Inside Palm Springs, building permits come from the city’s Building Safety Department at City Hall, 3200 E. Tahquitz Canyon Way (760-322-8398, buildingsafetydepartment@palmspringsca.gov). The public counter is open Monday to Thursday, 7:30 a.m. to 5:30 p.m., and applications are filed online in Palm Springs Online. Under the FY 2025–2027 Comprehensive Fee Schedule each building permit carries a $328 issuance fee, and a 200 sq ft home addition is $1,424 before that fee.
What requires a building permit in Palm Springs?
The department’s rule is broad: an owner or authorized agent who plans to build, enlarge, alter, repair, move, demolish or change the occupancy of a building or structure, or to install, alter, repair, remove, convert or replace an electrical, gas, mechanical or plumbing system regulated by the state code, must apply and obtain a permit first. Its Permits page answers the common questions.
Permit required
- Fences and walls over 3 feet high, measured from finished grade to the top
- All attached and free-standing patio covers
- New air conditioners, replacements and major HVAC repairs
- Re-roofing or roof repairs over 100 sq ft on a home or garage
- Installing or replacing a water heater
No permit required
- A patio slab
- Tool or storage sheds, playhouses and similar buildings up to 120 sq ft with no plumbing, mechanical or electrical work, within the page’s 10-foot height limit (15 feet in the R-1-AH and R-1-A zones)
The page sets the 3-foot test aside for walls that support a surcharge or impound flammable or combustible liquids, so ask the department about those. A shed taller than the fence or wall line must sit at least 10 feet (15 feet in R-1-A and R-1-AH) from the side and rear property lines under Section 92.01.03 of the municipal code. Work built without a permit can be legalized through the permit process; if that is not possible, it has to be removed under a demolition permit.
What Palm Springs decides and what the state holds
The city sets its own Comprehensive Fee Schedule and construction tax (Chapter 3.94), and collects the Coachella Valley regional fees under Chapters 8.90 and 8.95. The shed setbacks come from Section 92.01.03 and business licenses from Chapters 3.40 to 3.96. Contractor licenses are issued by the state Contractors State License Board, whose website lets anyone check a contractor by name or license number.
Palm Springs building department: who handles permitting
The city’s Building Safety Department reviews plans, issues permits and inspects construction throughout Palm Springs. Riverside County permits only unincorporated land outside the city. When it issues a permit the department also collects the related Planning, Engineering and Fire fees, and the Comprehensive Fee Schedule includes the Fire Department’s plan review and inspection charges.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Building Safety Department, City Hall, 3200 E. Tahquitz Canyon Way, Palm Springs, CA 92262 |
| Main line | 760-322-8398; fax 760-778-8441; TDD 760-864-9527 |
| Permit Center email | buildingsafetydepartment@palmspringsca.gov |
| Counter hours | Monday to Thursday, 7:30 a.m. to 5:30 p.m. |
| Inspections | building.inspections@palmspringsca.gov |
| City Hall switchboard | 760-323-8299 |
Palm Springs permit types
To apply, create an account in Palm Springs Online, choose Apply on the home page and search for the application that matches the project, taking care to select the correct permit type. The department posts user guides for the portal and keeps its forms and handouts, plan review and building code information on separate pages. Questions about an application or its status go to the Permit Center technicians by email.
Residential permits
Detached one- and two-family homes and townhouses up to three stories, with their accessory structures, are permitted under the California Residential Code categories of the fee schedule. New homes are priced from a 1,200 sq ft base, additions and remodels from a 200 sq ft base, each with an add-on per extra 100 sq ft. Pools and spas, walls and fences, re-roofs and demolition each have their own lines, and the schedule also lists simple mechanical, electrical, plumbing and building permits at $284 each.
Building or remodeling a home here? Alliance handles residential permit applications, so the crew isn't waiting on the counter.
Commercial permits
Every other building, including apartments, offices, shops and hotels, falls under the California Building Code categories: new buildings and additions are priced from a 2,500 sq ft base and remodels from a 500 sq ft base, with add-ons per extra 500 sq ft. Signs are priced by area. The fee schedule also prices a temporary certificate of occupancy and hourly reviews of disabled access hardship waivers.
For tenant improvements and new commercial builds, Alliance handles commercial building permits through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Planning. Planning fees tied to the permit are collected by the Building Safety Department when the permit is issued.
- Engineering. New construction pays the city’s sewer facility fee before the building permit is granted, and properties outside the city connecting to city sewer pay twice the in-city rate.
