What Is a Notice of Commencement?

It is a lien document, not a permit document. It will not stop your permit from being issued — it will stop your first inspection. Here is what Florida actually requires, and the two ways it goes wrong.

By Weston SenatoreReviewed by Marshall Chmura, Founder & CEOPublished 10 min read

Get a free quoteSee Our ServicesCall 1-855-478-4290

Where the notice actually sits

The notice of commencement in the permit sequence A permit can be issued without a recorded notice of commencement. The notice is required before the first inspection, which is where the job stops if it is missing. STEP 1 PERMIT ISSUES STEP 2 · THE GATE NOC FILED WITH AHJ STEP 3 FIRST INSPECTION MISSING HERE? INSPECTIONS STOP, NOT THE PERMIT RECORDED AT THE CLERK
What the permit office controlsWhat Chapter 713 controls

Most contractors meet the notice of commencement the same way: a permit is in hand, a crew is scheduled, somebody calls for the first inspection, and the jurisdiction says it cannot be scheduled because no NOC is on file.

That sequence confuses people, because it implies the permit office was asleep. It was not. The notice of commencement is not a permit document at all.

If you would rather this never reached your schedule: we prepare, file and track permits across Florida and the other 49 states, and we flag the NOC requirement before the first inspection is booked.
Request a Free Quote

What it actually is

A notice of commencement is a document recorded in the public records of the county where the property sits. It is governed by Fla. Stat. § 713.13, which is part of Chapter 713 — Florida's construction lien law.

It is a lien document that the building department happens to enforce.

That single fact explains most of the confusion around it. The NOC exists to protect people who supply labor and materials, by putting the world on notice that an improvement is underway and that claims of lien may follow. It is recorded with the clerk of court, not the building department. Nobody at the permit counter drafts it, and in most jurisdictions nobody there will write it for you.

What § 713.135 does is bolt that lien-law obligation onto the permitting process, and make the building department the checkpoint. Which is why it lands on your desk.

Worth saying plainly: recording one is not a lien. § 713.13(3) states that recording the notice does not constitute a lien, cloud, or encumbrance on the property. It gives constructive notice that claims of lien may be recorded, and that they may take priority under § 713.07. It is a notice mechanism, not a claim against anybody.

Filing in Florida and unsure where the NOC sits in your sequence? Request a free quote.

It does not stop the permit. It stops the inspection.

This is the part that is almost always stated wrongly, including by people who should know better.

§ 713.135(1)(f) is explicit that the authority issuing the permit may not require recording of the notice of commencement as a condition of applying for, processing, or issuing a building permit. A jurisdiction cannot hold your permit hostage over it.

What it can do — and must do — sits one subsection earlier. Under § 713.135(1)(e)1., where no copy has been filed, the authority or its private provider may not perform or approve subsequent inspections until the applicant files it.

StageBlocked by a missing NOC?Authority
Permit applicationNo — the authority may not require recording as a condition of applying§ 713.135(1)(f)
Permit processingNo — same provision§ 713.135(1)(f)
Permit issuanceNo — same provision§ 713.135(1)(f)
First and later inspectionsYes — subsequent inspections may not be performed or approved until the copy is filed (temporary utility, land-clearing and preliminary site-work inspections are excepted)§ 713.135(1)(e)1., 4.

The practical consequence is a scheduling trap rather than a permitting one. A permit that issues cleanly feels like clearance to mobilize. If no notice was recorded, the job will run right up to the first inspection and stop there, with a crew on site and nothing to do about it for however long recording takes in that county.

That gap is what tracking is for. Tell us your Florida markets and we will watch it on every file.

When one is required

For permitting, the threshold is in § 713.135(1)(e): the applicant must file a copy with the issuing authority before the first inspection where the direct contract is greater than $5,000.

One exception sits in the same subsection. It does not apply to a direct contract to repair or replace an existing heating or air-conditioning system in an amount less than $15,000. Note the shape of that carve-out: it is specific to repair or replacement of an existing system, and it falls away once the contract reaches $15,000.

