Alameda County building permits come from the Public Works Agency’s Building Inspection Department in Hayward. Apart from flood control, the agency primarily serves the unincorporated areas of the county.

Authority: ACPWA Building Inspection DepartmentServes: Primarily the unincorporated areasPhone: (510) 670-5440
Building Inspection
(510) 670-5440permitbid@acpwa.org
Inspection request line
(510) 670-543424 hours a day, seven days a week
Minimum fee
$140.00Schedule A, effective July 1, 2024
ADU plan review
20 business daysFirst review, after 5 for intake

Building permits for unincorporated Alameda County are issued by the Building Inspection Department of the Alameda County Public Works Agency (ACPWA). Apart from flood control, ACPWA “primarily serves the unincorporated areas of Alameda County.” The unincorporated communities include Ashland, Castro Valley, Cherryland, Fairview, Hayward Acres, San Lorenzo, Sunol and rural east county communities outside the cities of Livermore, Dublin and Pleasanton.

This guide covers the County’s Building Inspection Department. The fee schedule the County links (effective July 1, 2024) and its inspection-request brochure are both filed under “Archived” file names, so their figures may be out of date; confirm with the Department.

What requires a building permit in Alameda County?

The County’s Q&A on permit exemptions says window replacement always needs a building permit, because of the California Energy Code. Trellises, arbors, patio covers and similar sunshade structures at single-family homes may be exempt if each is no more than 120 square feet and averages no more than 10 ft high.

Even when work is exempt from a building permit, approval may still be needed from the Planning Department, Environmental Health, the Fire Department or Road Encroachment, and signs need Planning Department approval before installation.

Short on time to read all of this?

Get a free quote →

Public Works issues separate permits for encroachment (work in County roads, sidewalks and rights-of-way), drilling and wells, tree removal in unincorporated areas, grading, and stormwater and watercourse work. Septic and other onsite wastewater systems are permitted by Environmental Health’s Onsite Wastewater Systems (OWS) Program.

California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments

Who handles permitting in Alameda County?

County offices for a building project
OfficeHandlesContact
Building Inspection DepartmentBuilding permits and inspections; 399 Elmhurst Street, Room 141, Hayward(510) 670-5440; permitbid@acpwa.org
Public Works AgencyEncroachment, wells, trees, grading, stormwater; 399 Elmhurst Street, Hayward; Monday – Friday 8:30 am – 5:00 pm(510) 670-5480
Planning DepartmentZoning; main office 224 West Winton Avenue, Rm. 111, Hayward; Zoning Desk at the Permit Center, 399 Elmhurst Street, Suite 141, Mon-Thu 8:30am - 4:30pm510.670.5400
Environmental Health OWS ProgramSeptic and onsite wastewater; 1131 Harbor Bay Parkway, Alameda(510) 567-6842; dehowts@acgov.org

Not sure this scope needs a permit?

Get a free quote →

How to get a building permit in Alameda County

1. Clear Planning/Zoning

The published review timelines apply only to projects that already have Planning/Zoning approval.

2. Submit through the portal

All applications, plans and supporting documents go through the County’s online permit portal, acpermit.acgov.org.

3. Allow for review

New single-family dwelling or remodel/addition: 5 business days for intake, 30 for first review, 15 for later reviews. ADU: 5, 20 and 10. Multifamily: 5-10, 40 and 20.

4. Pay fees

Plan review and permit fees under Schedule A.

5. Schedule inspections

Through the portal or on the Inspection Request Line.

A building permit carries a validity period and can expire if work does not start or stalls between inspections; confirm the expiry with the County Building Inspection Department on phased or delayed work. Permit validity in California

Rather talk it over?

Call 1-855-478-4290 →

Alameda County permit costs and fees

From the Building Inspection Department Service Fee Schedule (Schedule A, effective July 1, 2024; filed by the County as an archived document):

  • A $140.00 minimum fee or hourly rate applies to any plan review, permit or inspection service.
  • Building permit: $140.00 for $1.00 to $1,000.00 of valuation; for $10,001.00 to $50,000.00, $381.46 for the first $10,000 plus $8.88 for each additional $1,000.00.
  • Building plan review: 80% of the building permit fee, $140.00 minimum. Permit processing fee: $20.00 per single permit, $30.00 per combo permit.
  • Residential solar or other renewable energy system under 35 Kva with no plan review: $280.00 for the first system, $140.00 for each additional one.
  • Re-inspections: $140.00 per hour; inspections outside normal business hours: $210.00 per hour, two hours minimum.

Inspections in Alameda County

Inspections can be scheduled in the permit portal or phoned in 24 hours a day, seven days a week on the automated Inspection Request Line, (510) 670-5434; requests must be received before 12 A.M. on the day you want the inspection. Have the permit number and the Inspection Type Code from the job card. These phone details come from the County’s archived inspection brochure, so confirm them with the Department. The County also posts a daily inspection route sheet.

Rather not deal with the Alameda County building department?

Get a free quote →

Official Alameda County permitting resources

These are the primary sources behind this guide. Codes, fee schedules and procedures change — confirm the position for your filing date.

Want this handled start to finish?

Get a free quote →

Frequently asked questions

Does window replacement need a permit in unincorporated Alameda County?

Yes. The County says a building permit is always required for window replacement, because of the California Energy Code.

How long does County plan review take for an ADU?

The County publishes 5 business days for intake, 20 for the first review and 10 for later reviews, for projects with Planning/Zoning approval.

Where do I apply?

Through the County’s online permit portal, acpermit.acgov.org, which is also used to schedule inspections and check permit status.

Simplify Alameda County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Inspections are where schedules slip.

Get a free quote →
  • Confirm which office has the parcel and which other agencies must sign off before the building permit
  • Prepare the application and plans in the format the local portal accepts
  • Track plan review, pay fees and schedule inspections against each office’s cut-off

Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Alameda County sooner?

Let Alliance prepare, file, and track your Alameda County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Alameda County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.