In Montclair, building permits are issued by the City’s Building Division in the Community Development Department at City Hall, 5111 Benito Street (909-625-9477), where Louis Vasquez is the Building Official. Most permits are obtained in person over the counter, Monday to Thursday from 7:00 to 9:00 a.m. and 4:00 to 5:30 p.m., and first plan reviews take about two weeks. Fees come from the City’s 2022 Master User Fee Schedule, which charges $39 to issue each permit plus plan check and inspection fees set by project type and size.
What requires a building permit in Montclair?
New buildings, additions, remodels and the electrical, plumbing and mechanical work inside them go through the Building Division’s plan check and permit process. Montclair also publishes triggers for small projects that owners often assume are exempt.
- New homes, garages, accessory buildings and room additions
- Residential remodels, garage conversions and new interior walls
- Every patio cover and patio enclosure
- Masonry walls 24 inches high or more, retaining walls and pilasters
- All fences (the Public Works encroachment handout says a building permit is required for every fence)
- Reroofing, skylights, replacement windows and doors, siding and stucco
- Pools, spas and pool demolition
- Water heaters, furnaces, plumbing fixtures, electrical services and solar systems
- Demolition and grading
The City’s permit pages publish no list of exempt work; ask the Building Division (909-625-9477) before starting a job you believe needs none.
Fence and wall design (materials, height and the corner sight-line cut-off) is set by Section 11.38.050 of the Montclair Municipal Code and checked by the Planning Division, while the structure of masonry and retaining walls is checked by the Building Division.
What Montclair decides and what the state holds
The City Council adopted the 2025 California Building Standards Code by Ordinance No. 25-1016, effective in Montclair on January 14, 2026. The Building Division publishes its own design criteria for plans: Seismic Design Category D, E or F as the California Building Code determines, a 96 mph wind speed with Exposure B, and drainage designed for 2 inches of rain per hour. Fire code amendments sit in Chapter 10.28 of the Municipal Code, zoning in Title 11, and ADU rules in Chapter 11.23. Fees, plan check procedures and local zoning are Montclair’s decisions; contractor licensing stays with the state.
Montclair building department: who handles permitting
The Building Division issues building permits, performs plan checks and inspects construction for property inside Montclair. The Planning Division handles zoning, design and land use; the Public Works Engineering Division handles grading plan check, sewer connections and work in the street; and the Montclair Fire Department’s Fire Prevention Bureau reviews fire protection systems. Unincorporated county land next to the city, shown on the County Zoning Map the City posts, is permitted by San Bernardino County Land Use Services (see the San Bernardino County guide); Montclair’s planners only send comments on projects there.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Community Development Department, City Hall, 5111 Benito Street, Montclair, CA 91763 |
| Main line | 909-625-9477 |
| Walk-in counter | Monday to Thursday, 7:00–9:00 a.m. and 4:00–5:30 p.m.; appointments outside those hours by phone |
| Office hours | Monday to Thursday, 7:00 a.m. to 6:00 p.m.; closed Friday to Sunday |
| Building Official | Louis Vasquez, 909-625-9437 |
| Plan check status | 909-625-9433 |
| Inspection requests | 909-625-9448 (results: 909-625-9449) |
| Planning Division | 909-625-9434 or 909-625-9435 |
| Fire Prevention Bureau | 909-447-3552 |
Montclair permit types and what comes first
Montclair’s fee schedule is organized by permit type: new construction (priced by occupancy and floor area), mechanical, electrical and plumbing permits (priced per fixture or unit), and miscellaneous building permits for items such as patios, walls, reroofs, pools and demolition.
Residential permits
For a single-family project the division wants the complete plan set on a USB thumb drive as one combined multipage PDF (architectural, structural, Title 24 energy, an MEP fixture count worksheet and calculations where needed) plus one paper copy of the architectural set for Planning. The plot plan shows floor areas, setbacks, elevations and any buildings to be demolished. If the Planning Commission approved the project, its conditions go on the first sheet. For small jobs without engineering, such as patio covers and one-story wood-frame additions, owners may draw their own plans; the City has pre-engineered masonry wall plans and a sample patio plan, and solar permits run through its online Solar Permits portal. Accessory dwelling units follow Chapter 11.23, rewritten by Ordinance No. 25-1014, which took effect March 4, 2026.
Building or remodeling a home here? Alliance handles residential permit filing, so the crew isn't waiting on the counter.
Commercial permits
Commercial, industrial, multi-family and Montclair Place tenant improvement projects each have their own submittal page. Disabled access plans are required for additions, alterations and repairs to existing commercial buildings, including tenant improvements, and for new buildings. The division can ask for a soils report, structural calculations, energy calculations and electrical design for services of about 400 amps or more. Fire sprinkler, alarm, underground fire main, high-pile storage and hazardous materials plans go separately to the Fire Prevention Bureau by email.
For tenant improvements and new commercial builds, Alliance handles commercial permit expediting through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Planning. Zoning, design and any Planning Commission approval come first; the Planning counter in the City Hall lobby keeps the same hours as Building.