Florida permit guides Recording practice and turnaround vary by county. We maintain published requirements across Florida. Browse Florida guides

If you have read $2,500 somewhere, check what it refers to. Until 2023 it was the § 713.135 threshold for filing a copy with the building department, and it still appears in a great deal of contractor guidance, county handouts and template packets. That filing threshold is now $5,000. The $2,500 figure does survive elsewhere in the lien law: under § 713.02(5), improvements with a direct contract price of $2,500 or less are exempt from most of it, including the owner's recording duty in § 713.13. This is a good example of why the age of a source matters more than its confidence.

Working from a packet that may be stale? Get a quote and we will file against current requirements.

What goes in it

§ 713.13(1)(a) sets out what the notice must contain. In practice it is an information-gathering exercise more than a drafting one, and the items that hold jobs up are the ones nobody has to hand:

  • A legal description of the property, plus the street address and tax folio number if available. The legal description is the usual sticking point — it is not the mailing address.
  • A general description of the improvement
  • The owner's name and address, their interest in the site, and the name and address of the fee simple titleholder if that is someone else
  • The contractor's name and address
  • The surety's name and address and the bond amount, where there is a payment bond. A copy of the bond is attached when the notice is recorded.
  • The lender's name and address, where there is one
  • A person within Florida designated to receive notices, with their address. The owner may also designate a second person to receive lienors' notices.

Where a contract period runs beyond a year, the notice needs to say so — it states the period it is effective for, which is the mechanism behind the expiration rule below.

Who files it, and who posts it

Three distinct obligations get collapsed into one in conversation, and they belong to different people.

The owner records it. Under § 713.13(1)(a) the notice is recorded before actually commencing the improvement, or before recommencing after a default or abandonment. It takes effect on filing.

The owner posts it at the site. Either a certified copy, or a notarized statement that the notice has been filed for recording with a copy attached. Where a lender records the notice, the lender is not required to post it — posting remains the owner's obligation.

The permit applicant files a copy with the building department. That is the § 713.135 obligation, and the one that gates inspections. A copy can be a certified copy of the recorded notice, a notarized statement with a copy attached, or the clerk's official records information such as the instrument number or book and page.

Contractors assume the whole thing is theirs. Owners assume the contractor handles it. That is how a job arrives at its first inspection with nothing recorded.

The jurisdiction does have a verification role, though a narrow one. Under § 713.135(1)(e)2. it checks that the owner's name and address, the contractor's name, and the property location on the notice match the permit application. Under § 713.135(3), the authority is not liable in any civil action for failing to verify that the copy was filed — so the building department's check is no substitute for your own.

Running work across several Florida counties? Request a free quote or call 1-855-478-4290.

The 90-day trap and the one-year trap

Two timing rules catch people, and they pull in opposite directions.

Recorded too early: the 90-day void

Under § 713.13(2), a notice of commencement is void if the improvement is not actually commenced within 90 days after recording.

That matters because the instinct on a well-run job is to get the paperwork out of the way early. Record the NOC when the permit application goes in, then hit a three-month delay in review, a financing hold or a weather window, and the notice that was filed responsibly is now void. Nobody gets a letter about it.

Running long: the one-year expiration

The notice is effective for one year from recording unless it specifies a different date. The statutory form carries that on its face.

The consequence is in § 713.13(1)(c): payments made by the owner after the notice expires are considered improper payments. On a job that runs past a year — which is routine on commercial work — that is a live exposure for your client, and the fix is an amended notice extending the effective period rather than a quiet hope that nobody checks.

If the contract period is known to exceed a year at the outset, the notice should say so from the start.

Long-running job with an NOC recorded months ago? Worth a look before the next draw.

How it goes wrong on a permit file

Four patterns, in rough order of how often we see them.

Nobody owned it. The most common by far. It is not a building department form, so it does not appear on the submittal checklist in the way a truss drawing does, and it falls between the owner and the contractor.

It was recorded but never filed with the jurisdiction. Recording and filing are two separate acts. A notice sitting correctly in the county records does nothing for your inspection if the copy never reached the building department.