- Fire. Fire plan review and inspection fees are part of the same comprehensive schedule.
- Addresses. A new address is assigned on request for $353 per address.
Not sure this scope needs a permit?
Get a free quote →Palm Springs permit fees
Building permit fees are in the Comprehensive Fee Schedule for FY 2025–2027; the Building and Safety section prices permits by type and area rather than by a valuation table. Permit technicians explain how fees are calculated at 760-322-8398.
| Item | Fee |
|---|---|
| Permit issuance | $328 per building permit |
| New home (residential code) | $2,415 up to 1,200 sq ft, plus $345 per extra 100 sq ft |
| Home addition | $1,424 up to 200 sq ft, plus $316 per extra 100 sq ft |
| Home remodel | $1,147 up to 200 sq ft, plus $36 per extra 100 sq ft |
| Commercial new building or addition | $3,590 up to 2,500 sq ft, plus $369 per extra 500 sq ft |
| Commercial remodel | $1,854 up to 500 sq ft, plus $142 per extra 500 sq ft |
| Simple permit: mechanical, electrical, plumbing or building | $284 each |
| Pool and spa | $1,351 up to 600 sq ft, plus $4 per extra sq ft |
| Walls and fences | $870 up to 100 linear feet, plus $312 per extra 100 feet |
| Re-roof | $277 up to 3,000 sq ft, plus $6 per extra 100 sq ft |
| Signs | $277 up to 200 sq ft, plus $211 per extra 100 sq ft |
| Complete demolition | $447 |
| Additional inspection | $256 |
| Inspection outside normal hours (weekends, holidays) | $380 per hour, 3-hour minimum |
| Permit extension request | $297 |
| Temporary certificate of occupancy | $532 |
| Technology fee | $1.09 per $1,000 of building valuation |
Worked example: a 400 sq ft addition to a house is $1,424 for the first 200 sq ft plus 2 × $316, or $2,056. With the $328 issuance fee that is $2,384, and if the job is valued at $80,000 the technology fee adds $87.20, for $2,471.20 before state fees, the construction tax and any Planning, Engineering or Fire charges. A 2,000 sq ft new home works out the same way: $2,415 plus 8 × $345, or $5,175, plus $328.
Work started without the required permits pays double the normal fee. Fast-track plan review, when offered, costs twice the plan review fee. Staff time is billed at $138 an hour for a building inspector, $145 for a plans examiner and $231 for the Building Official.
Rather talk it over?
Call 1-855-478-4290 →Fees collected for others. The construction tax applies to any new building, addition or trailer space, except additions to an existing single-family home valued at no more than $3,550. The Local Development Mitigation Fee is charged on all permits for new homes and nonresidential buildings; from July 1, 2026 the conservation commission’s rate is $1,785 per home at up to 8 units per acre and $7,930 per acre for commercial or industrial land. The Transportation Uniform Mitigation Fee is charged on new development and on changes of use that add vehicle trips, with low- and lower-income housing exempt; the 2026 rates are $2,900 per single-family home, $1,670 per multifamily unit and $4,400 per hotel room. The state SB 1473 fee applies to every building permit and the strong motion fee to new construction.
Trade permits and who may pull them in Palm Springs
Electrical, gas, mechanical and plumbing permits come from the same department. The fee schedule lists simple mechanical, electrical and plumbing permits at $284 each; it does not say which jobs qualify, so ask the Permit Center which permit fits a stand-alone trade job. Before the final on new work, a final electrical inspection releases the electric meter for testing.
- Who files. The owner or the owner’s authorized agent applies; contractors working in California must be licensed by the state, and the department points owners to the Contractors State License Board lookup to check a license.
- Water heaters and HVAC. The department reminds owners that water heaters must meet seismic strapping, relief valve, elevation and location rules, and inspectors check HVAC installations against the code and energy standards.
- Business license. The city’s business license tax program falls under Chapters 3.40 to 3.96 of the municipal code. Applications and renewals are made in the city’s customer service portal, renewal reminders come by email only, and a reference sheet explains who needs a license.
How to apply for a Palm Springs building permit
Use the department’s permit questions for fences, patio covers, sheds, HVAC, re-roofs and water heaters.
Register in Palm Springs Online; the portal’s user guides cover the first steps.
Select Apply and search for the application that matches the work.
Attach the plans and documents to the application in the portal.
Respond to plan review corrections; status questions go to the Permit Center by email.
Pay the issuance fee, permit fee, technology fee and the related city and regional fees collected at issuance.
