Marion County’s list of departments includes a Floodplain Office but no building department: outside its 11 cities and towns, the permit the County Commission requires before new construction, substantial improvement or placing a manufactured home is a Floodplain Development Permit from the county Floodplain Office at 50 Centerview Drive, Fairmont. Inside Fairmont, the county seat (18,035 people in 2025), the City’s Department of Building Inspection and Rental Registration issues building permits at $20 per $1,000 of job cost, with a $60 minimum.
The Commission’s Floodplain Ordinance, enacted on March 27, 2019, makes that permit a condition for any development, new construction, substantial improvement, repair of substantial damage or placement of a structure in the county, not only for land on the flood maps. It names the county GIS Coordinator as Floodplain Administrator; the Floodplain Office now works as a division of the county’s Department of Homeland Security and Emergency Management. The Floodplain Administrator sends each permit to the County Assessor and passes those for new structures to the county’s E-911 addressing coordinator. The Commission itself sits at 200 Jackson Street, Room 403, Fairmont (304-367-5400).
This guide covers unincorporated Marion County and summarizes the 11 incorporated places: the cities of Fairmont, Mannington and Pleasant Valley and the towns of Barrackville, Fairview, Farmington, Grant Town, Monongah, Rivesville, White Hall and Worthington.
The permit depends on the address. Fairmont and Mannington have adopted the State Building Code (2018 editions, in force since August 1, 2022) and issue building permits. Unincorporated land needs the county Floodplain Development Permit, and a new or repaired septic system needs a construction permit from the Marion County Health Department.
What requires a building permit in Marion County?
Unincorporated land has no building permit list; the county’s test is the Floodplain Ordinance, which reaches every structure and also earthwork such as fill and excavation. Each town keeps its own list.
County Floodplain Development Permit
- New houses and new commercial or industrial buildings
- Garages and other detached structures
- Placing or relocating a manufactured home
- Substantial improvement of a building, or repair of substantial damage
- Excavation, fill and other development
- Demolition, which has its own box on the county application
Other permits by location
- Septic systems anywhere in the county: Health Department construction permit
- Fairmont: building permit for additions, roofs, siding, windows, decks over 200 sq ft and pools 2 ft deep or more; zoning permit for fences and small sheds
- Pleasant Valley: development (building) permit for new buildings, additions, fences, decks, porches, sheds, garages and pools
- Pleasant Valley: generally no city permit for work inside the footprint of an existing structure, such as new windows or a roof
Which places have adopted the State Building Code
Fairmont and Mannington have adopted the State Building Code by ordinance, with the 2018 International Building, Residential, Existing Building, Plumbing, Mechanical and Fuel Gas codes, the 2020 National Electrical Code and the 2015 residential energy code, effective August 1, 2022; Mannington’s adopting ordinance (No. 471) passed on July 18, 2022. Pleasant Valley has adopted the 2015 International Property Maintenance Code, and its development permit is for planning and zoning purposes only.
Short on time to read all of this?
Get a free quote →West Virginia lets each county and city adopt the State Building Code or no building code at all; no other building code may be adopted, and floodplain, sewage and fire rules can apply either way. West Virginia rules
Marion County building department: who handles permitting
On unincorporated land the county Floodplain Office reviews and issues the Floodplain Development Permit, and the Marion County Health Department permits septic systems and water wells. Each city and town handles its own permits; the second table shows whom to call in each.
