Building permits in Hercules involve two governments. The City’s Building Department & Permit Services at 111 Civic Drive ((510) 799-8244) is the front door: it posts the City’s contractor and owner-builder applications and handouts, answers permit questions and collects City development impact fees and business licenses. Contra Costa County Building Inspection lists Hercules among the areas it covers and inspects the work, and the permit rule the City quotes requires permits from the county building official. Inspections are booked on the County’s automated line, 925-646-4108. The City counter is open Monday to Thursday from 8 a.m. to 1 p.m., with afternoon appointments until 5 p.m., and is closed on Fridays.
What requires a building permit in Hercules?
The permit rule the City quotes is wide: no person or company may erect, construct, enlarge, alter, repair, move, improve, remove, convert or demolish a building or structure, or install or connect regulated equipment, without first getting the necessary permits from the county building official. Against that, the City’s Building page posts a short list of residential work that needs no building permit, quoted from the 2022 California Residential Code, and warns that an exemption never allows work that breaks the code or other local laws.
No building permit
- One-story detached accessory buildings of no more than 120 square feet
- Water tanks on grade holding no more than 5,000 gallons, no taller than twice their width
- Painting, papering, tiling, carpeting, cabinets, countertops and similar finish work
- Prefabricated above-ground pools at a house that are under 24 inches deep and hold no more than 5,000 gallons
- Window awnings on houses and accessory buildings projecting no more than 54 inches, without extra support
- Shade cloth structures for nursery or farm use; oil derricks
Still needed
- Electrical, plumbing and mechanical permits, even where the structure itself is exempt
- Planning, Sanitary District or Contra Costa County Environmental Health approval for some small accessory buildings, depending on their number, size, location and foundation
- A protective pool barrier when the water is over 18 inches deep
Cabinet work is on the exempt list, but the City’s page asks owners to call (510) 799-8244 to clarify cabinet jobs, remodels and additions before starting.
What Hercules decides and what the state holds
Hercules sets its own development impact fees, collects the West County Subregional Transportation Mitigation Program fee under its 2019 ordinance for the regional committee, charges a public benefit fee on the Bayfront project, and requires a business license under Title 8, Chapter 6 of its municipal code. Planning decides use permits and zoning questions. Building inspection is done by Contra Costa County Building Inspection, the permit rule names the county building official, the building code itself is the state code, and contractor licenses are state licenses.
Short on time to read all of this?
Get a free quote →Hercules building department: who handles permitting
A Contra Costa County Department of Conservation and Development handout on building inspection requirements lists Hercules as one of six County Building Inspection areas, together with Lafayette, Moraga, Orinda, Clayton and unincorporated County land. The County’s daily inspection schedule shows its inspectors at Hercules addresses on County permit numbers, and the permit rule quoted on the City’s Building page requires permits from the county building official. Hercules projects begin at the City’s Building Department & Permit Services counter, part of the Planning & Building Department that collects the City’s application processing and impact fees. The County’s wider rules are in our Contra Costa County building permit guide.
| Office | Details |
|---|---|
| City Building Department & Permit Services | 111 Civic Drive, Hercules, CA 94547; (510) 799-8244; Monday–Thursday 8 a.m. to 1 p.m., 1 to 5 p.m. by appointment; closed Fridays |
| Planning (use permits) | (510) 799-8244 |
| Contra Costa County Building Inspection | 30 Muir Road, Martinez, CA 94553; 925-655-2704; Building Code Hotline 925-655-2737; Monday–Thursday 7:30 a.m. to 5 p.m., Friday 7:30 a.m. to 4 p.m. |
| County Application and Permit Center | 30 Muir Road, Martinez; 925-655-2700; fax 925-655-2744 |
| County inspection scheduling | 925-646-4108 (automated phone system) |
| Business licenses (Neumo, for the City) | (866) 240-3665; hercules.bizlicenseonline.com |
| Questions and complaints | Hercules Connect, the City’s online request system; City Hall main line (510) 799-8200 |
Hercules permit types
Hercules uses two application forms, chosen by who will do the work: the Application for Contractors, and the Owner Builder Application for property owners building or improving their own property. A fillable general Building Permit Application is also posted. Project handouts list the requirements for the most common jobs.
Residential permits
- ADUs. An Accessory Dwelling Unit Submittal Checklist sets out the plans needed; the multifamily impact fee table lists a fire facilities fee of $881 for an accessory dwelling unit.
- Remodels. Separate residential bathroom and kitchen remodel handouts, and a residential smoke and carbon monoxide alarm handout.
- Re-roofs and windows. Residential re-roof and window replacement handouts.
- Equipment. Residential furnace and water heater handouts.
- Retaining walls and pools. A retaining wall handout and the swimming pool and spa installation handout, which covers barriers.
Building or remodeling a home here? Alliance handles residential permit applications, so the crew isn't waiting on the counter.
