Building permits in San Bruno come from the city’s Building Division, part of the Community Development Department at City Hall, 567 El Camino Real (650-616-7074, option 2). Every application, plan upload, fee payment and inspection request runs through SB Permits, the city’s name for its MyGovernmentOnline portal. Fees come from the FY 2025-26 Master Fee Schedule: a 400 sq ft wood-frame addition is valued at $119,200 and carries a $3,165 building permit fee before plan review and other charges.
What requires a building permit in San Bruno?
San Bruno’s 2025 handout quotes the permit rule and exemption list of the 2025 California Building Code: building, enlarging, altering, repairing, moving, demolishing or changing the occupancy of a building, or installing or replacing regulated electrical, gas, mechanical or plumbing systems, needs a permit first.
No building permit (city exemption list)
- One-story detached sheds, playhouses and similar structures up to 120 sq ft
- Fences up to 7 ft high
- Retaining walls up to 4 ft, measured from the bottom of the footing, that hold back no surcharge
- Painting, papering, tiling, carpeting, cabinets, countertops and similar finish work
- Above-ground prefabricated pools at a house that are under 24 inches deep and hold no more than 5,000 gallons
- Stopping leaks and clearing stoppages, as long as no pipe, valve or fixture is replaced or moved
Permit needed (fee schedule and handouts)
- New homes, additions, ADUs and junior ADUs
- Kitchen and bathroom remodels, even like-for-like
- Re-roofs and window replacements
- Decks, attached patio covers and skylights
- Water heater replacements and electrical service upgrades
- Pools and spas, solar, battery storage and EV chargers
- Demolition, building relocation and tenant improvements
Exemptions only lift the permit itself; the work must still meet the code and the city’s zoning. Emergency repairs to equipment may start first, but the permit application must reach the building official by the next working business day.
What San Bruno decides and what the state holds
The building code is the statewide Title 24 code. The city sets its permit process, fees, zoning and design review, and its construction time limits (Chapter 11.34 of the municipal code). Since March 2026 it has also required boundary surveys by a licensed land surveyor for all new construction, and for additions, accessory structures with foundations and retaining walls built within 3 inches of a required setback or easement or within 5 feet of a property line. No building permit is issued until the survey is complete and recorded with the San Mateo County Recorder.
San Bruno building department: who handles permitting
The city’s Building Division issues building permits and takes in plans for review for every property inside San Bruno, and its field inspectors check residential and commercial work against the state codes and city ordinances. The city’s staff directory names Darcy Axiaq as Chief Building Official, and the Chief Building Official sets the construction valuation used for fees. Coordinated plan review sends one submittal to Building, Fire, Planning and Public Works.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Building Division, Community Development Department, City Hall, 567 El Camino Real, San Bruno, CA 94066 |
| Counter hours | Monday to Thursday, 7:30 a.m. to 5:00 p.m.; City Hall is closed to the public Friday to Sunday |
| Phone | 650-616-7074 (option 2 Building, option 3 Planning) |
| building@sanbruno.ca.gov; planning@sanbruno.ca.gov | |
| Legacy-permit inspections | 650-616-7076 |
| Portal help | MyGovernmentOnline help desk, 985-851-0760 |
| Business licenses | 650-273-4371 |
San Bruno permit types
SB Permits is the city’s name for its MyGovernmentOnline (MGO Connect) portal, so existing MGO accounts keep working; it handles applications, plans, fees, permits, job cards and inspections, also through the MGO Connect mobile app. The fee schedule shows the main record types: building permits, electrical, mechanical and plumbing permits, demolition and moved-building permits, and fixed-fee permits for common jobs.
Residential permits
The Building Division posts 2025 handouts for remodels, re-roofs, decks, patios, skylights, egress windows, water heaters and service upgrades, plus residential submittal and plot plan checklists. Every applicant, whether an owner-builder or a licensed contractor, signs the city’s applicant declaration confirming the answers given in the portal. Rooftop solar on houses up to 38 kW, with or without a battery, goes through SolarAPP+ for an automated code review before the city permit is issued in SB Permits; systems over 38 kW, systems with an EV charger, multi-family and commercial solar apply directly. ADUs follow their own path, described below.
Building or remodeling a home here? Alliance handles residential permit filing, so the crew isn't waiting on the counter.
Commercial permits
Tenant improvement plans must be stamped by the licensed designer at submittal and wet-signed before issuance, carry the construction best management practices sheet, and show the accessible parking and accessible route from the public right of way. PDF plans go in at 1/4-inch scale with the Title 24 energy report and structural calculations. Debris must stay in covered bins on site, at least 65% of the waste must be recycled, and a recycling receipt is needed before final approval.
