In San Carlos, building permits are issued by the city’s Building Division in the Community Development Department at City Hall, 600 Elm Street ((650) 802-4261, building@cityofsancarlos.org). Applications, plans and inspection requests go through the city’s Tyler Enterprise Permitting & Licensing self-service portal, and paper plans are not accepted. Fees follow the FY 2026-27 Cost of Services schedule: a 400 sq ft house addition is valued at $92,800 and carries a $3,255.93 building permit fee and a $2,441.77 plan check fee.
What requires a building permit in San Carlos?
The Building Division’s own answer is that almost any construction needs a permit, and that it is easier to list what does not. In general that means mechanical or structural work (the city’s examples are cabinets, doors, windows and roofs), plumbing work such as sinks, irrigation and water heaters, and electrical work for appliances, furnaces, garage door openers and pool pumps. A water heater needs a permit whether a plumber installs it or the owner does.
No building permit (city FAQ)
- Side and rear yard fences 6 ft high or less (front yard fences are limited to 4 ft, and 3 ft inside a corner lot’s sight triangle)
- Wood retaining walls 3 ft or shorter, and masonry or concrete walls under 4 ft measured from the bottom of the footing
- Detached one-story sheds and greenhouses up to 120 sq ft, within Planning’s location and height limits
- Painting and wallpapering
- Replacing a toilet like for like
Permit needed (city FAQ)
- Re-roofs, which must be at least Class B rated
- Furnace and water heater replacements
- Pools, spas and hot tubs, which also need security fencing
- Sink replacements and similar plumbing (simple plumbing permits)
- Additions, new homes, decks, remodels and tenant improvements
- Sheds and greenhouses over 120 sq ft
Work in the street right of way, including a fence or retaining wall too close to the street or a connection to the city storm drain, needs an encroachment permit from Public Works ((650) 802-4195). Air-conditioning condensers must sit in the rear half of the lot; a 25 ft setback from property lines generally meets the city’s noise limits, and every unit needs 3 ft of working clearance.
What San Carlos decides and what the state holds
Plans must follow the 2025 California code cycle; the city’s technical building codes are in Chapter 15.04 of its municipal code. The Building Division publishes the local design values it applies: climate zone 3, seismic zone E, a 91 mph basic wind speed, exposure categories B to D, soil hazard zones A and B (B the stricter) and a 1,500 psf soil bearing value, below which a soils report is needed. The wildland-urban interface covers the area south of San Carlos Avenue and west of Alameda de las Pulgas. After recent court decisions, the city is not enforcing its rules that banned natural gas infrastructure in new buildings.
San Carlos building department: who handles permitting
The city’s Building Division issues building permits for all property inside San Carlos. It guides applicants through the process, reviews applications against local rules and state and federal codes, inspects the work and enforces the municipal code. The Planning Division, a separate division on the first floor of City Hall, reviews height, size, use and neighborhood impact, and its approval comes before a new home or addition goes to the Building Division.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Building Division, Community Development Department, City Hall, 600 Elm Street, San Carlos, CA 94070 |
| Phone / email | (650) 802-4261; building@cityofsancarlos.org |
| Inspections | Portal requests; changes and cancellations to inspections@cityofsancarlos.org |
| Planning Division | (650) 802-4263; planning@cityofsancarlos.org |
| Public Works (encroachments) | (650) 802-4195 |
| Portal | Customer Self-Service, Tyler Enterprise Permitting & Licensing |
San Carlos permit types
All permit and planning applications are processed in the city’s Tyler Enterprise Permitting & Licensing system. Applicants create a profile in the Customer Self-Service portal, start the application there and upload the completed one-page Building Permit Application Form as an attachment. The fee schedule shows the main record types: building permits by valuation, electrical, plumbing and mechanical permits, demolition, grading for pools and other work, and solar permits.
Residential permits
For new homes and additions, the city’s checklist asks for digital architectural plans at a minimum 1/4-inch scale with a site plan showing every setback, floor plans, elevations and construction sections, plus a landscaping plan, a demolition and tree protection plan, the Planning conditions and a reference set of civil plans. Title 24 energy forms are required for any added conditioned space, and structural plans, calculations, a soils report and a survey may be required. Plans may be drawn by a licensed architect or by an unlicensed designer; an architect’s plans must be stamped and signed. Residential solar must go through SolarAPP+, and the permit number arrives by email, usually within 1 to 2 business days.
Building or remodeling a home here? Alliance handles residential permit filing, so the crew isn't waiting on the counter.
Commercial permits
The Building Division keeps a separate checklist for tenant improvements and commercial additions, duct test requirements for new commercial buildings and for commercial alterations and change-outs, an EV charging station checklist and a fire safety checklist for business owners. Commercial solar and other systems not eligible for SolarAPP+ apply in the portal with a permit application form, and manual review usually takes three to five business days.
