How Long Does a Building Permit Take?

There is no national answer. But five states put the deadline in statute with real remedies attached — and they split on where the clock starts.

By Weston SenatoreReviewed by Marshall Chmura, Founder & CEOPublished Updated 13 min read

Get a free quoteSee Our ServicesCall 1-855-478-4290

Which states set a clock

Where the statutory clock starts In completeness states the statutory deadline runs only once the application is complete; the time spent getting there is unclocked and belongs to the applicant. UNCLOCKED · YOURS Getting to complete CLOCK STARTS COMPLETE APPLICATION CLOCKED · THEIRS Statutory review period
You or your expediterThe jurisdiction

The honest answer to how long does a building permit take is that nobody can tell you from the outside. Two projects in the same state, filed the same day, can run months apart depending on which side of a county line they sit on.

Why there is no national average

Permit review is administered locally. A jurisdiction's timeline is a product of its staffing, its backlog, how many departments touch your scope, and whether it runs on a modern portal or on paper. None of that is set nationally and none of it averages usefully.

So a single figure — "four to six weeks" — is describing the middle of an enormous range. It is not wrong so much as unusable, because you cannot plan a subcontractor schedule around a national median.

What is knowable in advance is the law. Several states now set the review clock by statute, with defined deadlines and financial consequences when a jurisdiction misses them. Those are published, checkable, and specific — which makes them a far better planning input than any average.

Where the clock starts, and why states differ

Before the numbers, the feature that changes how you read all of them.

It would be neat to say every statutory clock starts on a complete application. It does not, and the split matters more than the tidy version would.

Clock starts onStates
Completeness
Florida, California, and North Carolina's commercial provisionThe deadline runs only once the jurisdiction has a complete and sufficient package. Time spent getting there is unclocked, and no penalty attaches to it.
Submission
Texas, and North Carolina's general provisionThe deadline runs from the date the application is submitted. Texas § 214.904(b) says "not later than the 45th day after the date an application for a permit is submitted"; N.C. § 160D-1110 says "within 20 business days of submission of the plans."

Completeness is the lever in every state. It just works differently depending on which side of that split you are filing into.

In a completeness state, an incomplete package means the clock never starts. You can burn a month and have no statutory protection for any of it, because as far as the statute is concerned the application has not arrived yet.

In a submission state, the clock starts anyway — but an incomplete package burns that clock rather than pausing it, and it triggers the applicant-fault carve-out that most of these statutes carry. Georgia states it plainly: delay through fault of the applicant does not count toward the days. You get the deadline, you just spend it on your own paperwork and forfeit the remedy at the end.

Either way the conclusion is the same and the mechanism is different, which is worth knowing if you file across state lines.

Statutory deadlines by state

Five states with published deadlines. All figures below are from the statutes themselves, linked in each row.

StateDeadlineIf missed
Florida
Fla. Stat. § 553.792
30 business days, residential and trade permits under 7,500 sq ft
60 business days, larger structures and nonresidential under 25,000 sq ft
12 business days under a master building permit
Permit fee reduced 10% per business day late; 20% per business day after revisions are submitted
Texas
Loc. Gov't Code § 214.904
45 days to grant or deny; or written notice stating why it has not, which then runs 30 days from receipt of that notice Municipality may not collect permit fees and must refund fees already collected
North Carolina
G.S. 160D-1110
G.S. 160D-1110.1
15 business days for residential initial review under the Residential Code
20 business days for other initial review, from submission
45 days for commercial and multifamily with sealed plans, then up to 10 additional days after receiving requested changes
Refund of 10% of the permit application fee per business day late, up to 10 business days.
Elect third-party review and the local government must issue within 3 business days and refund or waive all plan review and permit fees
Georgia
O.C.G.A. § 8-2-26(g)
30 days for plan review
2 business days for inspection after a valid written request
Applicant may retain a private professional provider whether or not the jurisdiction can meet its timeframes, with regulatory fees cut by 50%. With a provider affidavit, no written notice of deficiencies within 30 days means the application is deemed approved as a matter of law
California
Permit Streamlining Act; AB 2234; AB 253
15 days to determine completeness, then 30 to 60 business days depending on project size; 30 business days on residential plan check under AB 253 Applicant gains the right to retain a licensed private professional to perform the plan check

Current as of August 2026. Statutes change, and local ordinances can specify different timeframes than state law — not only stricter ones. California is cited by bill number rather than to a single codified section, and is the one row without a body link to primary text — verify it at California Legislative Information before relying on it. This is general information about administrative process — not legal advice. Verify against the current statute, or consult counsel, before relying on any deadline.

Filing across several of these states? We prepare, file and track permits in all 50 states across seven trades. Look up what your county requires in the permit guides, see what we cover on the Alliance Permitting home page, or tell us your jurisdictions and we will map the clocks.

