Inside the City of San Rafael, building permits are issued by the Building Division of Community and Economic Development at City Hall, 1400 Fifth Avenue, third floor ((415) 485-3367). The division is fully digital: you apply, upload plans, pay and book inspections in OpenGov, and change-outs such as water heaters, furnaces, re-roofs and single-family solar are issued instantly. Under the fees approved July 1, 2026, the permit fee is set from project value, with building plan check at 65% of it; residential plan-review permits take about 2–6 weeks.
What requires a building permit in San Rafael?
San Rafael requires a permit for anyone who intends to build, enlarge, alter, repair, move, demolish or change the occupancy of a building, or to install, alter, convert or replace an electrical, gas, mechanical or plumbing system. The city’s own exemption list, posted in October 2026, sets out what is not covered, and adds that Planning, the Fire Prevention Bureau or Public Works may still place conditions on exempt work.
No building permit
- Sheds, gazebos or playhouses on non-hillside residential lots, up to 120 sq ft and 15 feet tall, with no utilities and meeting setbacks
- Residential fences up to 7 feet, or masonry walls up to 36 inches, outside the front or street yard and not serving as a pool barrier
- Retaining walls up to 4 feet from the bottom of the footing, with no surcharge
- Patios, walks and driveways no more than 30 inches above grade
- Decks up to 200 sq ft and 30 inches above grade, not attached and not on an exit path
- Painting, flooring, carpet and countertops
- Roof repairs under 100 sq ft, same-opening door and garage door replacement, grading under 50 cubic yards
Needs a permit
- New homes, ADUs, additions and garage conversions
- Structural changes and foundation work
- Major kitchen and bath remodels
- Decks, balconies and taller retaining walls
- Re-roofs and re-siding
- Water heater, furnace, AC and panel change-outs
- Re-striping a parking lot
What San Rafael decides and what the state holds
San Rafael applies the state codes with local amendments and adds its own rules: a building reach code for remodels of older homes, its zoning and design rules in Title 14, its annually approved fee schedule and development impact fees, and a resale inspection program. Applications filed complete on or before December 26, 2025 could still follow the 2022 code. Contractors are licensed by the state.
San Rafael building department: who handles permitting
The Building Division enforces the building code for residential, commercial and industrial projects through plan check and inspection, and handles every step in OpenGov. Applications are routed to Planning, Public Works, Fire and the sanitation district as needed, and the same office serves as the city’s permit, planning, zoning and code enforcement counter. Property outside the city limits is under Marin County, so check the property’s jurisdiction before applying.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Building Division, Community and Economic Development, City Hall, 1400 Fifth Avenue, 3rd floor, San Rafael, CA 94901 |
| Phone | (415) 485-3367 |
| Counter hours | Monday to Thursday 8:30 a.m. to 4 p.m., Friday 8:30 a.m. to 12:30 p.m.; closed holidays |
| Online | OpenGov permit portal, available 24/7 |
| Planning questions | planning@sanrafael.gov |
| Appointments | Walk-ins welcome; book ahead for complex projects and pre-application meetings |
San Rafael permit types
San Rafael has two main categories: permits that need plan review and minor permits that do not. In OpenGov you choose a building, demolition, electrical, plumbing, mechanical, pool or spa, renewable energy or roofing permit, and the system works out the fees.
| Permit type | Typical time |
|---|---|
| Panel, water heater, roof, furnace, wall heater or ducting change-out; single-family solar without storage | Instant issuance |
| Residential solar / commercial solar | 1–2 days / 2–4 weeks |
| Electrical / HVAC | 5–12 days each |
| Residential building permits | 2–6 weeks |
| Commercial permits | 4–12 weeks |
Residential permits
- Minor plumbing: water heaters of 100 gallons or less, tankless heaters (a gas schematic is reviewed first), and water, sewer or drain lines inside the house and up to 3 feet outside the wall; beyond 3 feet the sanitation district issues its own permit.
- Minor mechanical: same-location furnace, AC and duct change-outs; a new AC unit needs a site plan showing its distance from property lines and neighbors’ windows and its decibel rating.
- Minor electrical and roofing: service panels and subpanels, small wiring jobs with a plan, and re-roofs that add only one overlay and leave rooftop equipment alone.
- Windows, doors and siding: retrofit windows and doors are minor permits if framing and waterproofing are untouched; a new opening needs plan review.
- Reach code: a remodel of more than 500 square feet on a single-family home built before 2010 must meet the city’s reach code through the Flex Path form, choosing upgrades such as insulation, efficient heating or solar to reach a target score; the city estimates $500 to $4,000 up front.
Building or remodeling a home here? Alliance handles home building permits, so the crew isn't waiting on the counter.
