Menlo Park’s Building Division, part of Community Development at City Hall, 701 Laurel Street (650-330-6704), issues building permits in the city. The process is entirely paperless: applications, resubmittals, revisions and inspection requests all go through the Accela Citizen Access portal, and there is no over-the-counter review. Fees come from the Master Fee Schedule approved on April 28, 2026, which prices plan check and permits by occupancy, size and construction type rather than by valuation.
What requires a building permit in Menlo Park?
Residential work needs a permit unless it is on the exempt list in Municipal Code Section 12.08.010, which amends the state residential code’s exemption section; non-residential work follows the same approach under Section 12.06.010. The fee schedule shows the range of jobs the city permits, from decks, fences, patio covers, sheds, retaining walls and outdoor kitchens to kitchen and bathroom remodels, window replacements, re-roofs, siding, skylights, dry rot repair, seismic upgrades, fireplaces, pools and demolition.
Common residential permits
- New homes, additions and ADUs
- Kitchen and bathroom remodels, including non-structural ones
- Window and sliding door replacement
- Re-roofing, siding and stucco
- Decks, fences, patio covers and sheds (fees listed)
- Replacing an air conditioner (heat pump rule applies)
- Swimming pools, spas and pool demolition
Local rules that change the scope
- Heat pump instead of a new AC condenser on replacement
- Extra energy measures for additions and alterations
- EV charging in new construction, electric-ready wiring
- Raceway and breaker space near gas appliances
- Single-pass water systems prohibited
- 65% construction waste recycling on jobs of 1,000 sq ft or more
Because the city’s exempt-work lists are local amendments, check them before assuming a small job is permit-free; the fee schedule even lists a fee for a shed up to 120 square feet with no utilities.
What Menlo Park decides and what the state holds
Menlo Park applies the 2025 California Building Standards Code to applications received on or after January 1, 2026, with local amendments in Title 12 of its Municipal Code. Besides the exempt-work sections, those amendments adopt Appendix J for grading (with a rule on imported fill), amend the residential code’s climatic and geographic design criteria, prohibit single-pass water systems in the plumbing code, add energy code requirements for additions and alterations, and add CALGreen rules on EV charging, electric readiness, pre-wiring, construction waste and heat pumps. The city also sets its own fees and ADU ordinance; the City Council adopted an updated ADU ordinance on June 9, 2026, effective July 10, 2026. Contractors are licensed by the state. (The Building Division’s general FAQ still says the city uses the 2022 codes; the code page is the current one.)
Menlo Park building department: who handles permitting
The Building Division reviews plans, issues permits and inspects construction, using the Accela platform for every step. Planning handles zoning and ADU standards. The fee schedule also prices floodplain reviews, heritage tree permits, storm drainage connections and landscape water efficiency checks outside the building tables.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Building Division, City Hall, 701 Laurel Street, Menlo Park, CA 94025 |
| Building permits and questions | 650-330-6704 |
| Inspections | Online, or questions at 650-330-6767 |
| City Hall hours | Monday to Thursday 7:30 a.m. to 5:30 p.m.; every other Friday 8 a.m. to 5 p.m. |
| Walk-in code questions | 1 to 5 p.m. on days City Hall is open; appointments can be booked online |
| Online portal | Accela Citizen Access (applications, resubmittals, revisions, inspections, status) |
Menlo Park permit types
To apply, register for an account on the Accela Citizen Access portal; it is used to create new applications, follow updates, upload corrections and revisions. The forms page has the building permit application and data sheet, the electrical load calculation form, the special inspection form, the deferred submittal form and the smoke alarm affidavit. The city is not offering over-the-counter review.
Residential permits
- New homes, additions and alterations each have their own submittal requirements on the one- and two-family dwelling page, along with a knob-and-tube wiring safety handout.
- Repairs to existing structures have a separate submittal page.
- ADUs. Planning’s ADU page explains the permit process and pre-approved ADUs under the ordinance in effect since July 10, 2026.
- Heat pumps. If your project replaces or upgrades an air conditioning condenser, Section 12.18.110 requires a heat pump instead, unless the extra cost would exceed 20% of the construction cost (shown on the AC-to-heat-pump hardship form) or the system meets the alternative duct sealing, airflow and thermostat requirements.
- Solar and batteries have their own permit information page, and residential solar fees are capped at the state limit.
- Owner-builders. The owner or a licensed contractor may pull a permit, and the city has an owner-builder information page.
Building or remodeling a home here? Alliance handles home building permits, so the crew isn't waiting on the counter.
