Skip to main content
Municipal GuideCaliforniaHillsborough · San Mateo County

Hillsborough, California Building Permit Guide

To get a building permit in Hillsborough, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Hillsborough’s Building Division at Town Hall, 1600 Floribunda Avenue, issues all building and trade permits in the town through its eTRAKiT portal, under local rules that add fire sprinkler triggers, Class A roofs and construction time limits.

Authority: Hillsborough Building DivisionFiling: eTRAKiT onlinePhone: (650) 375-7411
Authority
Town Building Division1600 Floribunda Ave
Hours
Mon–Thu 8–5Friday 8 to noon
Plan check
25% of permit fee75% over $1 million
Completion deposit
2% of valuationJobs over $50,000

In the Town of Hillsborough, permits come from the Building Division at Town Hall, 1600 Floribunda Avenue ((650) 375-7411). Every application is filed online through the town’s eTRAKiT portal, after contractors and owner-builders register for a login. Hillsborough’s Title 15 adds its own rules to the state codes, including fire sprinklers in new homes and many large remodels, Class A roofs everywhere and time limits for finishing construction backed by a 2% deposit. Fees follow the FY 2026–27 Master Fee Schedule.

What requires a building permit in Hillsborough?

Hillsborough publishes a broad list of work that needs a permit. Besides new buildings and additions, it includes decks, garages, fences, gates, antennas, satellite dishes, fireplaces, pools, water heaters and landscaping; renovations of garages, basements, kitchens, bathrooms, storage rooms and pool houses; re-roofing; HVAC systems; plumbing, including landscape irrigation and drainage; electrical and solar systems; and tree removal. Separate permits are normally needed for electrical, plumbing and heating or air-conditioning work.

Town permit list

  • New houses, ADUs and additions
  • Decks, garages, fences, gates and pool houses
  • Kitchen, bathroom, basement and garage renovations
  • Re-roofing (Class A required)
  • Fireplaces and chimneys
  • Pools, irrigation and drainage
  • HVAC, water heaters, electrical and solar
  • Tree removal

Local triggers to plan for

  • Fire sprinklers in every new one- or two-family house
  • Sprinklers in existing large homes when added or altered area passes the town’s threshold
  • Spark arrestors on solid-fuel chimneys before any permit is finaled
  • Possible structural or geotechnical evaluation when structure is exposed
  • Pre-construction meeting and job superintendent at $750,000

The town suggests calling the Building Division at (650) 375-7411 before you start, ideally in the afternoon when staff are not busy at the counter; staff can usually say over the phone whether a project needs a permit.

What Hillsborough decides and what the state holds

Hillsborough adopts the 2025 California codes in Title 15 of its Municipal Code with local amendments and local development standards. Under Section 15.03.110, sprinklers are required in new one- and two-family homes and in existing homes over 2,000 square feet or more than two stories when permitted additions or alterations exceed 1,500 square feet, or 20% of the floor area for homes over 7,500 square feet, with matching rules for ADUs. A room counts as altered when 50% or more of its wall or ceiling covering is removed or replaced, and work is added up over two years. Every roof and roof covering must be Class A. Chimneys serving solid-fuel appliances need spark arrestors, which must be installed before a property is sold and before any permitted job is finaled. Fire plan check under the fire and wildland-urban interface codes is done when the fire code official requires it. Contractor licensing is the state’s.

Short on time to read all of this?

Get a free quote →

Hillsborough building department: who handles permitting

The Building Division issues permits to homeowners and contractors, reviews plans, inspects work and works with the Planning Division on design. Fire plan review is by the Central County Fire Department (CCFD), under its own fee schedule. Encroachment and grading permits are issued by the Engineering Department (pw@hillsborough.net, (650) 375-7444).

Hillsborough permit contacts
DetailInformation
OfficeBuilding Division, Town Hall, 1600 Floribunda Avenue, Hillsborough, CA 94010
Phone / fax(650) 375-7411 / (650) 375-7415
Emailplancheck@hillsborough.net
Service hoursMonday to Thursday 8 a.m. to 5 p.m.; Friday 8 a.m. to noon
Planning(650) 375-7422; appointments with a planner by phone or email
Code enforcement(650) 375-7572

Hillsborough permit types

The town processes every permit through eTRAKiT and issues permits electronically. Before your first application, register with the town for a login: contractors give their state license number, architects and engineers their state license number, and anyone working in the public right-of-way needs a Class A contractor’s license and proof of liability insurance. The handouts page has the building permit application, plan check requirements, the required soils report handout and the town’s brochure on the residential design, permitting and construction process.

