit plans

Bring them to City Hall or upload them through electronic plan check after reading the city’s submittal guidelines and file-naming rules.

4. First review

The city aims to review within two weeks and sends comments and corrections.

5. Revise and resubmit

Up to two resubmittals are covered; more than two cost extra.

6. Plan check approval and permit

The Building page says approval lasts one year from submittal (the e-plan guidelines count the year from the day the plan check fee is paid); an issued permit is valid for six months, and both may be extended.

7. Build and call for inspections

Request each inspection by phone before 3:30 p.m. for the next day.

Rather not deal with the Temple City building department?

Get a free quote →

Review, corrections and what causes delay

The city says the average review is two weeks. Its plan check status page lets you follow a review, and the plan checker answers questions on Monday and Wednesday mornings. Electronic submittals go through a completeness check first, and the city emails when a project is accepted or what is missing. The package must include the application showing the plan check number and fees paid and any Planning resolution or conditions of approval, and each file is named by street name, street number and plan type. Plans sent outside business hours (Monday to Friday, 8:00 a.m. to 5:00 p.m.) are checked the next business day, and under the e-plan guidelines the one-year life of a plan check starts on the day the plan check fee is paid, not the upload date.

Inspections in Temple City

Building inspections are made Monday through Thursday. Call (626) 656-7327 and leave a message with your name, permit number, job site address, type of inspection and a contact phone number. Requests received before 3:30 p.m. are scheduled for the next day; later calls go to the next available business day. The city posts a daily inspection schedule.

Inspections are made at the stages of construction set by the permit. For window replacements the inspector makes the final decision on whether each window meets the code, and the energy labels must stay on the glass until then.

California building code in Temple City

Temple City enforces the state code through its own Building & Safety division, with fees tied to Los Angeles County’s. Temple City is not found in the FEMA Community Status Book list for California. The ADU handout’s fire-flow figures distinguish parcels in a fire hazard zone from those outside one.

California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments

Temple City building permit FAQ

How much is a building permit in Temple City?

Plan check and permit fees are 120% of the Los Angeles County fees. For a $20,000 residential job with an energy check, that is $648.74 for plan check and $766.36 for the permit, based on the county’s 2026-27 table.

Want this handled start to finish?

Get a free quote →

How long does plan review take?

The city aims for two weeks or less per review, and says the average is two weeks. Planning must approve the project first.

How long is a permit good for?

A plan check approval is good for one year from submittal and an issued permit for six months; both can be extended.

How do I schedule an inspection?

Call (626) 656-7327 before 3:30 p.m. for a next-day inspection, Monday through Thursday.

Can I convert my garage into an ADU?

Yes, but it is a change of use, so the structure must meet current code, including fire-rated walls near property lines, a footing under the old garage door opening, a slab vapor retarder and separate heating. Planning sets the zoning requirements first.

Do contractors need a Temple City business license?

The city issues a contractor’s business license, applied for online or in person with the Contractor License Application.

Can I look up old permits?

Yes. The city’s online permit search shows scanned images of past paper permits, searched by street name and then street number; only one person can use it at a time.

Temple City permit search and official resources

Past paper permits are online as scanned PDFs through the city’s permit search, and newer permit and project records and plan check status are in the Permit & Project Portal. The city also publishes monthly Community Development reports listing permits issued.

Inspections are where schedules slip.

Get a free quote →

Simplify Temple City permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Temple City sooner?

Let Alliance prepare, file, and track your Temple City permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Temple City permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.