In Emeryville, building permits come from the city’s own Building Division in the Community Development Department, 1333 Park Avenue (510-596-4310), whose Chief Building Official, Jason Williams, is also the Fire Code Official. Applications are emailed as PDFs or filed at the counter, and the division aims to process emailed applications within 1 business day. Under the posted FY 2025-26 Master Fee Schedule the building permit costs 0.80% of construction valuation (minimum $193), with plan check at 65% of that fee paid when you submit.
What requires a building permit in Emeryville?
The Building Division’s own summary is short: building permits are required for most construction and repair work, and the division issues building and fire permits on the same application. Its fee schedule shows what that covers: building permits (including signs and demolition), separate or combined electrical, plumbing and mechanical permits, solar and solar thermal systems, grading permits, fire suppression systems and sewer connections.
Permit required
- New buildings, additions, remodels and tenant improvements
- Signs and demolition (both covered by the building permit fee)
- Electrical, plumbing and mechanical work
- Re-roofs (with a mid-job inspection at 50% complete)
- Rooftop solar and battery storage
- Fire sprinklers, alarms and smoke detection systems
- Grading and new sewer connections
Exempt under the posted amendments
- Sidewalks, decks and driveways no more than 30 inches above grade that are not attached, not over a basement or story below, and not part of an accessible route
- Painting, papering, tiling, carpet, and resurfacing cabinets or countertops
Emeryville rewrote items 6 and 7 of building code section 105.2 this way, so its deck and driveway exemption carries extra conditions. Any work in a public street or sidewalk also needs an encroachment permit from Public Works.
What Emeryville decides and what the state holds
Emeryville enforces the state code and keeps its local rules in Title 8 of the Municipal Code. The amendments the division links are Ordinance No. 22-013, adopted November 15, 2022: they add sprinkler triggers for assembly and mercantile spaces and renovations, construction-site fire safety rules, seismic gas shut-off valve standards and a “completion permit” for work left unfinished when a permit expires. The city sets its own fees, a 65% construction waste diversion rule, and design criteria for large projects: 85 mph wind, exposure B east of the freeway and C west of it, and 3 inches an hour of rain, on a site 2–10 km from the Hayward Fault.
Emeryville building department: who handles permitting
The Building Division handles code administration, plan review and field inspections for every property inside city limits. Large projects are plan-checked by outside consultants under contract to the city, and the architect or engineer may call the assigned consultant directly on technical points; status questions go to the division’s plan check and permit technician. Fire sprinkler and alarm inspections are made by the Alameda County Fire Department’s code compliance staff.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Building Division, Community Development Department, City Hall, 1333 Park Avenue, Emeryville, CA 94608 |
| Phone | 510-596-4310 |
| Inspection request line | 510-596-4315 |
| Permit counter | Monday–Thursday 9 a.m.–noon drop-in, 1–4 p.m. by appointment; Fridays by appointment |
| Cashier | Monday–Thursday 9 a.m.–noon and 1–5 p.m.; Fridays by appointment |
| Chief Building Official / Fire Code Official | Jason Williams |
| Flood program | Participating in the National Flood Insurance Program (FEMA community 060005; current map December 21, 2018) |
Emeryville permit types
One form, the Emeryville Building Permit application, is used for building and fire permits. It names the applicant, the architect or engineer with license number, and the contractor with CSLB license class and number, and carries the licensed-contractor, owner-builder and workers’ compensation declarations.
Residential permits
- Remodels, additions and new homes are priced on valuation; the Chief Building Official sets the valuation at the higher of your declared figure or the Engineering News-Record building cost index for the Bay Area.
- Solar: residential systems up to 15 kW carry a flat $450 fee with no general plan or technology fee, and the city runs SB 379 online permitting for rooftop solar and batteries up to 38.4 kW on single-family homes, detached ADUs and duplexes.
- ADUs: development impact fees are $0 for ADUs and junior ADUs on the FY 2025-26 schedule; building, plan check and school fees still apply.
- Re-roofs need an in-progress inspection once at least half the roof is done.
Building or remodeling a home here? Alliance handles home building permits, so the crew isn't waiting on the counter.
Commercial permits
Complex R&D and larger tenant improvement reviews run 7–10 business days on the expedited track, as set by the Chief Building Official. Foundation-only and other partial permits can be issued before the full set is approved, at the applicant’s risk, with grading plans, a soils report, structural plans about 85% complete and architectural plans about 15% complete; partial plumbing, electrical or mechanical permits are not issued. Projects creating new floor area must supply one extra set of floor plans for the County Assessor, and public art compliance is shown at the first building permit.
For tenant improvements and new commercial builds, Alliance handles commercial permit filing through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Planning approvals. Design review, use permits and subdivisions go through the Planning Division; minor design review costs $668 and major design review is billed at cost against a $3,000 deposit. Starting work without a required planning approval costs five times the approval fee.