Commercial permits
Non-residential and multi-family projects have their own permit information page. Tenant improvement plans must be prepared by a registered design professional or architect. Commercial plan check and permit fees use the same size and construction-type tables, and commercial projects pay the 0.58% street impact fee on work valued over $10,000.
For tenant improvements and new commercial builds, Alliance handles commercial permit filing through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Planning. Zoning review and any planning approvals come from the Planning Division.
- Flood zones. The fee schedule charges $1,011 to review a single-family building permit in a flood zone ($2,022 for commercial or multifamily) and $404 for a substantial improvement determination.
- Heritage trees. Heritage tree permits cost $542 each for one to three trees and $270 for each additional tree, plus arborist costs on development projects.
- Landscaping. Water-efficient landscape plan check starts at $809 for a single-family home.
Menlo Park permit costs and fees
The City Council approved the current Master Fee Schedule on April 28, 2026, after a cost-of-service study; its building tables took effect July 1, 2026, and the posted schedule is dated October 12, 2026. Instead of a valuation table, plan check and permit fees for new construction, additions and alterations are set by occupancy group and floor area, with a base cost at a set size plus a rate per extra square foot, multiplied by a construction-type factor (1.00 for wood-frame Type V, rising to 1.46 for Type I).
| Project | Plan check | Permit |
|---|---|---|
| New single-family home, 3,000 sq ft | $10,582.30 plus $3.190 per sq ft above | $4,897.18 plus $0.437 per sq ft above |
| Addition, 250 sq ft | $2,474.23 plus $3.451 per sq ft above | $1,772.48 plus $1.442 per sq ft above |
| Addition, 1,000 / 1,500 sq ft | $5,062.25 / $6,954.50 | $2,854.06 / $3,185.12 |
| Alteration, 1,500 sq ft | $5,905.70 | $2,680.24 |
| Bathroom remodel, non-structural | $350.00 | $593.33 |
| Kitchen remodel, non-structural | $350.00 | $564.48 |
| Windows or sliding doors, first five (each extra $46.16) | $381.00 | $638.44 |
| Residential re-roof | $87.21 | $228.57 |
| Deck / shed up to 120 sq ft without utilities | $500.33 | $402.92 |
| Residential demolition / pool demolition | $353.78 / $212.27 | $255.78 / $153.47 |
Rather talk it over?
Call 1-855-478-4290 →Worked example from the tables: a 500-square-foot wood-frame addition takes the 250-square-foot base plus 250 extra square feet, so plan check is $2,474.23 plus 250 × $3.451 ($3,336.98) and the permit fee $1,772.48 plus 250 × $1.442 ($2,132.98), $5,469.96 together. A new 3,000-square-foot house starts at $15,479.48 for plan check and permit. The schedule then adds a 9% technology fee, an 8% General Plan update fee and state fees.
Other building charges
- Street impact fee: 0.58% of valuation on projects over $10,000, except residential alterations and repairs.
- Storm drainage connection: $450 per single-family lot; transportation impact fees under Chapter 13.26.
- Work without a permit: a penalty equal to the permit fee.
- Reinstating an expired permit or plan check: half the original fee, $50 minimum.
- Re-inspection or late cancellation: $144.25 per half hour; after-hours inspection $432.75 an hour.
- Certificate of occupancy or temporary certificate: $682.
- Expedited outside plan check (if available): 50% of plan check; plan check by appointment for homes from $277 for the first hour.
- Card payments: processing fees are passed through, or a 2.5% convenience fee applies.
Trade permits and who may pull them
Electrical, plumbing and mechanical work is permitted by the Building Division through the same Accela portal. The city’s local amendments shape much of this work: replacing an AC condenser triggers the heat pump rule, the CALGreen amendments add an electrical raceway within three feet of a gas appliance with reserved breaker space, and new construction must meet the city’s EV charging requirements. The electrical load calculation form is on the forms page.
- Who may pull permits. A licensed contractor or the owner as owner-builder.
- Design professionals. Commercial tenant improvements need plans by a registered design professional or architect.
- Special inspections. Special inspection reports, engineer observation letters and surveyor placement letters are uploaded by the contractor to Accela, with copies on site.
How to apply for a Menlo Park building permit
Check zoning, ADU rules, heritage trees and flood zone status with the city before designing.
Create an Accela Citizen Access account; it is required to apply, receive updates and resubmit.
Follow the submittal requirements page for your project type and the green building pages for the local energy and electrification amendments.
Create the application in the portal, upload plans and forms, and pay plan check fees.
Resubmit corrections through Accela; your assigned staff member can answer status questions.
