Building permits in Pacifica are issued by the city’s Building Division in the Community Development Department (650-738-7341). Most applications are filed through the city’s online permit portal; eligible rooftop solar on a house or duplex can be permitted instantly through SolarAPP+. The first plan review typically takes three to four weeks and each resubmittal two to three weeks. Fees come from the Citywide Fee Schedule for FY 2025-26, effective July 1, 2025: a valuation-based permit fee, plan check at 65% of it, and a general plan maintenance fee of 0.252% of construction value. Inspections are booked on the hotline at 650-737-1000.
What requires a building permit in Pacifica?
The Building Division posts three handouts on the question: “Do I need a Building Permit?”, “When is a Building permit not required” and “When is a Licensed Professional required?”. The fee schedule and the division’s pages show the main kinds of permitted work:
Permitted work
- New buildings, additions, alterations and decks (the city posts deck requirements)
- Electrical work, from service changes to new wiring, appliances and pool circuits
- Plumbing work, each permit carrying its own issuance fee
- Solar PV and solar thermal systems
- Demolition and deconstruction; the city posts a construction, deconstruction and demolition guide, a debris waste management plan and a PCB screening form for building demolitions
- Seismic retrofits, for which the city offers a standard plan set
Extra paperwork that can apply
- A Tree Encroachment, Protection and Preservation Plan for work within 50 feet of a protected or heritage tree
- A smoke detector and carbon monoxide form
- Special inspection forms and a recognized agency
- Construction stormwater best management practices
- Park Facilities fee if a bedroom is added; Jefferson Union High School District fees if 500 sq ft or more is added
Building without a permit is charged double the building permit fee, and unpermitted work that needs an engineering permit is charged double the engineering permit cost.
What Pacifica decides and what the state holds
Pacifica has adopted local amendments to several of the 2025 California codes, codified in Municipal Code Title 8, which also sets construction hours (Section 8-1.05). The city’s tree ordinance (Sections 4-12.06, 4-12.08 and 4-12.11), its fee schedule and its development impact fees are local. The base codes, and contractor licensing, come from the state.
Pacifica building department: who handles permitting
The City of Pacifica’s Building Division, part of the Community Development Department, issues building permits and runs plan review and inspections inside the city. The Citywide Fee Schedule also sets review fees for Planning, Engineering, Wastewater and the Fire Department, and comments from all reviewing departments are released together once every reviewer has finished. Fire permits and inspections have their own page on the Fire Department’s site.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Building Division | 650-738-7341 or 650-359-5807 |
| Building Official hours | 8:30 a.m. to 12:00 p.m. |
| Building Inspection Hotline | 650-737-1000 |
| City Hall | 170 Santa Maria Avenue, Pacifica, CA 94044; 650-738-7300 |
| Online applications | City permit portal; notifications come from donotreply@csgengr.com |
| Residential solar | SolarAPP+ |
Pacifica permit types
Most building permits are applied for in the online permit portal, following the city’s Online Permit Portal Submittal Procedures. Notification emails come from donotreply@csgengr.com, so applicants should check spam folders if nothing arrives.
Residential permits
- Rooftop solar: PV and energy storage on a single-family home or duplex may qualify for a real-time permit through SolarAPP+, but systems valued at $50,000 or more, or needing a panel upgrade, use the standard process. The residential solar fee is $263 plus $15 per kW above 15 kW, plus the state SMIP and building standards fees.
- Additions: adding a bedroom can trigger the Park Facilities fee, and adding 500 sq ft or more can trigger Jefferson Union High School District fees.
- Seismic retrofits: the city posts a Seismic Retrofit Standard (Plan Set A).
- EV charging and electrification: an EV charging checklist and an electrification page support those permits.
- Decks: the city’s deck requirements handout applies.
Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
Commercial work uses the same valuation-based fee and 65% plan check. Commercial solar is $394 up to 50 kW, plus $7 per kW from 51 to 250 kW and $5 per kW above 250 kW. The city posts a handout on disability access requirements for commercial building permits and business licensing. New sewer connections for commercial units are priced by water meter size times a commercial strength factor, and fire sprinkler plan review and inspection is charged by the Fire Department.
For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Planning applications: development applications are deposit-based and billed at $263 an hour; a zoning verification letter is $131.
- Trees: work within 50 feet of a protected or heritage tree needs a Tree Encroachment, Protection and Preservation Plan by a qualified professional such as a licensed arborist, horticulturist or landscape architect; trees are measured at 4.5 feet above ground. A tree permit tied to a building permit is billed at $263 an hour.