- Pre-plan check meeting. Design teams are encouraged to meet the Chief Building Official and plan check engineer early; meetings are billed at $221 an hour with a 2-hour minimum.
- Construction waste plan. Projects permitted since November 2, 2017 must divert 65% of debris without counting landfill cover; plans go through Green Halo Systems for $161. Small jobs under 2 pounds of waste per square foot and residential remodels that add no living space are exempt.
- Encroachment. Work in the public right-of-way needs a Public Works encroachment permit.
Emeryville permit costs and fees
Emeryville’s fees are in the citywide Master Fee Schedule. The newest schedule posted on the Finance and Building pages is FY 2025-26, effective July 1, 2025 and approved April 15, 2025. Most building fees are percentages of construction valuation or of the building permit fee.
| Item | Fee (FY 2025-26) |
|---|---|
| Building permit (includes sign and demolition permits) | 0.80% of valuation, $193 minimum |
| General plan maintenance / technology fee | 0.50% / 0.10% of valuation (not on solar) |
| Plan check, initial review plus one resubmittal | 65% of the building permit fee, paid at submittal |
| Title 24 energy review (where required) | 12.5% of the building permit fee |
| Electrical / plumbing / mechanical with a building permit | 20% / 18% / 17% of the building permit fee |
| Electrical, plumbing or mechanical permit on its own | 1% of valuation, $193 minimum |
| Residential solar up to 15 kW | $450 flat |
| Grading permit / grading plan review | 1% of valuation / 65% of the grading fee ($161 minimum) |
| Further resubmittals, in house | $240 an hour, 2-hour minimum |
| Expedited plan check (3–5 day first review) | Full plan check fees plus 50%, minimum $500 |
| Re-inspection / after-hours inspection | $220 each / $178 an hour |
| Temporary or final certificate of occupancy request | $352 |
| Sewer connection, residential | $1,853 per single-family dwelling equivalent |
| School fees (EUSD rate), residential 500 sq ft or more | $5.17 per sq ft |
Rather talk it over?
Call 1-855-478-4290 →The plan check line also lists 50% of the permit fee and a $240 hourly rate beside residential work under $100,000, so ask the division which basis applies to a small residential job. Work done without a required permit is charged five times the permit cost. Card payments carry a 3.0% non-refundable service fee, and Finance does not take payments by phone.
Impact fees. The FY 2025-26 development impact fee table (valid through June 30, 2026) charges $8,269 for a new single-unit home ($4,950 park and recreation plus $3,319 transportation) and $41,742 per rental apartment unit, including the affordable housing fee; ADUs and junior ADUs pay $0.
Worked example. A commercial tenant improvement valued at $200,000, with electrical and mechanical permits issued alongside and a Title 24 energy review: building permit $1,600 (0.80%), plan check $1,040 (65%), general plan maintenance $1,000, technology fee $200, electrical $320 (20%), mechanical $272 (17%) and energy review $200 (12.5%), for $4,632 in city fees, plus $40 for the state seismic fee (0.02%) and $8 for the Building Standards Commission fee.
Trade permits and who may pull them in Emeryville
Electrical, plumbing and mechanical permits are issued by the Building Division. Issued with a building permit they are priced as a share of it (20%, 18% and 17%); issued on their own they cost 1% of valuation, with a $193 minimum either way. Gas shut-off valves, whether required or installed voluntarily under a plumbing permit, must meet the city’s seismic valve rules: motion-activated valves are mounted rigidly to the outside of the building on the owner’s side of the meter.
The application offers three paths: a licensed contractor signs the CSLB declaration; an owner-builder declares that they or their wage-paid employees will do the work on a structure not offered for sale; or an owner declares that only licensed contractors will build it. All sign the workers’ compensation declaration.
Business license. The city requires every business operating in Emeryville, including those based elsewhere, to obtain and keep an Emeryville business license, so out-of-town contractors working in the city need one too.
Rather not deal with the building department?
Get a free quote →How to apply for an Emeryville building permit
If the project needs design review or a use permit, get the Planning Division approval before the building submittal.
Use the Emeryville Building Permit form and attach plans stamped and signed by the architect or engineer of record (digital stamps are accepted), calculations and supporting documents.
Email the PDFs or a file-share link to the plan check and permit technician listed on the division’s page, or bring them to the counter during drop-in hours (Monday–Thursday, 9 a.m. to noon). Expect an email confirmation within 1–2 business days.
A complete application includes paid plan review fees. The city emails an invoice; pay by cash, check or card at the cashier or by card online.
Plan check covers the first review and one resubmittal; further rounds are billed hourly. Large projects are reviewed by the city’s consultants.
