Skip to main content
Municipal GuideCaliforniaMill Valley · Marin County

Mill Valley, California Building Permit Guide

To get a building permit in Mill Valley, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Mill Valley’s Building Division at City Hall, 26 Corte Madera Avenue, reviews plans, issues permits and inspects work inside the city limits, with applications filed online in eTRAKiT and a short counter window twice a week.

Authority: Mill Valley Building DivisionFees: Effective July 1, 2026Phone: 415-388-4033
Authority
City Building Division26 Corte Madera Avenue
Counter
Tue & Thu 8–noonCheck in by 11:30 a.m.
Plan check
4–6 weeks minimumResidential and commercial
Inspections
No Friday inspectionsBook by 3 p.m. the day before

Inside Mill Valley, building permits come from the Building Division of the Planning & Building Department at City Hall, 26 Corte Madera Avenue (415-388-4033), where Emil Dilanian is the Building Official. Applications are filed in eTRAKiT: water heaters, re-roofs and similar express permits are issued automatically to licensed contractors, while full plan check takes at least 4–6 weeks. Under the fee schedule effective July 1, 2026, plan check is 65% of the basic permit fee, and projects of $10,000 or more also pay a 1% road impact fee.

What requires a building permit in Mill Valley?

The city’s permit handout starts from the rule that no building, structure or building service equipment may be built, enlarged, altered, repaired, moved, converted or demolished without its own permit, and the FAQ adds that a water heater replacement needs one. Most of what is exempt is cosmetic. The handout lists the exceptions:

No building permit

  • One-story sheds or playhouses up to 120 sq ft and 10 feet tall, with no plumbing, electrical or heating, and not in a setback
  • Fences under 7 feet high
  • Retaining walls up to 4 feet from the bottom of the footing, with no surcharge
  • Platforms, walks and driveways no more than 30 inches above grade
  • Decks up to 200 sq ft, no more than 30 inches above grade, not attached to the house and not serving a required exit door
  • Painting, papering and similar finish work
  • Prefabricated pools under 24 inches deep; window awnings projecting up to 54 inches

Still needs a permit

  • Water heater, furnace and AC or heat pump installs
  • Re-roofs, and window or door replacements
  • Sewer laterals and panel or service changes
  • Kitchen and bath remodels
  • Decks, fences, retaining walls, pools and hot tubs beyond the exemptions
  • Any plumbing, electrical or mechanical work in an exempt structure
  • Any construction in a FEMA AO, AE or floodway zone

An exemption from a building permit does not override Planning or Public Works rules, so a fence or shed can still need their review.

What Mill Valley decides and what the state holds

The city sets its own fees each July 1, its construction hours, project completion limits (Municipal Code 14.05.032(G)), floodplain rules (Chapter 18), extra green building requirements (Chapter 14.48) and a mandatory soft-story seismic retrofit program for certain residential buildings (Ordinance 1343, effective December 26, 2023). Contractor licenses are issued by the state.

Mill Valley building department: who handles permitting

The Building Division reviews plans, issues permits and inspects work, working with Planning, Property Compliance, Public Works and Fire. Some addresses with a Mill Valley mailing address are in unincorporated Marin County rather than the city; the city asks you to check the jurisdiction on MarinMap first, and unincorporated properties go to the County of Marin.

Short on time to read all of this?

Get a free quote →
Mill Valley permit contacts
DetailInformation
OfficeBuilding Division, Mill Valley City Hall, 26 Corte Madera Avenue, Mill Valley, CA 94941
Phone415-388-4033
Emailbuilding@cityofmillvalley.gov (the city prefers email for code questions)
Counter hoursTuesdays and Thursdays 8 a.m. to noon; check in before 11:30 a.m. City Hall is open Monday to Thursday 8 to 5, closed noon to 1.
Building OfficialEmil Dilanian, 415-384-4816
Business licensesFinance, businesslicenses@cityofmillvalley.gov, (415) 384-4802
Unincorporated Mill ValleyCounty of Marin

Mill Valley permit types

Mill Valley sorts applications by review level, each with a published review time. Every file is uploaded as a PDF named “Street Name Street Number – Permit Number – Document Type”, and only complete submittals are processed.

Mill Valley review times
Permit typeReview time
Express (auto-issued to licensed contractors)1–3 business days
Solar and battery backup1–3 business days
Minor permits / non-structural residential remodels7–10 business days
Plan check, residential and commercial4–6 weeks minimum
Revisions to existing permits2–3 weeks minimum

Residential permits

  • Express permits for furnaces with no outside equipment, water heaters, sewer laterals, electrical panels up to 200 amps, main services and subpanels, re-roofs and window and door replacements are issued automatically to licensed contractors; the permit card follows after an administrative review, generally within a week. Same-opening window and door jobs and re-roofs need no plan submittal, but built-up roofs need a Certificate of Positive Roof Drainage at final.
  • Minor permits need plans: AC and heat pump installs need a site plan, equipment specifications and noise calculations at the property lines; gas line work needs a schematic and sizing calculations; battery backup and EV chargers are also minor permits.
  • Kitchens and baths without structural changes use the “Nonstructural Kitchen and Baths” type, with plans at 1/4-inch scale on sheets at least 11 by 17 inches; ceilings in these rooms must be at least 7 feet.
  • Residential plan check covers new houses, ADUs, additions, remodels, full or partial demolition, decks, garages and accessory structures, retaining walls, pools, fences and hot tubs. ADUs and junior ADUs need the city’s completeness checklist.
  • Rooftop solar and batteries can get instant residential permits through the city’s Symbium platform.