For tenant improvements and new commercial builds, Alliance handles commercial permit expediting through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Planning. A new home or addition starts with the Single Family Residential Compliance Review application; most houses are in the RS-6 or RS-3 zones and must meet the city’s objective design standards. The FY 2026-27 planning fees are $3,378 for a first-floor addition reviewed by staff, $5,065 for a second-floor addition reviewed by staff, $8,443 for a first-floor addition with notification and $11,821 for a new home or a second-floor addition with notification.
- Other planning approvals. A use permit before the Planning Commission is $10,132, a minor use permit from the Zoning Administrator $5,065, a variance $13,510 and planning review of accessory structures, including large decks, $2,026.
- Soils and survey. Ask the Building Division which soil hazard zone the property is in; the survey handout lists the city’s requirements.
- Encroachment permits from Public Works for work in the right of way.
San Carlos permit fees
Building fees come from the FY 2026-27 Cost of Services (user fee) schedule, marked adopted and effective July 1, 2026. Single-family work and multi-family, commercial and industrial work have separate valuation tables, each with a building permit fee and a plan check fee. Value is set from the schedule’s permitted values: $232 per sq ft for new residential space and additions, $117 for interior remodels, $48 for garages and accessory structures, $39 for decks and $57 for commercial shells and tenant improvements.
| Item | Fee |
|---|---|
| Value under $5,000 | Permit $348; plan check $291 |
| Value $5,000 to $24,999 | Permit $348 plus $34.84 per extra $1,000; plan check $291 plus $24.68 |
| Value $25,000 to $49,999 | Permit $1,045 plus $32.51 per extra $1,000; plan check $784 plus $24.39 |
| Value $50,000 to $99,999 | Permit $1,858 plus $32.51 per extra $1,000; plan check $1,393 plus $24.39 |
| Value $100,000 to $499,999 | Permit $3,484 plus $9.88 per extra $1,000; plan check $2,613 plus $7.41 |
| Value $500,000 to $999,999 | Permit $7,432 plus $7.43 per extra $1,000; plan check $5,574 plus $5.57 |
| Electrical, plumbing or mechanical, new home or addition | $232 for the first 1,700 sq ft, then $0.09 per sq ft (each trade) |
| Main electrical service or sub-panel | $278 |
| Solar PV permit | $348 |
| Water heater replacement | $117 |
| Furnace or HVAC replacement / new | $232 / $372 |
| Second and later re-inspections | $232 per hour (1 hour minimum) |
| Additional plan check | $232 per hour |
| Technology fee | 0.4% of the total permit fee |
| General Plan maintenance | 0.65% plus 0.09% of value, new construction and additions |
Rather talk it over?
Call 1-855-478-4290 →Each fee step is per $1,000 or fraction above the band’s starting value. Construction time-limit extensions are charged per 60-day extension, at 0.5% of project value for the first, 1.0% for the second and 1.5% for the third (the Building Official may waive the fee), and projects left unfinished beyond their time limit pay daily penalties of 0.01% to 0.02% of project value after a 30-day grace period. New homes also pay impact and connection charges set for FY 2026-27, including a park facility fee of $2,722 per bedroom and a sewer capacity charge of $14,929 per single-family unit, which is due before the building permit is issued.
Worked example: a 400 sq ft single-story house addition is valued at 400 x $232 = $92,800, in the $50,000 to $99,999 band. The $42,800 above $50,000 counts as 43 steps, so the building permit fee is $1,858 + 43 x $32.51 = $3,255.93 and the plan check fee is $1,393 + 43 x $24.39 = $2,441.77, before trade permits, the technology and General Plan fees, state fees and planning review.
Trade permits and who may pull them in San Carlos
Electrical, plumbing and mechanical permits are issued by the Building Division through the same portal. Most furnace replacements are done by mechanical contractors and most re-roofs by roofing contractors, who pull the permits themselves; a sink replacement takes a simple plumbing permit, and an EV charger installation is usually reviewed in 1 to 2 days.
- Owners. The owner may do the work on an owner-occupied home or hire someone else; the city keeps an owner-builder application among its forms.
- Contractors must be licensed and carry the proper insurance and a San Carlos business license. Solar installers must show an active city business license before applying.
- Business license. Businesses based outside the city still need one to work in San Carlos: $172 for 6 months or $289 for 12 months, each including the $4 state fee.
How to apply for a San Carlos building permit
Look up the parcel on the city’s interactive zoning map and read the development standards for its zone.
For a new home or addition, file the Single Family Residential Compliance Review; Planning approval comes before the building submittal.
Use the city’s checklist for new homes, additions or tenant improvements, and find out the property’s soil hazard zone and whether it is in the WUI area.