For tenant improvements and new commercial builds, Alliance handles commercial permit expediting through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Planning. Since July 2026, Architectural Review Permits for home alterations, facade, site and landscape changes, use permits and sign permits are filed in SB Permits. Variances, planned development permits, new commercial projects, subdivisions and SB 330 housing still go by email to the Planning Division. An administrative minor Architectural Review Permit in the R-1 or R-2 zones is $2,610, and a Planning Commission review is $5,072.
- Height surveys. Work within one foot of the height limit may need a surveyor’s height survey, in hand at the roof nail inspection.
- ADUs. Plans are routed to the Building, Fire, Planning and Public Works reviewers. First review takes 3 to 4 weeks and later rounds 1 to 2 weeks, and the applicant has one year to answer corrections. The site must meet fire flow under the fire code, and each unit needs its own gas and electric meters unless exempt.
- Outside agencies. School district fees and other agencies’ charges are paid separately.
San Bruno permit fees
The fees page links the FY 2025-26 Master Fee Schedule, effective July 1, 2025; the city says it usually updates the schedule every year. Building permit fees come from a valuation table. The Chief Building Official sets the valuation from the Engineering News Record cost index with a San Francisco Bay Area modifier of 1.21, published as a per-square-foot table: wood-frame (Type V) dwellings are valued at $298 per sq ft, remodels at $185, unfinished basements at $55 and wood-frame garages at $74.
| Item | Fee |
|---|---|
| Value $2,001 to $25,000 | $522 plus $21 per extra $1,000 or fraction |
| Value $25,001 to $50,000 | $1,003 plus $30 per extra $1,000 |
| Value $50,001 to $100,000 | $1,734 plus $24 per extra $1,000 |
| Value $100,001 to $500,000 | $2,885 plus $14 per extra $1,000 |
| Value $500,001 to $1,000,000 | $8,279 plus $33 per extra $1,000 |
| Permit issuance (building, electrical, mechanical or plumbing) | $98 each |
| Electrical, mechanical or plumbing system fee | 20% of the building permit (residential); 18% (non-residential) |
| Coordinated plan review, single-family addition | 4.4% of value up to 500 sq ft; 3.8% for 501–1,000 sq ft; 3.7% above |
| Like-for-like kitchen / bathroom remodel | $588 / $539 |
| House or duplex re-roof | $343 |
| House or duplex windows, 1–5 / over 5 | $392 / $490 |
| Electrical permit, new in-ground pool at a home | $587 |
| Demolition, house or small commercial building | $537 |
| Technology fee / General Plan maintenance | 5% of permit fees / 0.9% of valuation |
| Re-inspection | First free; then $195 each |
Rather talk it over?
Call 1-855-478-4290 →Instant solar permits are flat: $441 for a house solar system up to 38 kW, $641 with battery storage, $690 with storage and an EV charger, $543 for storage alone and $245 for an EV charger alone. Other charges include an art fee of 5% of residential (7% of commercial) permit fees, $195 an hour for inspections with no set fee, $251 an hour for the fourth and later plan reviews, and a construction and demolition debris deposit of $63 per estimated ton ($1,000 minimum). Development impact fees for a new single-family home total $31,811.22 per unit, and for-sale single-family units also pay a $1,000 residential tax.
Worked example: a 400 sq ft wood-frame addition is valued at 400 x $298 = $119,200. That falls in the $100,001 to $500,000 band: $2,885 plus 20 steps of $1,000 (a fraction counts as a full step) at $14, a building permit fee of $3,165. Coordinated plan review for a small single-family addition is 4.4% of value, $5,244.80, and the General Plan maintenance fee is $1,072.80, before the issuance, technology, art and state fees.
Trade permits and who may pull them in San Bruno
Electrical, mechanical and plumbing permits are issued by the Building Division in SB Permits. On a new building or addition they are charged as a share of the building permit fee; stand-alone work uses unit fees, such as $195 for an electrical service up to 200 amps, $195 for a furnace up to 100,000 Btu/h and $98 for a water heater, each plus the $98 issuance fee.
- Contractors. Each contractor working in the city needs a San Bruno business license. The owner-builder or general contractor must hand in a subcontractor list with each sub’s license class and number and city business license number before work starts, and the city will not inspect work by subcontractors who are not on it.
- Owner-builders. Owners who pull their own permit complete the city’s owner-builder disclosures and forms and sign the applicant declaration as owner-builder.
- Solar installers must register with SolarAPP+ and complete its training before applying for an instant permit.
San Bruno’s voter-approved business tax is due with the application and again every July 1. Businesses that will operate in town also need zoning conformance from Community Development.
How to apply for a San Bruno building permit
Ask Planning (option 3) whether an Architectural Review Permit or other approval is needed, and whether the boundary survey policy applies.
Follow the digital plan requirements: one PDF set or one per discipline, every sheet bookmarked, and a 3 by 3 inch blank space in each title block for city stamps.
Select New Account, or sign in with an existing MyGovernmentOnline login.
Choose the permit type, answer the questions, upload plans and forms, and attach the signed applicant declaration.