| Detail | Information |
|---|---|
| County Floodplain Office | 50 Centerview Drive, Fairmont, WV 26554: (304) 366-0196 on the county’s Floodplain Office page; the state WV Flood Tool list of floodplain managers (dated 10/24/2025) gives (304) 333-0786 for unincorporated Marion County |
| County Commission | 200 Jackson Street, Room 403 (4th floor, J. Harper Meredith Building), Fairmont; (304) 367-5400; Monday to Friday, 8:30 am to 4:30 pm; meetings on the second and fourth Wednesdays at 10:00 am |
| Septic and wells | Marion County Health Department, 300 2nd Street, Fairmont; (304) 366-3360; Monday to Friday, 8:00 am to 4:00 pm |
| Fairmont building permits | Department of Building Inspection and Rental Registration, 200 Jackson Street, 3rd Floor, Room 305, Fairmont, WV 26554; (304) 366-6211 ext. 303; Monday to Friday, 8:30 am to 4:30 pm |
| Place | Permits | Contact |
|---|---|---|
| Fairmont (city, pop. 18,035) | Building, electrical, plumbing and HVAC permits from the City’s Department of Building Inspection and Rental Registration under the State Building Code; zoning permits for smaller exterior work from Planning & Development | 304-366-6211 ext. 303 |
| Mannington (city, pop. 1,910) | Has adopted the State Building Code, which the City’s Code Enforcement Officer has authority to enforce; building permit fees are set in Code §1741.01, and Article 1731 requires a permit from the City’s Floodplain Administrator for development and new construction | 304-986-2700, the city’s floodplain contact on the state list |
| Pleasant Valley (city, pop. 3,457) | Development (Building) Permit for planning and zoning, with an on-site review by the Zoning/Code Enforcement Officer, whom the city’s floodplain ordinance names as Floodplain Administrator; the state list also shows Marion County support | City office, 2340 Kingmont Road: 304-363-2400; code enforcement 304-594-8999 |
| Barrackville (town, pop. 1,196) | The town’s floodplain ordinance requires a permit from the Mayor, as Floodplain Administrator, for development, new construction, substantial improvement or placing a structure anywhere in town | Town Clerk, 304-366-2954 |
| White Hall (town, pop. 700) | The Code of Ordinances, current through May 2026, has no building permit, zoning or floodplain chapter; its land-usage title holds only roadway specifications | Town office, 118 Tygart Mall Loop: 304-367-1687 |
| Fairview, Farmington, Grant Town and Rivesville (towns) | No town building permit is published; each is listed on the state floodplain managers list with its own floodplain manager, the Mayor in Fairview, Grant Town and Rivesville | Fairview 304-449-1642; Farmington 304-825-6442; Grant Town 304-278-7381; Rivesville 304-278-5301 |
| Monongah and Worthington (towns) | No town building permit is published; the state list shows Marion County supporting both towns’ floodplain programs. A petition to dissolve Worthington’s charter reached the County Commission on August 12, 2026, which took no action at that meeting | Monongah, 430 Bridge Street: 304-534-3320; Worthington 304-287-2238 |
Not sure this scope needs a permit?
Get a free quote →Permit types
Residential permits
For a house outside the towns, the county Floodplain Development Permit Application asks for the owner, the contractor and its WV licence number, the property address or tax map district, map and parcel numbers, the cost of improvement, the type of structure and a description of the work, with one copy of the plans and specifications. A house on a private system also needs the Health Department’s septic construction permit, and the ordinance expects that department’s approval of wells and septic systems as part of the floodplain review. In Pleasant Valley a new single-family or manufactured home needs the city’s development permit, and the city wants Health Department approval first when the lot uses a well or septic system.
Building or remodeling a home here? Alliance handles home building permits, so the crew isn't waiting on the counter.
Commercial permits
Commercial and industrial projects outside the towns use the same county application, marked commercial/industrial. In a special flood hazard area, a non-residential building must either be elevated or be flood-proofed to 3 feet above the base flood elevation, and the application has to show the elevations, certified by a registered professional engineer or licensed professional surveyor.
For tenant improvements and new commercial builds, Alliance handles commercial permit filing through issuance. More on this: commercial building permits explained.
What else goes in the county permit file
Applications are filed in writing, in duplicate, on the Commission’s forms. Before issuing a permit the Floodplain Administrator needs proof that each contractor holds a state licence, or an affidavit, filed with the County Clerk, that the applicant is not subject to licensing. The signed construction contract and any addendum must be shown to the Floodplain Administrator within 14 business days of signing, or the permit is void; when no licensed contractor is involved, or the work is worth less than $10,000 in materials and labor, a short written description and the estimated value are enough. Land partly or wholly in a special flood hazard area that is to be subdivided or developed needs a detailed site plan with elevation data first.