Residential permits

  • New homes and additions are valuation-based permits that go through Planning design review; the town posts a required soils report handout, and new homes need fire sprinklers.
  • ADUs. A new ADU has a flat building permit fee of $5,352 and an ADU or junior ADU converted from existing space $3,739, after a ministerial zoning clearance from Planning.
  • Remodels. A like-for-like kitchen or bathroom with no wall changes is $1,326, plus $261 for each additional room; anything larger is priced by valuation and may trigger the sprinkler rules.
  • Roofs. A re-roof is $823, or $1,545 when it needs architectural review; all roof coverings must be Class A, and the town also posts a gutter guard handout.
  • Solar and batteries. Solar and storage can be permitted through regular plan check in eTRAKiT or through the town’s automated Symbium pathway.
  • Owner-builders. Only the property owner qualifies, not a business owner or tenant; the town posts owner-builder requirements, a notice and a property owner’s package.

Commercial permits

Non-residential work uses the same valuation table and plan check rates as homes. Private school use permits and their annual certifications are Planning items in the fee schedule, and the town posts a notice to applicants for business licenses and commercial building permits.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Planning and design review. A pre-application meeting ($1,003) is required before a Type A or Type B design review application. Staff-level (Type B) review covers exterior material or style changes; larger work (Type A) goes to the Architecture and Design Review Board (ADRB), including second-story additions visible from the street, additions over 500 square feet, substantial alterations, “tear downs” and new houses. A ministerial zoning review of a building permit costs $752.
  • Trees. Voluntary removal of a healthy tree needs Planning review; dead or hazardous trees are handled through a Building Division tree permit.
  • Engineering. Grading and encroachment permits come from Engineering.
  • Fire. CCFD reviews plans when the fire code official requires it, including under the wildland-urban interface code.

Hillsborough permit costs and fees

The Master Fee Schedule is updated every year and approved by the City Council with the budget; the figures below are the adopted FY 2026–27 column. The building permit fee is set from valuation, using a square-foot cost model for new floor area. Plan check is 25% of the building permit fee for projects under $1,000,000 and 75% above that. Several percentage fees and the town’s business license tax are added to each permit.

Hillsborough building fees, adopted FY 2026–27
ItemFee
Valuation $1–$4,000$478
Valuation $4,001–$25,000$478 plus $23.70 per $1,000
Valuation $25,001–$50,000$976.18 plus $52.06 per $1,000
Valuation $50,001–$100,000$2,277.77 plus $30.60 per $1,000
Valuation $100,001–$500,000$3,807.96 plus $11.27 per $1,000
Valuation $500,001–$1,000,000$8,314.03 plus $9.00 per $1,000
Valuation $1,000,001–$5,000,000$11,026.10 plus $1.81 per $1,000
Plan check25% of building permit fee (75% over $1,000,000)
Business license tax (Category 1)0.75% of permit value, $30 minimum
General Plan maintenance0.61% of valuation
Construction vehicle impact fee0.83% of job value
Technology fee1% of permit fee
Construction completion deposit (value over $50,000)2% of valuation, refundable
Revision plan check$235 per hour
Re-inspection$248

Rather talk it over?

Call 1-855-478-4290 →

Worked example: a $200,000 addition falls in the $100,001–$500,000 band, so the permit fee is $3,807.96 plus 100 × $11.27, or $4,934.96, and plan check adds 25% ($1,233.74). The General Plan fee ($1,220), construction vehicle impact fee ($1,660), business license tax ($1,500) and technology fee ($49.35) bring the total to $10,598.05 before state fees, plus a refundable $4,000 completion deposit.

Flat-rate permits, FY 2026–27
ItemFee
Water heater / furnace like-for-like$421 / $421
HVAC replacement / system upgrade$566 / $834
Electrical service / generator / EV charger$942 / $800 / $588
Solar energy storage / battery system$905 / $789
Gas line / plumbing repair$577 / $468
Transfer-of-title sewer and water line testing$545
Demolition: house / pool or spa$1,208 / $727
Tree removal: dead / hazardous with arborist report$287 / $682

Planning fees

ADU zoning clearance is $663 for a state by-right unit and $1,141 where local objective design standards apply. Design review fees include $1,003 for staff review of style or material changes, $2,029 for an addition or accessory structure under 500 square feet, $1,109 for a street-side fence, gate or columns, $3,643 to $3,862 for ADRB review of additions, $4,986 for a new house and $5,739 for a substantial alteration or tear-down. Voluntary tree removal review is $1,076, and appealing a staff decision $4,652.

Trade permits and who may pull them

The Building Division issues the electrical, plumbing and mechanical permits, normally as separate permits from the building permit, and many are flat-rate permits (see the table above). Each extra appliance or unit on a flat-rate trade permit adds $64.

  • Registration. Contractors and consultants register with the town before getting eTRAKiT credentials, giving their state license number.
  • Business license tax. Contractors pay the town’s Category 1 business license tax, 0.75% of permit value with a $30 minimum, collected with the building permit fees.
  • Right-of-way work requires a Class A contractor’s license and liability insurance.
  • Subcontractors must all be listed on the town’s subcontractor sheet before any inspection is called.