Commercial permits
Commercial tenant improvements and new commercial buildings always need full plan review, and commercial mechanical work needs plans reviewed before issuance. Commercial generators and EV chargers are charged at 15% of the valuation-based building permit fee. The city may send any planning or building submittal to an outside consultant at the applicant’s cost.
Not sure this scope needs a permit?
Get a free quote →For tenant improvements and new commercial builds, Alliance handles commercial permit filing through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Planning approval is often needed first for new construction, large additions, accessory structures on hillside lots and retaining walls over 4 feet; check the property’s zoning, and ask planning@sanrafael.gov if unsure.
- Outside agencies. You file separately with Marin County Environmental Health, the Marin County CUPA (hazardous materials), the Bay Conservation and Development Commission and the Army Corps of Engineers where they apply.
- Public Works reviews drainage, grading, driveways, right-of-way work and flood zone compliance; large grading jobs need a separate grading permit.
- Encroachment permits cover driveway repair, landscaping by a sidewalk, and debris boxes or storage containers placed in the street.
San Rafael permit costs and fees
The City Council approves a master fee schedule every year; the building and safety fees and the mechanical, electrical and plumbing fees now posted were approved July 1, 2026. Fees are calculated automatically in OpenGov from the project value, which must include materials, labor for all trades and permanent fixtures, counting your own labor at market rate.
| Item | Fee |
|---|---|
| Valuation up to $2,000 | $267.53 |
| Valuation $2,000.01–$25,000 | $267.53 plus $24.72 per $1,000 over $2,000 |
| Valuation $25,000.01–$50,000 | $849.88 plus $11.90 per $1,000 over $25,000 |
| Valuation $50,000.01–$100,000 | $1,154.72 plus $16.55 per $1,000 over $50,000 |
| Valuation $100,000.01–$500,000 | $2,002.99 plus $7.58 per $1,000 over $100,000 |
| Valuation $500,000.01–$1,000,000 | $5,110.17 plus $13.96 per $1,000 over $500,000 |
| Plan check: building / energy | 65% / 10% of the building permit fee |
| Software integration and support | 5% of all permit fees |
| Furnace, AC, heat pump, water heater, panel up to 200A, residential EV charger or battery | $141 flat |
| Residential solar, 15 kW or less | $461 |
| Re-inspection / additional plan review | $195 per hour |
| After-hours / weekend inspection | $292 / $390 per hour, 2-hour minimum |
| Renewal of an expired permit | 15% of the permit fee |
| Investigation fee for work without a permit | 3 times the building permit fee |
| Residential Building Report, single-family or condo | $393 |
Rather talk it over?
Call 1-855-478-4290 →Worked example from the valuation table: a remodel valued at $200,000 falls in the $100,000.01–$500,000 band, so the building permit fee is $2,002.99 plus 100 × $7.58, or $2,760.99, and building plan check is 65% of that, $1,794.64, for $4,555.63. Energy review (10%) where it applies, the 5% software fee, trade permits and the state green building ($8) and seismic ($26) fees are added.
Other charges and payment
Mechanical, electrical and plumbing plan review is $97 on flat-fee permits, and an expired trade permit is renewed for $103. Plan check fees are due when you submit; inspection and records imaging fees are due before the approved plans are released. Hourly work is charged against deposits, which are not a cap: once a deposit is used up, the city bills monthly or asks for more. Card payments can carry a surcharge of up to 4%. New development also pays impact fees; the City Council adopted an updated transportation mitigation fee that took effect on August 14, 2026, and park impact fees have been under review.
Trade permits and who may pull them
Electrical, plumbing and mechanical permits are issued by the Building Division in OpenGov. Most residential trade jobs are flat $141 permits that cover up to two units or fixtures; larger or more complex work is charged on the valuation table as the Chief Building Official decides.
- Who can apply. The city issues permits only to a properly licensed California contractor or to a property owner acting legally as an owner-builder.
- Contractors need a current state license and a current City of San Rafael business license.
- Owner-builders take responsibility for the whole project, may hire licensed contractors for parts of it, and file the Owner-Builder Acknowledgment Form with the application. The city warns that hiring unlicensed workers can make you responsible for tax withholding, workers’ compensation and other obligations.
- Sewer laterals beyond 3 feet outside the building need a separate sanitation district permit.
Rather not deal with the building department?
Get a free quote →How to apply for a San Rafael building permit
Confirm the property is in San Rafael and whether the project needs a planning approval first.
Decide whether the job is a minor permit or needs plan review, and whether the reach code applies.
Use the city’s submittal checklist and upload complete PDF plans, structural calculations, energy documents and site information.
Create an account, select Building and the permit type, upload documents and pay the application fees by card, e-check or check.
