Building permits in Hayward are handled by the City’s Building Division at the Permit Center, 777 B Street, 1st floor lobby, Hayward, CA 94541. The Hayward e-Permits Portal takes applications, adds contractors to a project, collects fees, issues permit downloads and schedules inspections, and it shows the inspector’s estimated arrival time and the results.
This guide covers the City of Hayward’s Building Division, its FY 2027 fees and its inspections. Review times, the inspection cut-off and the over-the-counter list come from the City’s Current Codes & Permit Process handout, revised 10-6-21, which is still linked from the Building Division page.
What requires a building permit in Hayward?
The 10-6-21 handout says most Hayward permits are issued over the counter, the same day or within 24 hours: re-roofing, water heaters, like-for-like window replacements, stucco or siding replacement, minor non-structural repairs, emergency repairs and minor electrical work. Residential additions and alterations and new buildings go through plan review; see the review times below.
Since July 2nd, 2019 a City ordinance requires mandatory screening of potential soft-story buildings, typically wood-framed multi-story buildings permitted before January 1, 1979.
Short on time to read all of this?
Get a free quote →California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
Who handles permitting in Hayward?
| Office | Handles | Contact |
|---|---|---|
| Building Division | Building permits, plan check, inspections | (510) 583-4140; e-permits@hayward-ca.gov |
| Permits | General permit questions | (510) 583-4005 |
| Planning Division | Planning review | (510) 583-4216 |
| Fire Prevention | Fire review | (510) 583-4900 |
| Development Services Engineer | Minor and Major Encroachment Permits | (510) 583-4212 |
Permit Center hours: Monday through Thursday 9 a.m. to 1 p.m. for walk-ins and virtual appointments, 1 p.m. to 5 p.m. by appointment only, in person or virtual; Friday 8 a.m. to 5 p.m. by virtual appointment only.
Not sure this scope needs a permit?
Get a free quote →Local rules in Hayward
- Business license: the handout says contractors must hold a City of Hayward Business License to obtain permits.
- Local amendments: Hayward has minor amendments to the Mechanical and Electrical Codes, adopts no CalGreen tiers locally, and approves ABS, PVC and PEX plastic pipe.
- Public right-of-way: work in streets and sidewalks needs a Minor or Major Encroachment Permit; call the Development Services Engineer at (510) 583-4212 for the submittal list. $1,000,000 commercial general liability coverage is among the requirements.
- Construction hours: Monday to Saturday 7 a.m. to 7 p.m.; Sundays and holidays 10 a.m. to 6 p.m.
Contractors are licensed statewide by the Contractors State License Board (Classes A, B, B-2 and C) for work of $1,000 or more or any permitted work; a city may also require a business licence or tax registration. Contractor licensing in California
Hayward permit costs and fees
Building fees come from the Adopted FY 2027 Master Fee Schedule, effective July 1, 2026.
Rather talk it over?
Call 1-855-478-4290 →- Valuation-based permits: the building plan check fee is 1.0 times the building inspection fee; planning review and fire review are each .35 times it; a technology fee of .09 times it is added.
- Hourly work: $227.00 per hour for plan check, inspections or other administrative services.
- Flat fees: residential solar PV up to 15kW $454.00 per system; residential gas water heater $113.00; heat pump water heater $227.00; residential heating and/or cooling equipment, including ducts, $340.00.
- Card payments: a 4% convenience fee applies to credit card transactions over $250.
How to get a building permit in Hayward
Re-roofing, water heaters and like-for-like windows are usually issued the same day or within 24 hours.
Submit the application, add contractors and pay fees online.
The 10-6-21 handout lists 15 business days for a first submittal of residential additions and alterations, 10 for resubmittals, and 25 business days for new buildings.
Issued permits are downloaded from the portal.
Book them in the portal and check the inspector’s estimated arrival time.
Rather not deal with the building department?
Get a free quote →A building permit carries a validity period and can expire if work does not start or stalls between inspections; confirm the expiry with Hayward’s Building Division on phased or delayed work. Permit validity in California
Inspections in Hayward
Inspections are scheduled in the Hayward e-Permits Portal, which shows the inspector’s estimated time of arrival and the results. The 10-6-21 handout says building inspections requested before midnight are scheduled for the following day, and all residential inspections are done by a single inspector assigned to the area.
Official Hayward permitting resources
These are the primary sources behind this guide. Codes, fee schedules and procedures change — confirm the position for your filing date.
- Hayward Permit Center
- Hayward Building Division
- Hayward Master Fee Schedule
- Current Codes & Permit Process handout (rev. 10-6-21)
- Hayward encroachment permits
Want this handled start to finish?
Get a free quote →Frequently asked questions
What is the Hayward Building Division’s phone number?
(510) 583-4140, email e-permits@hayward-ca.gov. (510) 583-4005 is the general Permits line at the Permit Center.
Is plastic pipe allowed in Hayward?
Yes. The Building Division says ABS, PVC, PEX and similar materials are approved for use.
Does Hayward charge extra for credit card payments?
Yes. A 4% convenience fee applies to credit card transactions over $250.
Simplify Hayward permitting with Alliance Permitting
Inspections are where schedules slip.
Get a free quote →- Work out which city counters and outside agencies the project has to go through
- Prepare and upload the application, plans and forms in the city’s portal
- Book the inspections and follow the permit through to final
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Hayward sooner?
Let Alliance prepare, file, and track your Hayward permits while your crew stays on the job.
More California permitting guides
This guide is provided by Alliance Permitting for general information about Hayward permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.