Rather not deal with the building department?

Get a free quote →

How to apply for a Hillsborough building permit

1. Meet with Planning

Call or email to book a planner; design review applications require a pre-application meeting, and ADUs start with a ministerial zoning clearance.

2. Register for eTRAKiT

Complete the town’s online registration form to receive a username and password, with your state license number if you are a contractor or design professional.

3. Submit the application and plans

File the application and complete plan set in eTRAKiT, following the plan check requirements and soils report handouts.

4. Answer review comments

Upload resubmittals as complete plan sets, not single pages, and call your permit technician to say they are posted.

5. Pay and receive the permit

Staff contact you when the permit is ready to pay. Pay online by card or e-check (a card processing fee applies) or by check, post the completion deposit, and the permit is issued electronically.

6. Set up the site

Keep stamped plans on site, list subcontractors, and follow the construction impact rules on parking, screening and neighbor notice.

Review, corrections and what causes delay

Revisions to approved plans are billed at $235 an hour. Projects valued at $750,000 or more need a pre-construction meeting with Building and Engineering staff and a qualified job superintendent on site. Under Chapter 15.30, each project has a completion time limit based on its value, from 9 months under $50,000 to 36 months over $6,000,000, and late completion draws penalties of $200 to $1,000 a day charged against the deposit. Starting work without a permit can cost the regular fee plus up to ten times that amount, and lifting a stop work order costs $250 to $1,000.

Inspections in Hillsborough

Call the Building Division at (650) 375-7411 to schedule. The Building page asks you to allow 24 hours for a response and a three-day lead time, and says same-day and next-day requests cannot be accommodated; the town’s permit information page asks for at least 48 hours. After-hours requests can be submitted online.

  • Fees. A same-day cancellation, or an inspector unable to get on site or see the stamped plans and permit card, brings a cancellation fee; work not ready brings a $248 re-inspection fee.
  • Before final. Attach special inspection forms, the subcontractor list, irrigation audits and any landscape architect, architect and engineer letters to the permit in eTRAKiT. Fire protection must be approved by the fire chief before final inspection and the certificate of occupancy.
  • Construction hours. Monday to Friday 8 a.m. to 5 p.m. and Saturday 10 a.m. to 5 p.m.
  • Signs. Construction signs may be no larger than 12 by 15 inches, black letters on white.

Want this handled start to finish?

Get a free quote →

Local details in Hillsborough

  • Flood zones. Hillsborough participates in the National Flood Insurance Program; its current flood map is dated April 5, 2019.
  • Address numbers. Homes 36 to 50 feet from the street need numbers at least 6 inches high, and over 50 feet at least 9 inches, visible from the road.

California building code in Hillsborough

California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments

Hillsborough’s posted Title 15 adopts the 2025 codes and its amendments, including the sprinkler, roof, spark arrestor and address sign rules described above and a local trigger for structural and geotechnical evaluations of existing buildings using ASCE 41 where retrofit is needed.

Hillsborough building permit FAQs

Who issues building permits in Hillsborough?

The town’s Building Division at Town Hall, 1600 Floribunda Avenue ((650) 375-7411, plancheck@hillsborough.net), open Monday to Thursday 8 to 5 and Friday mornings.

Do I need a permit for a fence or for removing a tree?

Yes. Hillsborough lists fences, gates and tree removal among the work that needs a permit; street-side fences also go through design review.

Will my remodel need fire sprinklers?

New homes always do. An existing home over 2,000 square feet or over two stories needs them when permitted additions or alterations exceed 1,500 square feet, or 20% of the floor area for homes over 7,500 square feet, counting work over two years.

How much does a building permit cost?

For a $200,000 addition, the FY 2026–27 permit fee is $4,934.96 and plan check $1,233.74; with the town’s percentage fees and business license tax the total is about $10,598, plus a refundable 2% completion deposit.

Can a homeowner pull a permit?

Yes, as an owner-builder, but only the property owner qualifies, not a business owner or tenant. Owner-builders register for an eTRAKiT login like contractors do.

How far ahead must I book inspections?

Call (650) 375-7411 and allow a three-day lead time; same-day and next-day requests cannot be accommodated.

Is there a deadline to finish construction?

Yes. Chapter 15.30 sets time limits from 9 to 36 months depending on project value, with daily penalties charged against the completion deposit if you run late.

What are the construction hours?

Monday to Friday 8 a.m. to 5 p.m. and Saturday 10 a.m. to 5 p.m.

Inspections are where schedules slip.

Get a free quote →

Hillsborough permit search and official resources

Permit records can be searched in eTRAKiT. For archived plans or microfiche, fill in the microfiche form and visit the Building counter at Town Hall; plans for approved example projects can also be viewed there.

Simplify Hillsborough permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Hillsborough sooner?

Let Alliance prepare, file, and track your Hillsborough permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Hillsborough permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.