Inside the City of Seaside, building, electrical, plumbing and mechanical permits come from the Building & Code Enforcement Department at City Hall, 440 Harcourt Avenue, where Jose Jacobo is the Chief Building Official. Applications are accepted over the counter or by email to building@ci.seaside.ca.us, and the city calls when the permit is ready. Under the master fee schedule effective July 1, 2024, plan check and inspection for a new 2,500-square-foot wood-frame house total $17,958.91.
What requires a building permit in Seaside?
Seaside’s handout on unpermitted work restates the building code rule: a permit is needed when a structure is erected, built, enlarged, altered, repaired, moved, improved, removed, converted or demolished, with exceptions mainly for minor repairs and maintenance. The city recommends calling the department before any building project or major repair to confirm whether the scope needs a permit. Its fee schedule shows the range of work it permits:
Permitted work (fee schedule)
- New houses, additions, remodels and accessory buildings
- Re-roofs, siding and stucco, windows and doors, garage doors
- Fences and retaining walls, decks and patio covers
- Foundation repair and seismic retrofits
- Pools and spas, solar and battery systems
- Furnaces, water heaters, plumbing fixtures, gas lines, circuits and temporary power
- Demolition, signs and commercial tenant improvements
Work done without a permit
- Must meet the code in force when the retroactive permit is applied for, including setbacks, lot coverage and height
- Habitable space needs stamped as-built plans and an engineer’s inspection report
- Unpermitted electrical, plumbing or mechanical work can be documented with a licensed contractor’s report
- Work done before 1954 and kept in good repair needs no retroactive permit
Owners who rent out a structure built without permits are liable for tenant relocation benefits if tenants must vacate: at least the actual relocation cost, including two months’ rent and the deposit, up to $10,000. Work started without a permit also pays an investigation fee equal to the permit fee, capped at $500.
What Seaside decides and what the state holds
Seaside adopted the 2025 California codes with local amendments by Ordinance No. 2039, effective January 1, 2026, covering the building, residential, electrical, mechanical, plumbing, historical, existing building, green, energy and fire codes and the International Property Maintenance Code. The city also sets its fees, zoning and design review, and its real property disclosure report for sales. Contractors are licensed by the state.
Seaside building department: who handles permitting
The Building & Code Enforcement Department issues building permits, reviews plans, inspects construction and investigates municipal code and zoning complaints inside the city. Planning, which handles use permits, design review and planned development permits, works from 656 Broadway at the Seaside Creates office. Areas outside the city limits are unincorporated Monterey County.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Permits & Inspections counter, City Hall, 440 Harcourt Avenue, Seaside, CA 93955 |
| Hours | Monday to Friday, 8 a.m. to 5 p.m. |
| building@ci.seaside.ca.us | |
| Phones | Inspections 831-899-6723; Building Division 831-899-6737; code enforcement 831-899-6729 |
| Chief Building Official | Jose Jacobo |
| Planning | 656 Broadway; front counter 831-899-6825, planning assistance weekdays 10 a.m. to 4 p.m. |
| Online | Inspection requests online; planning applications in the SmartGov portal |
Seaside permit types
Seaside uses separate residential and commercial building permit applications. A submittal is complete only when every project detail, description, plan and attachment is listed and provided. The city’s plan review submittal package and preliminary application checklist describe what to include, and the forms page adds a plot plan example, a plan change or addendum request, a special inspection form, a certificate of occupancy application and an address request.
Residential permits
- New houses and additions are priced by floor area; the forms page posts development standards, bedroom requirements, insulation requirements and an erosion and sediment control plan template.
- Kitchens and bathrooms have their own remodel templates, and patio covers a plan check requirements sheet.
- Re-roofs take two or three inspections: pre-roof, nailing and final. Existing roofing must be torn off when it is water-soaked, when it is wood shake, slate, clay or cement tile, or when there are already two or more layers.
- Solar: licensed contractors can use SolarAPP+ for residential PV and PV with battery systems up to 38.4 kW, then apply in the city’s permitting system with the SolarAPP+ approval and pay online; SolarAPP+ charges its own processing fee.
Building or remodeling a home here? Alliance handles home building permits, so the crew isn't waiting on the counter.