The permit, job bag and approved plans appear in the portal’s documents as the “approved set–permit issued”; keep them on site, on paper at 24 by 36 inches or on a screen of at least 12 inches.
Rather not deal with the building department?
Get a free quote →Review, corrections and what causes delay
There is no over-the-counter review, so even small jobs are reviewed online. Revisions must be submitted before the work they cover is inspected. A permit is valid for 12 months after issuance, the first inspection must happen within that time, and later inspections must follow at least every 180 days; otherwise the permit expires and the work must be resubmitted under the code in force at that time, unless the city grants an extension. Expired permits may be reinstated for half the original fee.
Inspections in Menlo Park
Inspections can be requested only online, through the “Menlo Park Inspection Request” app or the Accela portal. Each trade or item you schedule buys 15 minutes, and the inspector stays only for the time booked, so book several items for a longer inspection (for example, underfloor frame, plumbing and mechanical for a 45-minute underfloor visit). The app books a day only; call 650-330-6767 before 9 a.m. that day for your time. The portal lets you pick a morning or afternoon window.
- On site. The permit, job bag and approved plans must be available to the inspector throughout construction.
- Alarms. A smoke and carbon monoxide affidavit is needed when the inspector cannot get inside, usually on exterior-only work.
- Construction hours. Menlo Park does not limit construction hours as long as the noise ordinance is met.
- Construction waste. Projects of 1,000 square feet or more must salvage or recycle 65% of construction and demolition debris; falling short brings a fine of $1 per square foot, and the schedule lists a $106.50 Green Halo administrative charge.
- Temporary occupancy. Requirements for a temporary certificate of occupancy or final vary by project; ask your inspector.
Local details in Menlo Park
- Flood zones. Menlo Park participates in the National Flood Insurance Program, with a flood map dated April 5, 2019, and is in FEMA’s Community Rating System at class 8, a 10% premium discount for eligible policies.
- Fees for records. Records research costs $213 an hour per address.
California building code in Menlo Park
California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
The city’s Building Code page lists the 2025 codes it adopted, including appendices to the building and residential codes and the new Wildland-Urban Interface Code, and links each local amendment section in Title 12.
Want this handled start to finish?
Get a free quote →Menlo Park building permit FAQs
Who issues building permits in Menlo Park?
The city’s Building Division at City Hall, 701 Laurel Street (650-330-6704). Applications are filed online in the Accela portal.
Can I get a permit over the counter?
No. The city is not offering over-the-counter review; all submittals go through the online portal. Walk-in code questions are answered from 1 to 5 p.m. on days City Hall is open.
How are permit fees calculated?
By occupancy, floor area and construction type, not by valuation. A 500-square-foot wood-frame addition, for example, has a plan check fee of $3,336.98 and a permit fee of $2,132.98, before the 9% technology and 8% General Plan fees.
Do I have to install a heat pump when I replace my air conditioner?
Generally yes. Section 12.18.110 requires a heat pump instead of a new AC condenser, unless the cost difference exceeds 20% of the job or the system meets the alternative duct and thermostat requirements.
Can I be my own contractor?
Yes. The owner or a licensed contractor may pull a building permit, and the city posts owner-builder information.
How long is a permit valid?
Twelve months from issuance for the first inspection, then at least one inspection every 180 days. An expired permit must be resubmitted under the current code unless extended or reinstated.
How do I schedule an inspection?
Online only, through the Menlo Park Inspection Request app or the Accela portal. Each item booked is a 15-minute slot.
Are there limits on construction hours?
Not separately: the city allows construction as long as the noise ordinance is met.
Menlo Park permit search and official resources
Check permit status and inspection results in the Accela portal by record number (for example, BLD2026-00012). For copies of older permits or house plans, contact the permit team; the forms page has the property record search and plans duplication request forms.
Inspections are where schedules slip.
Get a free quote →- Menlo Park Building Division
- General information and FAQs
- Building codes and local amendments
- One- and two-family homes and ADU permit information
- Green building and energy amendments
- Heat pump replacement requirement
- Online services
- Scheduling inspections
- Accela Citizen Access permit portal
- Accessory dwelling units
- Master Fee Schedule page
- Master Fee Schedule (October 12, 2026)
- 2025 California Title 24 building standards
- FEMA Community Status Book, California
Simplify Menlo Park permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Menlo Park sooner?
Let Alliance prepare, file, and track your Menlo Park permits while your crew stays on the job.
More California permitting guides
San Mateo County
Read guide →Millbrae
Read guide →Redwood City
Read guide →Merced Building Permit Guide
Read guide →Merced County Building Permit Guide
Read guide →Mill Valley Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Menlo Park permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.