Create a profile in Customer Self-Service, start the application and upload the plans and the one-page Building Permit Application Form.
Respond to review comments and resubmit; rechecks usually take 10 days to 2 weeks.
Pay by MasterCard or Visa; the permit card and approved plans arrive by email.
Rather not deal with the building department?
Get a free quote →Review, corrections and what causes delay
The city’s typical review times are 1 to 2 weeks for a deck, 1 to 3 weeks for an interior remodel, 3 to 5 days for a kitchen and bath remodel, 2 to 4 weeks for a single-story addition, 3 to 5 weeks for a second-story addition, 4 to 6 weeks for a new house or a new commercial building, 6 to 8 weeks for new multi-family housing, 2 to 4 weeks for tenant improvements and 1 week for revisions to issued permits. Fire sprinkler plans take 10 to 15 days and fire alarm plans 2 to 3 weeks. Applying before Planning has approved the project, missing soils or survey documents, and plans that leave out the Planning conditions all send a job back.
Inspections in San Carlos
Inspections are requested in the Customer Self-Service portal. New users create an account, then email inspections@cityofsancarlos.org with the permit numbers to link to it. Once staff confirm a request it shows under Scheduled in My Inspections. On the day, the 90-minute arrival window appears on the portal’s Today’s Inspections page after 8:30 a.m.; no login is needed to see it. Reschedules and cancellations go by email. Inspectors decide case by case whether an inspection is done in person, virtually, by photos or through a special inspector.
The contractor must keep a paper copy of the stamped, approved plans at a proper scale on site; color is recommended. A permit becomes void 180 days after the last major inspection, so a stalled job needs an extension request by email with the reason and expected completion date. Construction noise is allowed 8 a.m. to 5 p.m. on weekdays and 9 a.m. to 5 p.m. on Saturdays, including setup, cleanup and deliveries, and not on Sundays or ten listed holidays.
California building code in San Carlos
San Carlos plan checklists are written to the 2025 California code cycle, and the Building Division links the 2025 California Wildland-Urban Interface Code for the WUI area. FEMA’s Community Status Book lists San Carlos (community 060327) as a participating community in the National Flood Insurance Program, with a current map dated April 5, 2019, and as a Community Rating System class 9 community, which gives a 5% flood insurance discount.
California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
San Carlos building permit FAQ
Who issues building permits in San Carlos?
The city’s Building Division at City Hall, 600 Elm Street; call (650) 802-4261 or email building@cityofsancarlos.org.
Can I drop off paper plans?
No. San Carlos takes digital submittals only, through its Tyler Customer Self-Service portal, and sends approved plans and permit cards by email.
Want this handled start to finish?
Get a free quote →How much does a permit for an addition cost?
A 400 sq ft house addition valued at $92,800 has a $3,255.93 building permit fee and a $2,441.77 plan check fee under the FY 2026-27 schedule, plus trade, technology, General Plan and planning fees.
Do I need a permit for a fence?
Not for a side or rear yard fence of 6 ft or less. Front yard fences may not exceed 4 ft, and corner lots have a 3 ft limit in the sight triangle.
Do I need a permit to replace a water heater or roof?
Yes, for both. A water heater needs a permit even if you install it yourself, and new roofing must be at least Class B rated.
How long does plan review take?
From 3 to 5 days for a kitchen and bath remodel to 4 to 6 weeks for a new house and 6 to 8 weeks for new multi-family housing.
Is my property in the wildland-urban interface?
The city’s WUI area lies south of San Carlos Avenue and west of Alameda de las Pulgas; the Building Division confirms a specific address.
San Carlos permit search and official resources
Current permits, inspections and approved plans are in the Customer Self-Service portal. Past permit and plan records are requested from the City Clerk’s Office through a public records request; the Building Division says its files are most complete for homes built from 1980 on, and copies of plans need the written permission of the owner and of any architect or engineer who signed them.
Inspections are where schedules slip.
Get a free quote →- San Carlos Building Division
- Building permits and FAQ
- Customer Self-Service permit portal
- Forms and handouts
- Checklist for new homes and additions (PDF)
- Request a building inspection
- Inspection information (PDF)
- Solar permitting
- City fees and cost of services
- FY 2026-27 building fees (PDF)
- FY 2026-27 planning fees (PDF)
- FY 2026-27 impact fees (PDF)
- Building a new home or addition
- Planning Division
- Encroachment permits
- Business license
Simplify San Carlos permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in San Carlos sooner?
Let Alliance prepare, file, and track your San Carlos permits while your crew stays on the job.
More California permitting guides
San Mateo County
Read guide →San Mateo
Read guide →South San Francisco
Read guide →San Clemente Building Permit Guide
Read guide →San Diego Building Permit Guide
Read guide →San Diego County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about San Carlos permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.