- Engineering. Grading plans are checked by Engineering ($2,100 for the first two sheets of a rough or precise grading plan in the fiscal year 2025–26 schedule); once Engineering approves them, the Building Division issues the grading permit.
- Right-of-way. Fences or other private improvements in the City right-of-way, often 5 to 15 feet behind the curb, need a $35 encroachment permit from Engineering before the building permit is issued; staff usually inspect the site within two business days.
- Sewer and water. A new sewer lateral needs a construction permit and a street lane closure permit (about 10 business days), and water line plans are checked by the Monte Vista Water District.
- School fees. New homes, commercial and industrial buildings and additions that add floor area need certificates of compliance from the Ontario-Montclair School District and Chaffey Joint Union High School District before the City can issue the permit.
Not sure this scope needs a permit?
Get a free quote →Montclair permit fees
The fee page and the Building Division FAQ link the City’s Master User Fee Schedule 2022, adopted under Resolution No. 22-3372. It does not use a valuation table: new buildings are priced by occupancy type and floor area, with one table of plan check fees and one of inspection fees, and smaller jobs are priced per item. Each permit adds a $39 issuance fee.
| Item | Plan check | Inspection |
|---|---|---|
| Single-family house, custom or model, 1,000 sq ft | $1,720.56 | $1,720.56 |
| Single-family house, custom or model, 2,000 sq ft | $2,236.70 | $2,236.70 |
| Single-family house, custom or model, 3,000 sq ft | $3,040.85 | $3,040.85 |
| Residential garage, 800 sq ft | $1,001.25 | $1,001.25 |
| Residential accessory building, 360 sq ft | $596.71 | $596.71 |
| Room addition, single story, 200–499 sq ft | $534.60 | $534.60 |
| Residential remodel, per 250 sq ft up to 500 sq ft | $142.50 | $142.50 |
| Patio cover | $266.48 | $266.48 |
| City-standard masonry fence or wall, first 50 linear feet | $96 | $96 |
| Retaining wall, first 50 linear feet | $118 | $118 |
| Composition reroof, no tear-off, first 10 squares | $100 | $100 |
| Swimming pool or spa | $149.60 | $149.60 |
| Demolition (single-family) | $250 | $250 |
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee |
|---|---|
| Permit issuance (each permit) | $39 |
| Water heater | $65 |
| Plumbing fixtures | $27.23 per 5 fixtures |
| Forced-air furnace under 100,000 Btu/h | $46.92 |
| Electrical service up to 200 amps | $126.46 |
| Residential solar (miscellaneous table) | $450 up to 15 kW, plus $15 per kW above 15 kW |
| Re-inspection or compliance inspection | $198 |
| Supplemental plan check | $99 for the first hour |
| Board of Appeals | $1,000 |
| Transportation impact fee, single-family home (FY 2025–26) | $1,935 per unit |
| Park fee, single-family lot (FY 2025–26) | $2,800 |
| Sewer connection, IEUA plus City (FY 2025–26) | $8,620 plus $862 per equivalent dwelling unit |
Worked example. For a new 2,000-square-foot custom single-family house, the 2022 schedule lists $2,236.70 for plan check and $2,236.70 for inspection, or $4,473.40, before the $39 issuance fee, the electrical fee of $0.22 per square foot, plumbing and mechanical items, school fees and the impact and sewer fees above. The schedule’s residential solar figure appears twice, at $225 in the electrical table and as the kilowatt-based charge in the miscellaneous table, so ask which applies when you file.
Trade permits and who may pull them
Mechanical, electrical and plumbing permits are issued by the Building Division and priced per item: $65 for a water heater, $27.23 for each group of five plumbing fixtures, $46.92 for a furnace under 100,000 Btu/h, $126.46 for an electrical service up to 200 amps and $0.22 per square foot for the wiring of a new single-family house. These amounts appear in the schedule’s MEP inspection table, and its MEP plan check table lists the same amounts again.
The division lists three kinds of applicant: a properly licensed State contractor, the owner of the residential or commercial property, or an agent for the owner or contractor. A certificate of workers’ compensation insurance must be on file before any permit is issued. An agent for a contractor brings a signed letter of authorization on company letterhead. An owner-builder must initial and sign the City’s Property Owner’s Package acknowledgment before the permit is issued. The 2022 fee schedule also sets business license fees for contractors working in Montclair: $80 a year plus $0.30 per $1,000 of gross receipts for an in-town contractor, and $20 a quarter or $80 a year plus $0.40 per $1,000 for an out-of-town contractor.
Rather not deal with the building department?
Get a free quote →How to apply for a building permit in Montclair
Check zoning, setbacks and whether design or Planning Commission review is needed; call 909-625-9434 or visit the counter.
Get grading plan approval, an encroachment permit for anything in the right-of-way, and sewer or water approvals from the agencies involved.
Complete the Application for Building Permit or Application for Plans Examination and follow the submittal page for your project type.