Commercial permits

Commercial plan check covers new commercial buildings, tenant improvements, signs, commercial pools and remodels or repairs of apartments and mixed-use buildings. Plans for buildings other than houses (Group R-3) and Group U structures must be stamped and signed by a licensed architect or engineer. The city recommends talking to Planning & Building about zoning and use permits before signing a lease, and almost any alteration triggers some accessibility upgrade.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Design review by the Zoning Administrator or Planning Commission; for a Planning Commission hearing, story poles go up at least 10 days before, when notice is mailed to owners within 300 feet.
  • Tree removal. Heritage tree removal needs a permit ($1,401 per tree; $119 for a non-heritage tree).
  • Construction Management Plan. Many projects need a plan covering parking, truck routes, schedules, road closures and material storage, approved by the Building Official before the permit is issued.
  • Floodplain review. In AO, AE and floodway zones a Substantial Improvement Worksheet is required; renovations over a 2-year period are counted together, and substantial improvements can trigger raising the building above the base flood elevation.

Mill Valley permit costs and fees

Building fees are set in the Building Fees schedule effective July 1, 2026 and are adjusted every July 1. The basic permit fee comes from the project valuation; plan check, technology and General Plan fees are percentages of it, and road impact and affordable housing fees are percentages of valuation.

Mill Valley building fees, effective July 1, 2026
ItemFee
Valuation $1–$2,000$280
Valuation $2,001–$50,000$280 plus $24.21 per $1,000 over $2,000
Valuation $50,001–$100,000$1,423 plus $14.73 per $1,000 over $50,000
Valuation $100,001–$500,000$2,218 plus $13.68 per $1,000 over $100,000
Valuation $500,001–$1,000,000$7,667 plus $12.63 per $1,000 over $500,000
Plan check / technology fee65% / 5% of the basic permit fee
General Plan maintenance (projects $10,000+)19% of the basic permit fee
Road impact fee (projects $10,000+)1% of valuation
Affordable housing impact fee (projects $151,000+)1% of valuation; second units and micro units excluded
Electrical, plumbing or mechanical permit15% of the basic permit fee, $199 minimum
Water heater or furnace / tankless water heater$146 / $239
Rooftop solar, single-family home$450
Inspections / after-hours inspections$199 per hour / $227 per hour, 2-hour minimum
Work started without a permitInvestigation fee of 3 times the building permit fee
Residential Building Report (resale)$399 first unit, $91 each additional

Rather talk it over?

Call 1-855-478-4290 →

Worked example: an addition valued at $200,000 falls in the $100,001–$500,000 band, so the basic permit fee is $2,218 plus 100 × $13.68, or $3,586. Plan check adds $2,330.90, the technology fee $179.30, the General Plan fee $681.34, the road impact and affordable housing fees $2,000 each, and the building standards fee $8, for $10,785.54; the state seismic fee (0.013% for residential work, $26) brings it to $10,811.54. Trade permits, bedroom-based development fees and any drainage fee are extra.

Other charges

The planning and development fee is $270 for a home’s first bedroom and $178 for each additional bedroom, or $0.24 per square foot for commercial space. The downstream drainage fee is a one-time charge per parcel on permits of $5,000 or more if it was not paid at subdivision; it varies by drainage basin, from $160 an acre ($80 under an acre) downtown to $680 an acre ($340 under an acre) in East Blithedale Ryan. A permit that expired less than a year ago is renewed for half the building permit fee; after a year the full fee applies. Building and Planning fees can be waived for 100% affordable housing projects (Municipal Code 5.32.010). Planning fees include $5,224 for design review by the Zoning Administrator and $5,410 for a variance.

The Planning & Building page links an earlier copy of the July 1, 2026 building fees with higher solar figures (for example $538 for a single-family system); the version on the Forms, Fees & Resources page, updated in September 2026, shows $450, which is used here.

Trade permits and who may pull them

Electrical, plumbing and mechanical permits are issued by the Building Division through eTRAKiT and cost 15% of the basic permit fee with a $199 minimum. Simple replacements are express permits issued automatically to licensed contractors.