Rather talk it over?
Call 1-855-478-4290 →West Virginia licenses contractors at state level through the Contractor Licensing Board, run by the Division of Labor, valid statewide. West Virginia rules
Marion County permit costs and fees
The county ordinance leaves its floodplain permit fee to the Floodplain Administrator and, for work in a special flood hazard area, to a value-based schedule the Commission approves, so ask the Floodplain Office for the current amount. Engineering, surveying or other services needed to review a project are billed to the applicant, and a deposit may be required. City and health department fees are fixed amounts:
| Item | Fee or rule |
|---|---|
| County floodplain permit | Set by the Floodplain Administrator and payable to the Marion County Commission; an additional fee based on estimated construction value for work in a special flood hazard area; fees doubled when work starts before the permit, and tripled for each later occurrence by the same person |
| Fairmont building permit | $20 per $1,000 of job cost or part of $1,000 (2% of the job), $60 minimum; electrical $100 minimum |
| Mannington building permit | $20 minimum; $0 to $100,000: $7 per thousand or any part of $1,000; over $100,000: $10 per thousand or any part of $1,000 (Code §1741.01) |
| Pleasant Valley development permit | New single-family home (manufactured homes included) $100; new multi-family building $200 on the attached fee list ($100 on the form’s summary page); residential addition or accessory project such as a fence, deck, shed, garage or pool $50; commercial project up to $500,000 $200, plus $0.0004 for each dollar above $500,000 |
| Septic and well permits | Health Department: septic tank installation $235; sewage system modification $205; water well permit $140 |
Pleasant Valley’s own example: a $1,500,000 commercial project pays $200 plus $400, or $600. Its fees are non-refundable, due with the application and paid to the City of Pleasant Valley by check.
Rather not deal with the Marion County building department?
Get a free quote →Trade permits and who may pull them
Where trade permits are issued
- Fairmont: electrical, plumbing, mechanical and air conditioning permits from Building Inspection, at $20 per $1,000 of work ($100 minimum for electrical, $60 for the others)
- Fairmont: electrical and HVAC work can go on the Building & Zoning Permit Application
- Mannington: its adopted code includes the plumbing, mechanical and fuel gas codes and the 2020 National Electrical Code
On county land
- The county floodplain permit lists every contractor’s WV licence number
- In a special flood hazard area, a house’s lowest floor, ductwork and utilities must sit 3 feet above the base flood elevation
- Septic systems are installed by a certified installer under a Health Department permit
Trade work is permitted separately where the jurisdiction enforces the code and done by state-licensed contractors. West Virginia rules
How to apply for a Marion County building permit
Inside a city or town limit, that place’s permit applies. Look the parcel up on the county parcel viewer linked from the Floodplain Office page; the county form asks for its tax map district, map and parcel numbers.
Look the site up on the WV Flood Tool. In a special flood hazard area, plan for certified elevations and drawings showing the structure and utilities 3 feet above the base flood elevation.
A certified installer runs the percolation test and recommends a system; the owner or installer files the on-site sewage application with the Health Department, whose sanitarian visits the site before issuing a construction permit.
Submit the Floodplain Development Permit Application in duplicate with one set of plans and specifications, the cost of improvement and the contractor’s licence number or an exemption affidavit.
Pay the fee to the Marion County Commission and display the permit placard on the property while work is under way.
The permit expires if work has not begun within 180 days, and all work must be finished within 18 months unless the Floodplain Administrator grants a written extension.
Review, corrections and what actually causes delay
The ordinance gives the Floodplain Administrator up to 90 days from submission to review an application. Written objections from others are weighed before a decision, and the Administrator may hold a public meeting on them, announced on a County Commission agenda at least 10 calendar days ahead. No changes may be made to an issued permit or its plans without the Administrator’s written consent.