A permit technician emails you when it is due; plan review starts after payment.
Reviewers from Building, Fire, Planning and Public Works send comments through the portal; resubmit until all approve.
Pay the remaining fees online or at the counter and download the permit and job card.
Rather not deal with the building department?
Get a free quote →Review, corrections and what causes delay
The coordinated plan review fee covers three rounds; from the fourth review on, and for revisions and requests for information, the city bills by the hour. Missing boundary surveys hold up issuance, and plans changed after approval need a resubmittal before the work is built. Once issued, a permit has a time limit set by its valuation: 6 months up to $50,000, 12 months up to $500,000, 18 months up to $1 million, 24 months up to $3 million and 36 months above that. One 6-month extension may be granted for good cause if requested before the permit expires. After a 30-day grace period, daily fines start at $200 and can reach $250,000.
Inspections in San Bruno
Open the project in SB Permits, choose Request Inspection, pick the inspection type, the date and an inspection window, and put the on-site contact’s phone number in the notes. The inspector calls that morning to confirm the time. Requests must be in by 3 p.m. for the next day, and cancellations by 3 p.m. the day before to avoid a re-inspection fee. For permits from the older system, call 650-616-7076 at least 24 hours ahead with the permit number; morning inspections run 7 a.m. to noon and afternoon ones 1 to 4:30 p.m.
The city’s residential checklist sets the order: underground utilities, forms and footings, underfloor plumbing and framing, exterior shear and roof nail, rough mechanical, electrical and plumbing, fire sprinklers where required, rough framing, insulation, drywall, shower pan and interior lath, exterior lath, and final. Work must be complete and walked by the contractor before the inspector arrives, special inspection reports must be ready, and the job card and approved plans must be on site. Projects with planning entitlements or design conditions also need a final inspection by a city planner. The checklist still prints a $156 re-inspection fee; the adopted Master Fee Schedule makes the first re-inspection free and charges $195 for each later one.
California building code in San Bruno
The Building Division enforces the California building, residential, plumbing, mechanical, electrical and energy codes, and its handouts are written to the 2025 California codes. FEMA’s Community Status Book lists the city (community 060326) as participating in the National Flood Insurance Program, with a current map dated April 5, 2019, and the division posts a flood zone construction material guide and defensible space handouts.
California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
Want this handled start to finish?
Get a free quote →San Bruno building permit FAQ
Who issues building permits in San Bruno?
The city’s Building Division in the Community Development Department at City Hall, 567 El Camino Real. Call 650-616-7074 and choose option 2.
How much is a building permit in San Bruno?
It depends on value. A $119,200 addition has a $3,165 permit fee under the FY 2025-26 schedule, plus plan review, issuance and other charges. Simple jobs have flat fees, such as $343 for a house re-roof.
Do I need a permit for a fence or shed?
Fences up to 7 ft and one-story sheds up to 120 sq ft are on the city’s exemption list, but zoning rules still apply.
How long does plan review take?
For ADUs the city gives 3 to 4 weeks for the first review and 1 to 2 weeks for each later round. Eligible house solar systems are approved instantly through SolarAPP+.
When do I need a boundary survey?
For all new construction, and for additions, accessory structures with foundations or retaining walls within 3 inches of a setback or easement or within 5 feet of a property line.
Do contractors need a city business license?
Yes. Every contractor and subcontractor working in San Bruno needs one, and unlisted subcontractors’ work is not inspected.
San Bruno permit search and official resources
Applicants follow their own permits, inspections and documents in SB Permits. Older city records are kept in the City Documents Portal, and the Building Division (building@sanbruno.ca.gov) can say where a past permit or plan set is filed.
Inspections are where schedules slip.
Get a free quote →- San Bruno Building Division
- SB Permits portal
- Apply for a building permit
- Online permits help
- Building permit fees
- Master Fee Schedule FY 2025-26 (PDF)
- 2025-26 building valuation table (PDF)
- Work exempt from permits (PDF)
- Building permit time limits (PDF)
- Boundary survey policy (PDF)
- Handouts and guides
- Tenant improvement plan requirements (PDF)
- Subcontractor list (PDF)
- Applicant declaration (PDF)
- Digital plan requirements (PDF)
- Residential inspection checklist (PDF)
- Permit refund policy (PDF)
- Owner-builder disclosures (PDF)
- Inspections
- Expedited solar permits
- ADUs and junior ADUs
- Planning applications
- Business license
- City Documents Portal
- Community Development Department
Simplify San Bruno permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in San Bruno sooner?
Let Alliance prepare, file, and track your San Bruno permits while your crew stays on the job.
More California permitting guides
San Mateo County
Read guide →San Carlos
Read guide →San Mateo
Read guide →San Clemente Building Permit Guide
Read guide →San Diego Building Permit Guide
Read guide →San Diego County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about San Bruno permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.