- Engineering: grading permits are charged at actual time and materials, and encroachment permits and inspection at $263 an hour.
- Landslides and flooding: the division posts a landslide preparedness notice and flood insurance map information.
- Utilities: the division posts a courtesy notice on PG&E lead times.
Not sure this scope needs a permit?
Get a free quote →Pacifica building permit fees
Review and permit issuance fees follow the Citywide Fee Schedule for FY 2025-26, effective July 1, 2025, the schedule linked from the Building Division page; it prints the adopted 2024-25 and 2025-26 amounts, so ask the Building Division whether newer amounts apply in the fiscal year that began July 1, 2026. The building permit fee is based on dollar valuation, using ICC building valuation data adjusted by the Engineering News-Record San Francisco Bay Area Building Cost Index.
| Total valuation | Fee |
|---|---|
| $1 to $500 | $75 |
| $501 to $2,000 | $75 for the first $500 + $4 per additional $100 |
| $2,001 to $25,000 | $137 for the first $2,000 + $19 per additional $1,000 |
| $25,001 to $50,000 | $597 for the first $25,000 + $17 per additional $1,000 |
| $50,001 to $100,000 | $1,044 for the first $50,000 + $9 per additional $1,000 |
| $100,001 to $500,000 | $1,516 for the first $100,000 + $8 per additional $1,000 |
| $500,001 to $1,000,000 | $4,878 for the first $500,000 + $6 per additional $1,000 |
| Over $1,000,000 | $8,030 for the first $1,000,000 + $5 per additional $1,000 |
The bands do not run into each other exactly (the $100,001 band reaches $4,716 at $500,000, while the next band starts at $4,878), so use the band the valuation falls in. Plan check is 65% of the permit fee; the general plan maintenance fee is 0.252% of construction value; an education fee of $2 is charged per permit; and the archive fee is $15 plus $1 per plan page for sheets larger than 11 by 17 inches.
Worked example: a house addition valued at $200,000. The permit fee is $1,516 plus 100 × $8, or $2,316. Plan check at 65% adds $1,505.40, general plan maintenance at 0.252% adds $504, SMIP for a residential building up to three stories (0.00013 of valuation) adds $26, the building standards fee ($4 per $100,000) adds $8 and the education fee $2: $4,361.40 before the archive fee, trade items, school and park fees.
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee |
|---|---|
| Hourly plan check (Planning, Engineering, Wastewater) and permit change review | $263 per hour |
| Inspection outside normal hours | Contract staff: actual consultant cost; city staff: time and a half, 2-hour minimum |
| Building without a permit | Double the building permit fee |
| Fire plan review, new construction or tenant improvement (includes first hour) | $336 |
| Fire plan check resubmittal or each additional hour of fire review | $202 |
| Fire sprinklers, new commercial or residential installation | $0.15 per sq ft, $606 minimum |
| Fire sprinklers in a tenant improvement with 9 or fewer heads / new manufactured home system | $193 / $647 |
| Tree permit not tied to a building permit (hourly) / tree permit appeal | $256 / $461 |
| Address assignment or change | $263 |
| Sewer connection, residential, 1-inch / 1.5-inch / 2-inch meter | $12,497 / $24,994 / $39,990 |
| Sewer connection for an ADU | Total drainage fixture units × $658 |
| Extension of a development application permit | $788 |
Development impact fees calculated by Public Works include the in-lieu park dedication fee (updated by Ordinance 878-C.S., May 9, 2022), the Highway 1 Improvement Fee, the Oceana/Manor/Palmetto mitigation fee and the subdivision drainage fee; the Capital Improvement Fee is calculated by the Building Department. Card payments carry a 3.0% service fee.
Trade permits and who may pull them in Pacifica
Electrical and plumbing permits are issued by the Building Division under the same fee schedule. Electrical items for FY 2025-26 include $0.15 per sq ft for a new residential building ($0.14 for multifamily), $54 for a service up to 200 amps, $113 for 200 to 1,000 amps and $226 above 1,000 amps, $44 for temporary power, $87 for a private pool and $7 for each residential appliance. Plumbing permits carry a $45 issuance fee ($17 for a supplemental permit on an open one), with miscellaneous plumbing items at $21.
The division posts a handout titled “When is a Licensed Professional required?” for questions about who must prepare plans. Contractors need the CSLB license for their trade; owners may apply as owner-builders for their own property. Planning charges $131 to review a business license request for zoning consistency.
Rather not deal with the building department?
Get a free quote →How to apply for a Pacifica building permit
Use “Do I need a Building Permit?” and “When is a Licensed Professional required?” to scope the job.