Inspections in Marion County
The Floodplain Administrator, or other authorized county, state or federal officials, may inspect a permitted site during construction, and work that departs from the application brings a stop-work order and revocation of the permit. In a special flood hazard area no one may occupy a new or altered building, and no utility may make a permanent connection, until the Floodplain Administrator issues a Certificate of Compliance based on that inspection and any finished-construction elevation certificate. For septic systems, the certified installer must call the Health Department for a final inspection before the system is covered. Inside Fairmont, inspections are booked with Building Inspection on 304-366-6211 ext. 303, and a repeat inspection after a failure costs $30.
Want this handled start to finish?
Get a free quote →Marion County permit search and official resources
- City of Fairmont — code enforcement, permitting and rental registration
- Fairmont Building Inspection & Rental Registration — permit fees, office and hours
- Marion County Floodplain Office — contacts, flood maps, parcel viewer and forms
- Marion County Floodplain Ordinance (enacted March 27, 2019)
- Marion County Floodplain Development Permit Application
- Marion County Health Department: sewage and septic systems
- Marion County Health Department environmental fees
- Mannington Codified Ordinances, Article 1711: State Building Code
- Mannington Codified Ordinances §1741.01: building permit fees
- City of Pleasant Valley forms, incl. the Development (Building) Permit Application
- Town of White Hall Code of Ordinances
- WV Flood Tool list of county and town floodplain managers
- West Virginia State Fire Marshal — the State Building Code, adoption notifications and code official certification
- West Virginia Division of Labor — runs licensing for the Contractor Licensing Board, plus plumber and HVAC licences
- West Virginia Code 15A-11-5 — the statute on the State Building Code, local adoption and enforcement, and the priority of stricter local rules
Inspections are where schedules slip.
Get a free quote →Frequently asked questions
Does Marion County issue building permits?
Not building code permits. Outside the cities and towns the county issues a Floodplain Development Permit, which is required for any new construction, substantial improvement or placement of a structure, including a manufactured home, wherever the land lies.
Who issues permits in Fairmont?
The city’s Department of Building Inspection and Rental Registration, on the 3rd floor (Room 305) at 200 Jackson Street (304-366-6211 ext. 303), which issues building permits, enforces the codes the city has adopted and administers rental registration.
How long does the county take to review a permit?
The Floodplain Ordinance allows up to 90 days from the date the application is submitted. Once issued, the permit expires if work has not started within 180 days, and the work must be complete within 18 months unless an extension is granted in writing.
Who issues septic permits in Marion County?
The Marion County Health Department, 300 2nd Street, Fairmont (304-366-3360). A certified installer evaluates the site, the owner or installer files the application, a sanitarian approves the site and issues the construction permit, and the installer calls for a final inspection before the system is covered. A septic tank installation permit costs $235.
Do I need a permit for a fence or deck in Pleasant Valley?
Yes. The city’s development (building) permit covers residential additions and accessory projects such as fences, decks, porches, sheds and pools, for a $50 fee. Work inside the footprint of an existing structure, such as new windows or a roof, generally needs no city permit.
How much is a building permit in Mannington?
Section 1741.01 of the city code sets a $20 minimum, $7 per thousand dollars (or any part of $1,000) from $0 to $100,000, and $10 per thousand (or any part of $1,000) over $100,000.
Which Marion County places enforce the State Building Code?
Fairmont and Mannington have adopted it by ordinance, with the 2018 International codes and the 2020 National Electrical Code in force since August 1, 2022.
Simplify Marion County permitting with Alliance Permitting
Marion County's building code enforcement stops at the Fairmont and Mannington city lines, and its risks run underneath. We establish the authority before design and read the mining record before siting.
Ready to break ground in Marion County sooner?
Send us the scope and the parcel. We confirm the review path with Fairmont code enforcement and the Marion County authorities, assemble the submittal, file it, and track it through issuance — corrections included.
More West Virginia permitting guides
More West Virginia permitting guides
Monongalia County
Read guide →Harrison County
Read guide →Kanawha County
Read guide →Marshall County Building Permit Guide
Read guide →Martinsburg Building Permit Guide
Read guide →Mason County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Marion County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.