School, sewer and impact fees are settled before issuance. After approval, print the approved drawings to scale and deliver them to City Hall.
Review, corrections and what causes delay
An application is not complete until the plan review fee is paid. For a faster first review, the Chief Building Official may grant expedited plan check (3–5 business days for Building and Fire only) if you ask in writing before submitting; requests made at submittal are refused, and flat-fee solar permits are not eligible. Projects needing Planning or Public Works approval fall outside that turnaround. A permit lapses if work does not start within 180 days or stops for 180 days; renewing an expired permit needing one final inspection costs $193.
Inspections in Emeryville
Request inspections on the Inspection Request Line, 510-596-4315, the day before, and no later than 6 a.m. on the day you want; requests more than 1 business day ahead are not taken. Leave a phone number, because the office does not call back to confirm. Inspectors work Monday to Friday, 8 a.m. to 4 p.m.; after-hours inspections cost $178 an hour with a 2-hour minimum on weekdays and 4 hours on weekends.
- The contractor must confirm the work is ready and be on site, with a ladder where needed.
- Signs get an in-progress inspection on installation day; re-roofs at 50% complete.
- Inspectors will not approve work that departs from the approved drawings; revisions are reviewed at the office, not in the field.
- A $220 re-inspection fee can apply when work is not ready, corrections are incomplete, the permit card or plans are missing, or there is no access.
- Fire sprinkler and alarm systems are inspected by the Alameda County Fire Department.
- Temporary and final certificates of occupancy are issued on a formal request to the Chief Building Official after the $352 request fee is paid; the occupancy letter can take a week.
General construction noise is limited to 7 a.m. to 6 p.m., Monday to Friday, under Municipal Code section 5-13.05.
California building code in Emeryville
California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
Want this handled start to finish?
Get a free quote →The Building Division lists the 2025 building, residential, green, mechanical, plumbing, energy, electrical and fire codes as in effect from January 1, 2026, and will not accept new applications under the 2022 codes after that date. The local amendment text it links, Ordinance No. 22-013 of November 15, 2022, was written for the 2022 codes; its findings cite the North Hayward fault 2–4 km away and Interstates 80 and 580, whose bridges could cut districts off from emergency crews.
Frequently asked questions
Who issues building permits in Emeryville?
The City of Emeryville’s Building Division, at City Hall, 1333 Park Avenue, issues building and fire permits for all property inside the city. Outside consultants review large projects for the city.
How much does a building permit cost in Emeryville?
On the FY 2025-26 schedule the permit is 0.80% of valuation (minimum $193), plus plan check at 65% of that fee and general plan and technology fees of 0.50% and 0.10% of valuation. A $200,000 tenant improvement with electrical, mechanical and energy review comes to $4,632 in city fees.
Can I apply online?
Applications are emailed as PDFs or file-share links, or filed at the permit counter; there is no separate permit portal on the division’s pages. Payment can be made online by card after you receive the invoice.
How do I schedule an inspection?
Call 510-596-4315 the day before, or by 6 a.m. on the day. The line does not take requests more than one business day ahead.
How long is an Emeryville permit valid?
It becomes invalid if work does not start within 180 days of issuance or stops for 180 days. An extension request or a renewal for a permit needing one final inspection costs $193.
Do I need a business license to work in Emeryville?
Yes. The city requires every business operating in Emeryville, including those based outside it, to hold an Emeryville business license.
Can I get a faster plan review?
Possibly. Expedited plan check (3–5 business days for Building and Fire) must be requested in writing before submittal and costs the full plan check fee plus 50%, minimum $500.
Emeryville permit search and official resources
Emeryville’s pages show no public online permit search. Copies of plans are requested from the Building Division ($161 per request, except counter review), and microfilm or photocopies cost $0.50 or $1.00 a page for projects up to $100,000.
Inspections are where schedules slip.
Get a free quote →- Building Division: codes in effect, contacts, hours
- Building and fire permits and programs
- Building permit submittals and payment
- Emeryville Building Permit application (PDF)
- Large projects, expedited review and partial permits
- Construction guidelines and inspection instructions (PDF)
- Master Fee Schedule FY 2025-26 (PDF)
- Development impact fees FY 2025-26 (PDF)
- Ordinance No. 22-013, local building amendments (PDF)
- Construction and demolition waste rules
- Streamlined rooftop solar permitting
- Planning Division
- Business licensing and starting a business
Simplify Emeryville permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Emeryville sooner?
Let Alliance prepare, file, and track your Emeryville permits while your crew stays on the job.
More California permitting guides
Alameda County
Read guide →Fremont
Read guide →Hayward
Read guide →Encinitas Building Permit Guide
Read guide →Escondido Building Permit Guide
Read guide →Eureka Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Emeryville permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.