Commercial permits
Commercial projects use the commercial application and the commercial plan review submittal package. The city’s plan review submittal package for multifamily and commercial or industrial work (dated December 31, 2019) asks for a plan review submittal form, minimum document checklist, occupancy inventory and construction valuation form; three plan sets on 18 by 24 or 24 by 36 inch sheets plus two sets of trade or site sheets; two sets of structural and energy calculations; and the architect’s or engineer’s stamp and signature on every page, with a wet-signed cover sheet at issuance. Ask the counter whether paper sets are still needed now that applications can be emailed. New commercial, multifamily, shell and tenant improvement work is priced by square footage and construction type, and commercial pools, cell towers, accessibility upgrades and coach installations have flat fees. Non-residential water use goes through the water release and permit application on the forms page.
Not sure this scope needs a permit?
Get a free quote →For tenant improvements and new commercial builds, Alliance handles commercial permit filing through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Planning. Use permits, minor use permits and planned development permits are filed in SmartGov; design review of a new one- or two-family house costs $1,200, and of an addition that adds less than half the structure $500.
- Stormwater. Construction projects file the stormwater compliance tracking form and follow the city’s post-construction low impact development manual and construction best management practices.
- Housing projects. A housing development preliminary application checklist is posted for projects using that path.
- Other clearances. Public Works (831-899-6835) reviews flood zone, geologic hazard and grading issues; City Fire (831-899-6790) reviews sprinklers, alarms and hazardous materials; Monterey One Water approves food and drinking establishments, public pools and manufacturing discharge; and county environmental health approves food businesses. Water allocation and meters go to the Monterey Peninsula Water Management District, Marina Coast Water District or California American Water, depending on the location.
Seaside permit costs and fees
The building page links Seaside’s master fee schedule effective July 1, 2024 (adopted with the fiscal 2024-25 budget, a 4% increase) as its current schedule. Most smaller jobs carry flat fees; new construction, additions and major remodels pay separate plan check and inspection fees set by building size, occupancy and construction type.
| Item | Fee |
|---|---|
| New house, 2,500 sq ft, wood frame (Type V): plan check / inspection | $6,984.10 / $10,974.81 |
| New house, 1,000 sq ft, wood frame: plan check / inspection | $5,488.10 / $7,981.42 |
| Residential addition or structural remodel, 200 sq ft: inspection | $997.33 |
| Residential solar (permit and inspection) | $500 plus $15 per kW above 15 kW |
| Re-roof | $157 for the first 10 squares plus $75 per added square (fee column lists $218) |
| Siding or stucco / fence or non-engineered wall / demolition | $330 each |
| Windows or doors, first 10: non-structural / structural | $330 / $439 |
| Water heater / plumbing fixtures | $218 / $36 each, $440 minimum |
| Furnace | $439 |
| Certificate of occupancy | $240 |
| Additional plan check or re-inspection | $331 an hour, minimum |
| After-hours or fast-track plan check (3-hour minimum) | $2,088 |
| Work without a permit | Equal to the permit fee, up to $500 |
Rather talk it over?
Call 1-855-478-4290 →Worked example from the new construction tables: a 2,500-square-foot one-family house of wood-frame construction sits exactly on a table threshold, so plan check is $6,984.10 and inspection $10,974.81, a total of $17,958.91 before trade items, school, water and sewer charges. Sizes between thresholds add the listed cost per square foot.
Electrical, plumbing and mechanical permits not tied to a building permit are reviewed at $695 an hour, with item fees such as $330 for each 10 circuits of 15 or 20 amps and $330 for a sewer lateral test. A new address costs $158, a temporary certificate of occupancy $240 plus a deposit, a garage door replacement $218, and a seismic retrofit of a building under 5,000 square feet $3,130.
Trade permits and who may pull them
The Building & Code Enforcement Department issues electrical, plumbing and mechanical permits, either with a building permit or on their own at the rates in the fee schedule. Contractors use the city’s contractor-only business license tax certificate application; others use the non-contractor version. The application fee is $18, and license taxes follow Seaside Municipal Code chapter 5.04.
- SolarAPP+ is limited to qualified licensed contractors.
- Unpermitted trade work that is not exposed can be documented for final inspection with a report from a C-10 electrician, a licensed plumber or a licensed mechanical contractor or engineer, though the Building Official may still require opening walls.
- Retroactive permits for habitable space need as-built plans bearing the original stamp and signature of a California architect or engineer.
Rather not deal with the building department?
Get a free quote →How to apply for a Seaside building permit
Call the department, and file any use permit or design review with Planning in SmartGov first.
Follow the plan review submittal package and preliminary application checklist, and list every plan and attachment.
Residential or commercial building permit application, or the SolarAPP+ path for eligible solar.