The details do not match the permit. The jurisdiction verifies owner name and address, contractor name and property location against the application. An LLC named slightly differently on the two documents is enough to bounce it.

It went stale. Either the 90-day void or the one-year expiration, usually discovered at a late inspection or at closeout rather than when it happened.

None of these are code problems. They are all coordination problems, which is why they tend to survive a careful plan review and surface at the worst moment.

Current as of November 2026. Thresholds, forms and recording procedures change, and counties differ in how they accept filings. This article describes administrative process and is not legal advice — the notice of commencement sits in lien law, and questions about lien rights, payment exposure or a defective notice belong with a Florida construction attorney rather than with a filing service.

Where we come in

We prepare, file, track and close out permits, and on Florida work that includes treating the notice of commencement as part of the permit file rather than somebody else's paperwork.

In practice: flagging the requirement when the contract value crosses the threshold, confirming who is recording it and when, checking that the recorded details match the permit application before they get verified against it, filing the copy with the issuing authority, and watching the 90-day and one-year dates on jobs that run long.

What we do not do is draft legal documents, give lien advice, determine your lien rights, or act as your attorney. The notice is the owner's to record and your attorney's to advise on. The full scope of what we cover is in what permit expediting actually covers, and the sequence it fits into is in how the building permit process works.

Want the NOC tracked with the rest of the file? Request a free quote and tell us your Florida volume.

Notice of commencement FAQ

What is a notice of commencement?

A recorded document that identifies the property, the improvement, the owner, the contractor, any surety and lender, and a person in Florida designated to receive notices. It is filed in the public records of the county where the property sits, under Fla. Stat. § 713.13. It is a construction lien document rather than a building department document, but the building department enforces it, which is why contractors meet it through permitting.

When is a notice of commencement required in Florida?

Fla. Stat. § 713.135(1)(e) requires the permit applicant to file a copy with the issuing authority before the first inspection where the direct contract is greater than $5,000. One exception sits in the same subsection: it does not apply to a direct contract to repair or replace an existing heating or air-conditioning system in an amount less than $15,000. Older guidance often cites $2,500 as the filing threshold; that was raised to $5,000 in 2023. Separately, § 713.02(5) exempts improvements of $2,500 or less from most of the lien law.

Does a missing notice of commencement stop the permit from being issued?

No, and this is the most common misunderstanding. § 713.135(1)(f) says the authority may not require recording of the notice as a condition of applying for, processing, or issuing the permit. What stops is inspections. Under § 713.135(1)(e)1., the authority or private provider may not perform or approve subsequent inspections until the applicant files the copy. The permit issues; the job cannot be inspected.

Who is responsible for filing the notice of commencement?

The owner records it and the owner posts it at the job site, under Fla. Stat. § 713.13(1)(a). The permit applicant files a copy with the issuing authority. Those are different obligations and contractors frequently assume the whole thing belongs to them, which is how jobs reach the first inspection with nothing recorded.

How long is a notice of commencement good for?

One year from recording unless the notice specifies a different date, under Fla. Stat. § 713.13. Two traps follow. It is void if the improvement is not actually commenced within 90 days after recording, so recording it far ahead of mobilization can kill it. And payments made by the owner after the notice expires are treated as improper payments, which matters on any job that runs past a year.

Does recording a notice of commencement put a lien on the property?

No. Fla. Stat. § 713.13(3) states that recording does not constitute a lien, cloud, or encumbrance on the property. It gives constructive notice that claims of lien may be recorded and may take priority under § 713.07. It is a notice mechanism, not a claim.

Weston Senatore — Marketing Lead, Alliance PermittingWeston writes about the administrative side of construction permitting for Alliance Permitting. This article draws on our filing team's day-to-day work across Florida, Texas, Georgia and North Carolina.

Alliance Permitting prepares, files, tracks, and coordinates construction permits in all 50 states for homebuilders, roofing, solar, mechanical, electrical, plumbing, and windows, doors and siding contractors. We do not perform plan review, inspections, engineering, or construction, and we do not provide legal advice. Browse our Florida permit guides or request a free quote.