Commercial permits
Commercial, office, industrial and hotel projects follow the same path, City counter first and County inspection after, and pay impact fees by building area or room count instead of by dwelling unit. A new business must first get any use permit Planning requires and then a business license; out-of-town contractors are exempt from the use permit step and go straight to the license.
For tenant improvements and new commercial builds, Alliance handles commercial building permits through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Planning: zoning review and any use permit, through the Planning & Building Department at (510) 799-8244.
- Sanitary district and Environmental Health: may be needed for accessory buildings, depending on size, location and foundation, as the Building page notes.
- Encroachment permit: the City issues its own encroachment permits for work in the public right-of-way ($387 per permit, or $197 for a temporary one).
- Impact fees: development impact fees for new homes, apartments and commercial space, effective September 23, 2025.
Hercules permit costs and fees
The City’s fees are in its Master Fee Schedule for fiscal year 2026-27, adopted by the City Council as Resolution 26-066 on October 13, 2026 and effective that day. Its Building Inspection Division section has no valuation table for the building permit itself: for any fee not listed in the County or City schedule, the City follows the most current edition of the UBC fee schedule, so ask the counter at (510) 799-8244 for the building fee on your plans. The schedule does set the add-ons that are figured from that building fee or from valuation:
| Item | Fee |
|---|---|
| Title 24 accessibility plan check | 25% of the building fee |
| Title 24 energy plan check | 25% of the building fee |
| Filing fee | 25% of the building fee |
| General Plan update cost recovery | 1% of the construction value of any permit issued |
| Green building fee (state) | $1 to $4 for valuations up to $100,000, plus $1.01 for each further $25,000 or part |
| Demolition inspection review | $73 |
| Sewer connection (if not paid through an assessment district) | $5,632 |
| Pool sewer connection | 10% of the building permit fee |
| Sewer lateral certificate | $240 |
Seismic (SMIP) and green building fees are collected by the City and passed to the state. Planning fees in the schedule include the City’s 5% imaging fee and 5% technology enhancement fee. The development impact fees below were posted with an effective date of September 23, 2025, and the 2026-27 schedule carries the same single-family amounts.
Rather talk it over?
Call 1-855-478-4290 →| Fee | Single-family home | Multifamily unit |
|---|---|---|
| Park and recreation facilities | $1,770 | $1,072 |
| General public facilities | $858 | $538 |
| Police facilities | $1,522 | $950 |
| Fire facilities | $1,886 | $1,163 apartment; $881 ADU |
| Transportation facilities | $6,204 | $3,511 |
| Sewer facilities | $4,857 | $4,857 |
| Community development tax | $1,500 | $1,500 |
| West County STMP (AB 3177 eligible) | $6,915 ($6,010) | $3,404 ($2,961); $3,407 in the 2026-27 schedule |
| Public benefit fee, Bayfront project only | $4,000 | $2,350 |
Worked example from that table: a new single-family home outside the Bayfront project pays $25,512 in City-collected impact fees ($1,770 + $858 + $1,522 + $1,886 + $6,204 + $4,857 + $1,500 + $6,915), or $24,607 where the lower AB 3177 STMP rate applies.
| Fee | Retail / flex | Office | Industrial |
|---|---|---|---|
| General public facilities | $0.69 | $0.28 | $0.49 |
| Police / fire facilities | $0.30 / $1.00 | $0.51 / $1.00 | $0.22 / $1.00 |
| Transportation facilities | $8.00 | $6.00 | $6.00 |
| Sewer facilities | $0.62 | $1.00 | $1.00 |
| West County STMP | $8.37 | $11.08 | $7.06 |
The 2026-27 schedule lists the STMP one cent higher per square foot ($8.38, $11.09 and $7.07) and $6,610 per fuel pump. Hotels pay per room, including $2,277 for transportation and $1,878 for sewer. Some projects may qualify for lower transportation fees under Section 66005.1 of the Mitigation Fee Act, based on factors such as access to transit and the housing and parking provided on site; reductions are negotiated through a development agreement with the City Manager’s office.
Trade permits and who may pull them
Electrical, plumbing and mechanical work always needs a permit in Hercules, and County Building Inspection inspects it; the County’s schedule shows electric meter releases and plumbing tests at Hercules addresses, and the City’s furnace and water heater handouts cover the most common replacements. Contractors file on the Application for Contractors and must hold the matching state CSLB license, while property owners doing their own work use the Owner Builder Application.
Rather not deal with the building department?
Get a free quote →Every organization operating in Hercules needs a City business license (the County’s contractor handout also marks Hercules as requiring one), including home-based businesses and owners who rent out a home or rooms. Contractors based outside Hercules skip the use permit step and apply directly through the City’s licensing partner Neumo (formerly Avenu Insights): online, by emailing a paper form and paying by phone, or by mailing the form with a check. Licenses renew by January 1 with a 30-day grace period to January 31; from February 1 the late fee is 25% of the license amount and grows by 25% a month up to 100%.