Florida, in full

Florida has the most developed regime of the five, and it is worth reading properly because it shows what a complete shot clock looks like.

The completeness deadline

The local government has 5 business days to tell you in writing what is needed for the application to be deemed properly completed. If it fails to give that notice on time, the application is automatically deemed properly completed and accepted. That is a real protection, and it only helps an applicant watching the calendar closely enough to notice.

The revision cliff

When the jurisdiction issues written notice that an application fails to satisfy the Florida Building Code or local ordinances, the applicant has 10 business days to submit revisions.

Miss the Florida revision window and the application is not delayed. It is denied.

That is the single most consequential deadline in this article, and almost nobody filing in Florida knows it exists. We cover it alongside the other correction-cycle mechanics in the five most common permit rejection reasons.

The clock runs both ways

Submit revisions inside that window and the agency then has its own 10 business days to approve or deny. If it misses that, the fee reduction doubles to 20 percent per business day. Correct on time and the jurisdiction inherits a deadline with twice the penalty attached.

The exceptions

The fee-reduction remedies fall away in three circumstances: the parties agree in writing to a longer period, the delay is caused by the applicant, or it is attributable to force majeure. Incomplete paperwork does not merely cost time — it forfeits the remedy.

Texas, North Carolina, Georgia, California

Texas

Texas is the bluntest. A municipality has 45 days to grant or deny, or to provide written notice explaining why it has not — which then gives it 30 days from receipt of that notice. If it fails to comply, it may not collect any permit fees associated with the application and must refund any already collected.

Texas HB 14 (2023) also allows an applicant to engage a third party where a city misses a review or inspection — after a 15-day grace period following the statutory deadline, not immediately on the miss.

North Carolina

North Carolina has the strongest remedy of the five, and it is buried in a subsection almost nobody reads.

Start with the base clocks under § 160D-1110, both running from submission. Where a local government chooses to review residential plans under the Residential Code, initial reviews must be performed within 15 business days. Where it does not perform initial review within 20 business days of submission, it refunds 10 percent of the permit application fee for each business day late, capped at 10 business days.

Then § 160D-1110.1, which covers commercial and multifamily applications with plans sealed by a licensed engineer or architect. It sets a 45-day decision period, and three further things in it are worth knowing.

A pre-submittal meeting you can demand. The local government must offer eligible applicants the option to request a pre-submittal meeting, scheduled within five business days of the request, to establish what plans and information it will require. It is free, it is on request, and it is almost entirely unused.

A resubmittal clock. Where the jurisdiction requests additional information or requires a resubmission, it has up to 10 additional days after receiving the changes to issue its decision — directly parallel to Florida's revision window, and the reason correction cycles deserve tracking here as much as anywhere.

And the remedy. If the local government does not issue a decision within the prescribed period, or determines it cannot complete the review, the applicant may elect an independent third-party plan review by a certified licensed engineer or architect. On receipt of that completed review with the required certification, the local government shall issue the applicable building permits within three business days, and shall refund or waive all applicable plan review and permit fees.

Three-day issuance and every plan review and permit fee refunded. That is the sharpest remedy in this article.

Georgia

Georgia sets a clear deadline and the most unusual remedy of the five. Under O.C.G.A. § 8-2-26(g), the applicant may retain a private professional provider at its own expense for plan review or inspection — and that right holds whether or not the county or municipality can meet its own timeframes of 30 days for plan review and 2 business days for inspection after a valid written request. Using a provider also cuts the associated regulatory fees by 50 percent.

Two features are worth knowing beyond the headline number.

They have to tell you up front. When the jurisdiction notifies you that a complete application has been accepted, it must also tell you whether it can actually meet those two timeframes. That converts a scheduling unknown into a disclosure you receive in writing at the start.

And silence can approve the permit. Where a private professional provider affidavit has been submitted, the building official must either issue the permit or give written notice of specific plan deficiencies within the prescribed 30-day period. If no written notice arrives inside that window, the application is deemed approved as a matter of law and the permit issues the next business day.

Two limits sit on that. A written notice of deficiencies tolls the period pending resolution, so silence approves but a comment stops the clock. And that period is counted in days, not business days, while the inspection window is two business days — confirm the count with the jurisdiction before relying on it.

Georgia is the one state on this list where the jurisdiction going quiet works in your favor.

The usual carve-out applies. Delay attributable to a cause outside the jurisdiction's control, or through fault of the applicant, does not count toward the days — the same principle as Florida, and the same reason completeness is the lever.

California

California's Permit Streamlining Act sets completeness and decision deadlines, and AB 2234 applies them to post-entitlement phase permits — 15 days to determine completeness, then 30 to 60 business days depending on project size. AB 253 adds a 30-business-day shot clock on residential plan check, past which the applicant may retain a licensed private professional to perform the plan check instead.