Bring the USB drive or plan sets to the Community Development counter during walk-in hours; plans are accepted only during counter hours and a plan check deposit is collected.
Pick up the correction list, revise the plans and resubmit; the designer signs the final set before staff approve it.
Staff check approvals from other agencies, school fee certificates, license and insurance, and calculate the remaining fees.
Pay by check, cash or credit card at City Hall and keep the inspection card and approved plans on site.
Review, corrections and what causes delay
The first plan review takes about two weeks during normal activity and each later review about one week; plan check status is available at 909-625-9433. Fire Prevention review adds about two weeks and cannot be expedited, while the Building Division accepts an expedite request letter. No permit is issued until administrative items such as written approvals from other agencies and proof of license and insurance are cleared, and changes made during construction need the design professional’s approval first.
Inspections in Montclair
Call the inspection hotline at 909-625-9448. A request made before 5:00 p.m. is scheduled for the next working day; because City Hall is closed on Fridays, a request made on Thursday is scheduled for Monday. Results are available at 909-625-9449.
The job must be complete for the stage being inspected, with the approved plans and the posted inspection card on site. An adult must be present for interior inspections and dogs must be secured. Foundation inspections need forms braced at the correct setbacks with rebar, anchor bolts and hold-downs in place; framing is inspected only after rough electrical, plumbing and mechanical work has passed. Deputy inspectors must be approved by the City in advance. Construction may not start before 7:00 a.m. or continue past 8:00 p.m., and portable toilets must stay on the site, not in the street. Re-inspections and after-hours inspections cost $198 each. Fire inspections are booked separately through Dennis Grubb and Associates, the firm named on the City’s pages, at 951-772-0007.
Building code in Montclair
Montclair enforces the state codes it adopted by Ordinance No. 25-1016, effective January 14, 2026, and keeps its fire code amendments in Chapter 10.28 of the Municipal Code. FEMA lists Montclair as a participating community in the National Flood Insurance Program, with a current flood map dated August 28, 2008; Public Works posts flood insurance rate map information for property owners.
California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
Want this handled start to finish?
Get a free quote →Frequently asked questions
Who issues building permits in Montclair?
The City’s Building Division in the Community Development Department at City Hall, 5111 Benito Street, issues building, electrical, plumbing and mechanical permits inside city limits. Louis Vasquez is the Building Official.
Can I apply for a Montclair building permit online?
Mostly no. The City says most permits are obtained in person over the counter at City Hall, Monday to Thursday from 7:00 to 9:00 a.m. and 4:00 to 5:30 p.m. Solar permits are the exception: they go through the online Solar Permits portal.
How much does a building permit cost in Montclair?
Under the 2022 Master User Fee Schedule each permit costs $39 to issue, plus plan check and inspection fees by project type. A 2,000-square-foot custom house lists $2,236.70 for each, a patio cover $266.48 for each, and a water heater $65.
Do I need a permit for a block wall, fence or patio cover?
Yes for masonry walls 24 inches high or more, and the Public Works encroachment handout says all fences need a building permit. All patio covers need one too. A fence in the City right-of-way also needs a $35 encroachment permit first.
How long does plan check take?
About two weeks for the first review and about one week for each later review. Fire Prevention plan review takes about two weeks and cannot be expedited.
How do I schedule an inspection?
Call 909-625-9448 before 5:00 p.m. for an inspection the next working day. City Hall is closed on Fridays, so Thursday requests are scheduled for Monday.
How do I get copies of old permits or plans?
Submit a public records request through the City’s NextRequest portal or at City Hall. Official plans can be viewed only at the Building Division, and copies need written permission from the design professional and the owner.
Montclair permit search and official resources
Building permit records, including whether a property has a recorded sewer connection, are requested through the City’s NextRequest public records portal or at City Hall; plan check status is given by phone at 909-625-9433 and inspection results at 909-625-9449. Plans on file can be duplicated only with the City’s Request to Duplicate Plans form and the written permissions it lists.
Inspections are where schedules slip.
Get a free quote →- Community Development Department
- Building Division
- Building Division FAQ
- Plan submittal
- Single family plan submittal
- Block walls, patios and other plan submittals
- Building design criteria
- Building forms and handouts
- Inspection hotline and procedures
- Master User Fee Schedule 2022 (PDF)
- Engineering Division fee schedule, FY 2025–26 (PDF)
- Encroachment permit information and application (PDF)
- School fees handout (PDF)
- Property Owner’s Package for owner-builders (PDF)
- Fire plan check and permit process
- Planning Division
- Municipal code, zoning ordinance and zoning maps
- Ordinance No. 25-1014 (ADUs and JADUs)
- Solar permits portal
- Public records requests
Simplify Montclair permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Montclair sooner?
Let Alliance prepare, file, and track your Montclair permits while your crew stays on the job.
More California permitting guides
San Bernardino County
Read guide →Ontario
Read guide →Rancho Cucamonga
Read guide →Montebello Building Permit Guide
Read guide →Monterey Building Permit Guide
Read guide →Monterey County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Montclair permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.