How to apply for a building permit in Hercules
Ask Planning at (510) 799-8244 whether the project or business needs a use permit or other zoning approval.
Use the Application for Contractors, or the Owner Builder Application if you are doing the work on your own property.
Follow the City handout for the job (ADU, remodel, re-roof, windows, furnace, water heater, retaining wall or pool).
Get any Sanitary District or Contra Costa County Environmental Health sign-off and an encroachment permit for work in the street.
Bring the application to Building Department & Permit Services, 111 Civic Drive, Monday to Thursday before 1 p.m., or book an afternoon appointment; ask there how your plans are routed for review.
Pay the permit and City impact fees, then book each inspection on the County line, 925-646-4108, or in the County’s ePermits Center.
Review, corrections and what causes delay
Plans are checked against the current California Building Code and local regulations. The City’s Building page names the approvals that can hold up even a small job: a shed or other accessory building may need Planning, Sanitary District or County Environmental Health approval depending on how many there are, their size and location and whether they sit on a permanent foundation, and cabinet work, remodels and additions are worth a call to the City counter first.
Inspections in Hercules
Every Hercules building permit requires a building inspection, and Contra Costa County Building Inspection makes them. Book on the County’s automated phone system at 925-646-4108 or in the County’s online ePermits Center, which needs no log-in for scheduling; give a contact name and phone number for the day. Same-day requests on the automated line are accepted until 5:30 a.m., Monday to Friday, and same-day requests left as voicemail are not scheduled. Cancel or reschedule online before 6:00 a.m. on the inspection day, or call the same line after that cut-off.
Want this handled start to finish?
Get a free quote →The County posts each business day’s inspection schedule after 8:45 a.m., with three-hour arrival windows; search it by street address, permit number or parcel number. To avoid a cancelled visit and a re-inspection fee, have the permit and the reviewed, stamped plans on site, an adult of 18 or older present, the work ready and open to view, and earlier corrections done. City handouts cover common inspection points such as smoke and carbon monoxide alarms and pool barriers where the water is over 18 inches deep.
California building code in Hercules
The City’s Building page says projects are checked for compliance with the current California Building Code and local regulations. FEMA’s Community Status Book lists the City of Hercules (community 060434) as participating in the National Flood Insurance Program, with flood maps effective March 21, 2017.
California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
Hercules permit search and official resources
The County’s ePermits Center shows inspection time frames, inspection status and permit history for County permits, and its daily inspection schedule can be searched by address, permit or parcel number. For City records, impact fee receipts or a business license, contact Building Department & Permit Services at (510) 799-8244 or use Hercules Connect.
- Hercules Building page: permit rules and exemptions
- Building Department & Permit Services contact and hours
- Building permit applications (contractor and owner-builder)
- Building forms, handouts and guidelines
- Development impact fees
- Business licenses
- Hercules business license online filing (Neumo)
- West County STMP fee information
- Master Fee Schedule FY 2026-27
- Master Fee Schedule FY 2026-27, Resolution 26-066 (PDF)
- Contra Costa County building inspections
- County daily building inspection schedule (PDF)
- County Building Inspection areas and contractor licenses (PDF)
- Contra Costa County Building Inspection contacts
- FEMA Community Status Book, California
Inspections are where schedules slip.
Get a free quote →Hercules building permit FAQs
Who handles building permits in Hercules?
Two offices. The City’s Building Department & Permit Services, 111 Civic Drive, is the starting point and collects City fees; Contra Costa County Building Inspection, the county building official named in the City’s permit rule, inspects the work. The City counter is open Monday to Thursday and closed on Fridays.
How do I schedule an inspection in Hercules?
Call the County’s automated line, 925-646-4108 (same-day requests until 5:30 a.m.), or use the County’s ePermits Center.
Do I need a permit for a shed?
Not for a one-story detached shed of 120 square feet or less, though Planning or other approvals may still apply.
Does an above-ground pool need a permit?
Not if it is prefabricated, under 24 inches deep and holds no more than 5,000 gallons; water over 18 inches still needs a barrier.
What impact fees does a new house pay?
$25,512 in City-collected impact fees outside the Bayfront project, under the rates effective September 23, 2025.
Can I pull a permit as the owner?
Yes, on the City’s Owner Builder Application.
Do out-of-town contractors need a Hercules business license?
Yes. They skip the use permit step and apply through Neumo online, by email or by mail.
Does electrical work need a permit?
Yes. Electrical, plumbing and mechanical work always requires a permit in Hercules, and the County inspects it.
Simplify Hercules permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Hercules sooner?
Let Alliance prepare, file, and track your Hercules permits while your crew stays on the job.
More California permitting guides
Contra Costa County
Read guide →Lafayette
Read guide →Martinez
Read guide →Hermosa Beach Building Permit Guide
Read guide →Hesperia Building Permit Guide
Read guide →Highland Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Hercules permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.