If any protected or heritage tree is within 50 feet, commission a tree protection plan from a qualified professional.
Follow the Online Permit Portal Submittal Procedures, or use SolarAPP+ for an eligible home solar system.
Upload the application, plans and forms in the portal and watch for emails from donotreply@csgengr.com.
Comments arrive once every department has finished; resubmittals take about two to three weeks each.
After approval, the processing stage of up to a week stamps the plans and calculates final fees.
Call the hotline at 650-737-1000, no more than one week ahead.
Review, corrections and what causes delay
The first review typically takes three to four weeks, and every resubmittal about two to three weeks. Once all departments approve, the project enters a processing stage of up to a week while staff collate the files into an approved set, stamp them and calculate the final fees; the applicant is then told the next steps through the permit account. Changes to an existing permit are billed at the hourly review rates of every department that must look at them, and more building fees can apply if the change affects valuation.
Pacifica building inspections
Inspections are scheduled by calling the Building Inspection Hotline at 650-737-1000, and cannot be requested more than one week in advance. The Building Division posts the current inspection schedule on its page. Inspections outside normal business hours are charged at actual consultant cost when a contract inspector does them, or at time and a half with a two-hour minimum for city staff.
Construction hours are set in Municipal Code Title 8, Chapter 1, Section 8-1.05. Projects that need special inspections use the city’s special inspection form and its list of recognized special inspection and testing agencies; a smoke detector and carbon monoxide form is also posted. Fire sprinkler and other fire construction permits are inspected by the Fire Department.
California building code in Pacifica
The 2025 California building, residential, electrical, plumbing, mechanical, energy and green building codes and the California Wildland-Urban Interface Code have been in effect in Pacifica since January 1, 2026, with the city’s local amendments codified in Municipal Code Title 8. FEMA’s Community Status Book lists the City of Pacifica (community 060323) as participating in the National Flood Insurance Program, with a current flood map dated April 5, 2019, and in the Community Rating System at class 8 (10% flood insurance discount) since October 1, 2024.
California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
Want this handled start to finish?
Get a free quote →Pacifica permit search and official resources
The Building Division posts monthly permit activity reports, and each applicant follows a permit’s status in the online portal account. For older records on a property, contact the division at 650-738-7341.
- Pacifica Building Division
- Online permit portal submittal procedures
- SolarAPP+
- Electrification
- Monthly permit activity reports
- Current inspection schedule
- Do I need a building permit?
- When is a building permit not required
- When is a licensed professional required?
- Deck requirements
- Construction and demolition debris waste management plan
- Recognized special inspection and testing agencies
- Smoke detector and carbon monoxide form
- Seismic Retrofit Standard (Plan Set A)
- Landslide preparedness
- Fire Department permits and inspections
- Citywide Fee Schedule FY 2025-26
- California Building Standards Code (Title 24)
- FEMA Community Status Book, California
Inspections are where schedules slip.
Get a free quote →Pacifica building permit FAQs
How long does a building permit take in Pacifica?
The first review typically takes three to four weeks, each resubmittal two to three weeks, and the processing stage after approval up to a week.
How do I schedule an inspection in Pacifica?
Call the Building Inspection Hotline at 650-737-1000, no more than one week before the inspection date.
How is the permit fee calculated?
From the project valuation under the FY 2025-26 Citywide Fee Schedule, with plan check at 65% of the permit fee. A $200,000 addition comes to $4,361.40 with plan check and the standard surcharges.
Do I need a permit near a protected tree?
Construction within 50 feet of a protected or heritage tree needs a Tree Encroachment, Protection and Preservation Plan submitted with the building permit application.
Can I use SolarAPP+?
Yes, for rooftop PV and storage on a single-family home or duplex, unless the system is valued at $50,000 or more or needs a panel upgrade.
Will my addition pay school or park fees?
Adding a bedroom can trigger the Park Facilities fee, and adding 500 sq ft or more can trigger Jefferson Union High School District fees.
What does building without a permit cost?
Double the building permit fee.
Has Pacifica amended the state codes?
Yes. Its local amendments to several 2025 California codes are codified in Municipal Code Title 8.
Simplify Pacifica permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Pacifica sooner?
Let Alliance prepare, file, and track your Pacifica permits while your crew stays on the job.
More California permitting guides
San Mateo County
Read guide →Redwood City
Read guide →San Bruno
Read guide →Palm Desert Building Permit Guide
Read guide →Palm Springs Building Permit Guide
Read guide →Palmdale Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Pacifica permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.