Where the clocks stop

Two gaps matter more than the deadlines themselves.

Florida's enumerated timeframes stop at 25,000 square feet. The statute lists five categories; nonresidential buildings at or above 25,000 square feet appear in none of them. The largest commercial projects in the state — the ones with the most schedule at risk — are the ones the shot clock does not reach.

Most states have no statutory deadline at all. Outside the handful with published clocks, timing is local practice, and local practice is not a commitment. In those jurisdictions the only planning input available is the department's own published target, which is not the same thing as a legal deadline.

Either way the conclusion is the same. Where a clock exists it can be started, burned, or forfeited by the state of your paperwork; where none exists, completeness is still the only lever you have. We cover the general shape of review in how the building permit process works and what commercial work adds in commercial building permits explained.

What you actually control

Total elapsed time breaks into three parts. Only two are yours.

OwnerComponent
You
Getting to a complete applicationUnclocked in the completeness states, and inside a running clock in the submission states — which means it either delays the deadline or consumes it. Either way no penalty attaches to it, and it is frequently the largest single block of elapsed time.
Jurisdiction
The review period itselfGoverned by statute where one exists, by local practice where it does not. We track it either way. Not influenced by anything you or any provider does.
You
How many correction cycles you takeEach one re-enters the queue rather than resuming. In Florida, missing the response window converts a delay into a denial.

The middle row is fixed. The first and third are administrative, and across a portfolio they are usually the larger share of the total. That is the whole case for filing carefully, and it is the only version of "faster permits" anyone can honestly sell. What we do, and the line where it stops, is set out in what permit expediting actually covers.

If your schedule depends on permits across several states, tell us which jurisdictions and we will tell you which clocks apply and where they do not.

Permit timeline FAQ

How long does a building permit take?

There is no national answer, because the deadline is set by state law where one exists and by local practice everywhere else. Several states do set statutory deadlines — Florida generally 30 business days for residential and trade permits under 7,500 sq ft and 60 for larger, Texas 45 days for municipal building permits, Georgia 30 days for plan review, and North Carolina 45 days for commercial and multifamily applications with sealed plans. Those clocks do not all start at the same point: Florida, California and North Carolina's commercial provision run from a complete application, while Texas and North Carolina's general provision run from submission. General information, current as of August 2026, not legal advice.

Does the permit review clock start at submission or at completeness?

It depends on the state. Florida, California and North Carolina's commercial provision run the clock from a complete application. Texas and North Carolina's general provision run it from the date of submission. In a completeness state an incomplete package means the clock never starts; in a submission state it starts anyway but an incomplete package burns it and triggers the applicant-fault carve-out. Completeness is the lever either way.

What happens if a jurisdiction misses the statutory deadline?

It varies by state and the remedy is usually financial. In Florida the permit fee is reduced by 10 percent for each business day late, or 20 percent per business day after revisions are submitted. In Texas the municipality may not collect permit fees and must refund fees already collected. In North Carolina a local government that does not perform its initial review within 20 business days refunds 10 percent of the permit application fee for each business day late, up to 10 business days.

Do these deadlines apply if the delay is my fault?

No. Florida's fee-reduction remedy expressly does not apply where the delay is caused by the applicant, where the parties agree in writing to a longer period, or where the delay is attributable to force majeure. Incomplete paperwork does not just cost time — it forfeits the statutory remedy.

Can I hire a third party if the jurisdiction is slow?

In some states. North Carolina allows third-party plan review for eligible commercial and multifamily applications with sealed plans. Georgia lets the applicant retain a licensed private professional provider for plan review or inspection, whether or not the local government can meet its 30-day plan review and 2-business-day inspection timeframes. Texas HB 14 allows a third party where a city misses a review or inspection. Florida's private provider program under § 553.791 is broader still. Each has its own registration and certification paperwork.

Do statutory deadlines cover every permit?

No, and the gaps matter. Florida's enumerated timeframes stop at nonresidential buildings under 25,000 square feet, so the largest commercial projects fall outside them. Most states have no statutory deadline at all, leaving timing to local practice. Check the statute for your state and confirm local ordinances, which can specify different timeframes.

Weston Senatore — Marketing Lead, Alliance PermittingWeston writes about the administrative side of construction permitting for Alliance Permitting. This article draws on our filing team's day-to-day work across Florida, Texas, Georgia and North Carolina.

Alliance Permitting prepares, files, tracks, and coordinates construction permits in all 50 states for homebuilders, roofing, solar, mechanical, electrical, plumbing, and windows, doors and siding contractors. We do not perform plan review, inspections, engineering, or construction, and we do not advise on what any code edition requires. Browse our county permit guides or request a free quote.