Staff routes the plans to the reviewing departments; resubmit with every comment answered.
When approved, pay remaining fees, download the permit card and plans, and print at least one full set at original scale (11 by 17 inches minimum) for the site.
Review, corrections and what causes delay
The city lists the usual causes of delay: missing sheets or details, plans that do not match each other, missing structural calculations or energy documents, and incomplete site information. Many applications qualify for streamlined processing in a few days, but times grow when information is missing or a project does not meet the objective standards. Work covered before inspection and corrections that are only partly answered also slow things down. Changes during construction need approved revised plans before they are built.
Inspections in San Rafael
Building and fire inspections are requested in OpenGov once the permit is issued, at least 1 business day ahead. Inspections run Monday to Thursday, in a morning window (8 a.m. to noon) or an afternoon window (1 to 4 p.m.); there are none on Fridays or weekends. Anyone booking who is not the applicant needs guest access to the permit, and someone must be available for the whole window with a printed plan set.
- Typical stages: foundation or footing, under-slab plumbing, framing, electrical rough-in, insulation and final; the permit card lists the ones your project needs.
- Final: exterior surfaces finished, fixtures installed, smoke detectors in place, and other departments such as fire sprinklers or Planning signed off first.
- Permit life: 180 days from issuance, extended 180 days by each approved inspection, up to 2 years in total; one free 180-day extension is available on an active permit.
- Resale reports: a Residential Building Record, with a permit history review and an inspection, is required when a residential property changes ownership and must be requested before escrow closes. For items such as an unpermitted water heater, furnace or window replacement, permits obtained and approved within 15 days of the report avoid enforcement action.
California building code in San Rafael
San Rafael applies the 2025 California building, residential, mechanical, plumbing, electrical, existing building and green building codes, the 2024 International Property Maintenance Code and the 2024 International Pool and Spa Code, with local amendments, and its building reach code adds energy upgrades for larger remodels of older homes. FEMA’s Community Status Book lists San Rafael (community 065058) as participating in the National Flood Insurance Program, with a current flood map dated March 16, 2016, and Public Works checks flood zone compliance during plan review.
Want this handled start to finish?
Get a free quote →California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
San Rafael building permit FAQs
Who issues building permits in San Rafael?
The Building Division at City Hall, 1400 Fifth Avenue, third floor ((415) 485-3367), through the city’s OpenGov portal. Unincorporated areas go to Marin County.
How much is a building permit in San Rafael?
It is based on project value: a $200,000 remodel has a $2,760.99 permit fee and $1,794.64 plan check, before energy review, the 5% software fee and state fees. A water heater or furnace change-out is $141.
Which permits are issued instantly?
Change-outs of main service panels, water heaters, roofs, furnaces, wall heaters and ducting, and single-family solar without battery storage.
Do I need a permit for a shed or fence?
A non-habitable shed up to 120 square feet and 15 feet tall on a non-hillside residential lot, and a residential fence up to 7 feet outside the front yard, are exempt; front-yard fences must meet Title 14.
Can a homeowner pull a permit?
Yes, as an owner-builder who takes responsibility for the project and files the Owner-Builder Acknowledgment Form.
When are inspections available?
Monday to Thursday, 8 a.m. to noon or 1 to 4 p.m., booked in OpenGov at least 1 business day ahead; there are no Friday inspections.
Do I need a report to sell my home?
Yes. A Residential Building Record is required when a residential property changes ownership, requested before escrow closes; it costs $393 for a single-family home or condominium.
San Rafael permit search and official resources
Current permits, inspections, fire permits, resale reports and planning projects are searched in OpenGov. Records from 2000 to early 2026 are in the city’s former eTRAKiT system, and records from 1940 to 2005 in its ePermits archive; help is available at (415) 485-3367.
Inspections are where schedules slip.
Get a free quote →- Apply for a building permit
- About the building permit process
- Types of building permits
- Work exempt from building permit
- Building and safety service fees, approved July 1, 2026
- Mechanical, electrical and plumbing permit fees
- Planning and building permit fees and payments
- Schedule a building or fire inspection
- Building codes and rules
- Building reach code for existing homes
- Contractors and owner-builders
- Search building permits and project records
- Residential Building Record program
- Development impact fees
- Front counter services
- 2025 California Title 24 building standards
- FEMA Community Status Book, California
Simplify San Rafael permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in San Rafael sooner?
Let Alliance prepare, file, and track your San Rafael permits while your crew stays on the job.
More California permitting guides
Marin County
Read guide →Larkspur
Read guide →Mill Valley
Read guide →San Ramon Building Permit Guide
Read guide →Sanger Building Permit Guide
Read guide →Santa Ana Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about San Rafael permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.