Bring it to the Permits & Inspections counter at City Hall or email building@ci.seaside.ca.us.
Use the plan change or addendum request for later revisions.
The city contacts you when the permit is ready to be issued.
Review, corrections and what causes delay
Incomplete submittals are the main cause of delay: the city treats an application as complete only when all project details, plans and attachments are provided. Plan check beyond the standard number of reviews is billed at $331 an hour, and applicants who want after-hours or fast-track review can pay $2,088 for a three-hour minimum or $2,784 for four hours.
Inspections in Seaside
Request inspections online or at 831-899-6723, at least 48 hours ahead. Inspections run Monday through Friday, except city holidays, in a morning (8:30 a.m. to noon) or afternoon (1 to 4 p.m.) window. A confirmation email follows within one business day, or staff call to arrange the next open slot, and the assigned inspector phones on the morning of the inspection with a narrower arrival time.
- Voicemail requests must give the requested date and time, permit number, job address, inspection type and a contact name and phone; a complete message puts you on the schedule even if no one calls back.
- For re-roofs, post the address where it can be seen, keep the job card on site and provide a safe ladder and fall protection.
- The final leads to a certificate of occupancy ($240).
Before any sale of real property in Seaside, the seller must complete a Real Property Disclosure Report under Municipal Code section 2.50.010. Staff review zoning, general plan, permit and assessor records and inspect the exterior and covered parking, checking that any garage door works; interiors are generally excluded unless there is reason to suspect violations. The fee follows the approved schedule and is non-refundable, and properties in the Monterey Peninsula Water Management District also need the district’s change-of-ownership inspection.
California building code in Seaside
Seaside enforces the 2025 California codes with the local amendments in Ordinance No. 2039, effective January 1, 2026, and every project submitted after that date must comply with both. The city’s municipal code is linked from its City Code page. FEMA’s Community Status Book lists Seaside (community 060203) as participating in the National Flood Insurance Program, with a current flood map dated June 21, 2017.
California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
Want this handled start to finish?
Get a free quote →Seaside building permit FAQs
Who issues building permits in Seaside?
The city’s Building & Code Enforcement Department at City Hall, 440 Harcourt Avenue, for property inside the city.
How do I submit an application?
In person at the Permits & Inspections counter or by email to building@ci.seaside.ca.us, using the residential or commercial application.
How much does a new house permit cost?
For a 2,500-square-foot wood-frame house, plan check is $6,984.10 and inspection $10,974.81 under the July 2024 schedule, before trade, school, water and sewer charges.
How much is a re-roof permit?
The schedule’s re-roof line reads $157 for the first 10 squares plus $75 for each additional square, while its adopted fee column shows $218, so ask the counter which applies; a re-roof takes two or three inspections.
How do I schedule an inspection?
Online or at 831-899-6723, 48 hours ahead; you get a morning or afternoon window and a call from the inspector that morning.
What if work was done without a permit?
Apply for a retroactive permit: the work must meet current code, and habitable space needs stamped as-built plans and an engineer’s report.
Does Seaside accept SolarAPP+?
Yes, for qualified licensed contractors installing residential PV, with or without batteries, up to 38.4 kW; upload the SolarAPP+ approval when applying in the city’s permitting system.
Do I need anything from the city to sell property?
Yes. A Real Property Disclosure Report must be completed before the sale.
Seaside permit search and official resources
For the permit history and code status of a property being sold, the Real Property Disclosure Report draws on the city’s permit records. Planning applications can be tracked in the SmartGov portal, and building permit questions go to the department at City Hall.
Inspections are where schedules slip.
Get a free quote →- Seaside Building & Code Enforcement
- Residential building permit application
- Commercial building permit application
- Plan review submittal package
- Building applications and forms
- Master fee schedule, effective July 1, 2024
- Building inspections
- Online inspection request
- SolarAPP+
- Re-roof procedure and inspections
- Structures built without required permits
- Real property disclosure report
- SmartGov planning portal
- Building & Code Enforcement staff directory
- California Building Standards Code (Title 24)
- FEMA Community Status Book, California
Simplify Seaside permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Seaside sooner?
Let Alliance prepare, file, and track your Seaside permits while your crew stays on the job.
More California permitting guides
Monterey County
Read guide →Greenfield
Read guide →King City
Read guide →Selma Building Permit Guide
Read guide →Shafter Building Permit Guide
Read guide →Shasta County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Seaside permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.