  • Contractors get an eTRAKiT professional account by emailing their CSLB license number and business email to building@cityofmillvalley.gov. Architects, designers, engineers and realtors email their business name, phone number and address.
  • Owner-builders email their name, phone number and address to set up an account, then upload the city’s Owner/Builder Packet with the application if they will do the work or act as general contractor.
  • Business license. Every business operating in Mill Valley needs a city business license, filed and renewed online through the city’s OpenGov portal, and the license must be paid for the current fiscal year before you can apply for a permit.

Rather not deal with the building department?

Get a free quote →

How to apply for a Mill Valley building permit

1. Confirm the jurisdiction

Search the address on MarinMap: “Mill Valley” means the city, “Unincorporated” means the County of Marin.

2. Clear planning items

Get design review, tree removal or floodplain determinations where they apply, and prepare a Construction Management Plan if one is needed.

3. Set up eTRAKiT and a business license

Request a professional or owner-builder account by email, and pay the city business license for the current fiscal year.

4. Apply and upload

Submit the application in eTRAKiT and upload the complete PDF package using the city’s file naming rule.

5. Answer corrections

Respond to the plan check report; second reviews take about a week.

6. Collect the permit

Allow about a week after approval for issuance, then post the permit card and keep the approved plans on site.

Review, corrections and what causes delay

The city warns that omissions or errors cause delays, and that other departments and agencies can take longer than the building review. If plan check comments go unanswered for 180 days, the application expires and may have to be resubmitted; the Building Official can grant a 180-day extension on a written request made before it expires. Deferred submittals, such as truss calculations, are allowed only if they do not change the project, and work on that element cannot go ahead until they are approved. Revisions to an issued permit need a Revision Submittal Form and take about 2–3 weeks.

Inspections in Mill Valley

Inspections are scheduled online in eTRAKiT for permits with an “issued” status, by 3 p.m. the day before and up to 7 days ahead; allow 2–5 business days. Inspectors give windows of 8–10 a.m., 10 a.m.–noon, 1–3 p.m. or 3–5 p.m., and there are no inspections on Fridays. An adult must be on site, the permit card posted and the approved plans available, and field changes must be approved as revisions before they can be inspected.

  • Covered work that was not inspected can be ordered opened up.
  • Permit life. A permit expires a year after issuance if no inspection has been approved, and each approved inspection extends it by 180 days.
  • Construction hours on a permitted site: light set-up from 7 to 8 a.m., heavy equipment from 8 a.m. to 5 p.m., light clean-up from 5 to 6 p.m., Monday to Friday, with no construction on weekends or city holidays.
  • Resale reports. A Residential Building Report is required whenever a home changes ownership and should be obtained before escrow closes; the real estate agent applies, and the report and permit history are emailed within about two weeks.

Want this handled start to finish?

Get a free quote →

California building code in Mill Valley

Plans must note compliance with the 2025 California building, residential, plumbing, mechanical, electrical, energy and green building codes, and Mill Valley adds green building requirements in Chapter 14.48 of its Municipal Code for commercial projects, new homes and additions of conditioned space. FEMA’s Community Status Book lists Mill Valley (community 060177) as participating in the National Flood Insurance Program, with a current flood map dated August 15, 2017; the city’s own floodplain rules are in Chapter 18.

California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments

Mill Valley building permit FAQs

Who issues building permits in Mill Valley?

The Building Division at City Hall, 26 Corte Madera Avenue (415-388-4033), for addresses inside the city. Unincorporated Mill Valley addresses go to the County of Marin.

How much is a building permit in Mill Valley?

It depends on valuation: a $200,000 addition comes to about $10,812 in permit, plan check, technology, General Plan, road impact, affordable housing and state fees, before trade permits and development fees.

How long does plan review take?

Express and solar permits take 1–3 business days, minor permits and non-structural kitchen and bath remodels 7–10 business days, and full plan check at least 4–6 weeks.

Do I need a permit for a fence or deck?

Fences under 7 feet and freestanding decks up to 200 square feet and 30 inches above grade are exempt from a building permit, but Planning or Public Works rules can still apply.

Can a homeowner pull a permit?

Yes. Owner-builders email the Building Division to set up an eTRAKiT account and upload the Owner/Builder Packet with the application.

When are inspections done?

In 2-hour windows between 8 a.m. and 5 p.m.; there are no inspections on Fridays. Book in eTRAKiT by 3 p.m. the day before.

Do I need a report to sell my home?

Yes. A Residential Building Report is required when a residential property changes ownership; the agent applies online and the fee is $399 for the first unit.

Mill Valley permit search and official resources

eTRAKiT holds building permit records from about November 2012 onward, along with parcel zoning, assessor and flood data and planning project history. For earlier permits, email building@cityofmillvalley.gov, and for planning approvals planning@cityofmillvalley.gov. The city also posts a monthly permit activity report.

Inspections are where schedules slip.

Get a free quote →

Simplify Mill Valley permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Mill Valley sooner?

Let Alliance prepare, file, and track your Mill Valley permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Mill Valley permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.