Paper plans of a legible size must be on site for every inspection.
Rather not deal with the building department?
Get a free quote →Review, corrections and what causes delay
The Permits page asks applicants to be sure they select the correct permit type. Reviews beyond the standard scope, such as alternate materials or code research, and Board of Appeals matters are billed by the hour at the staff rate. A permit extension request is $297. Starting work before the permit is issued doubles the fee, and unpermitted work must be legalized or removed.
Inspections in Palm Springs
Inspections are requested in the Palm Springs Online self-service portal: open My Work, select the permit, go to the Inspections tab, pick the inspection and click Request Inspection. If the type you need is not offered, book any available inspection and say in the note which one you need. A requested date is not guaranteed, and the daily inspection schedule is posted in the portal. Cancellations and reschedules go by email to the inspection supervisor listed on the Inspections page by 8:00 a.m. on the day of the inspection. Inspector comments are under My Inspections, on the Checklist tab.
- Below ground and foundation: underground plumbing, gas and electrical, then footings checked for setbacks, flood-control elevation, size and reinforcing steel, with hold-downs and anchor bolts in place.
- Structure: roof sheathing (truss calculations on site), wrap (shear walls, and windows installed for egress, glazing and flashing checks), and framing with rough plumbing, mechanical and electrical.
- Tests and finishes: drain and vent piping filled with water to the vents, insulation against the energy rules, drywall, lath, and a gas test of 10 psi for 15 minutes after drywall.
- Final: the electric final release comes first; the final covers fixtures, water heater strapping, appliances, smoke alarms, handrails and guards, rated construction, accessibility and drainage around the building.
Legible paper plans of sufficient size must be on site for every inspection. Extra inspections are $256, and inspections outside normal hours on weekends or holidays are $380 an hour with a three-hour minimum.
California building code in Palm Springs
The department posts code information on its Building Codes page. FEMA’s Community Status Book lists Palm Springs (community 060257) as participating in the National Flood Insurance Program, with a current flood map dated April 19, 2017, and as a Community Rating System member at class 6, with a 20% discount. Footing inspections check form elevations against the city’s flood control requirements.
Want this handled start to finish?
Get a free quote →California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
Palm Springs building permit FAQ
Who issues building permits in Palm Springs?
The city’s Building Safety Department at City Hall, 3200 E. Tahquitz Canyon Way (760-322-8398). Riverside County permits only unincorporated land.
Do I need a permit for a fence or wall in Palm Springs?
Yes, if it is over 3 feet high measured from finished grade to the top of the wall.
Do I need a permit for a shed?
Not for a shed or playhouse up to 120 sq ft with no plumbing, mechanical or electrical work, within the 10-foot height limit (15 feet in R-1-AH and R-1-A). Setback rules still apply.
Do I need a permit to re-roof?
Yes, to repair or replace roofing over 100 sq ft. The re-roof fee is $277 up to 3,000 sq ft plus the $328 issuance fee.
How much is a building permit in Palm Springs?
Fees depend on type and area: a 400 sq ft home addition is $2,056 plus the $328 issuance fee and a technology fee of $1.09 per $1,000 of valuation.
How do I book an inspection?
Request it in Palm Springs Online under My Work and the permit’s Inspections tab. Keep printed plans on site.
What happens if work was done without a permit?
Apply to legalize it through the permit process, at double the normal fee for work started without permits, or remove it under a demolition permit.
Palm Springs permit search and official resources
Permit status questions go to the Permit Center technicians at buildingsafetydepartment@palmspringsca.gov. Copies of building records are requested through the department’s Building Records request, and the City Clerk keeps public documents in Document Central.
Inspections are where schedules slip.
Get a free quote →- Building Safety Department
- Permits and common permit questions
- Plan review
- Inspections
- Inspection guidelines (PDF)
- Building permit and review fees
- Comprehensive Fee Schedule FY 2025–2027 (PDF)
- Applications, forms and handouts
- Building codes
- Business licenses
- City Clerk Document Central
- CVAG Transportation Uniform Mitigation Fee
- CVCC Local Development Mitigation Fee
- California Building Standards Code (Title 24)
Simplify Palm Springs permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Palm Springs sooner?
Let Alliance prepare, file, and track your Palm Springs permits while your crew stays on the job.
More California permitting guides
Riverside County
Read guide →Perris
Read guide →Rancho Mirage
Read guide →Palmdale Building Permit Guide
Read guide →Palo Alto Building Permit Guide
Read guide →Palos Verdes Estates Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Palm Springs permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.